Case Study - Background Flashcards

(10 cards)

1
Q

When were T&T appointed?

A
  • Appointed toward the end of October
  • There was no crossover between T&T and the previous consultant.
  • 1 week after them leaving
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What caused a delay in the transition?

A
  • Onboarding/vetting
  • Bringing up to speed
  • Reviews with designers/PM
  • Stage 3 cost plan
  • Validation
  • Review of solutions
  • Overall, about 2-3 weeks delay (including 1 week float)

Some float was added which saved a week.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What was driving the £850k overspend?

A

Key against the budget which was set by the previous consultant.

  • Additional scope added after S2(Mail Room/Corridor Works)
  • Increase in Catering Units (MEP impact)
  • Increase in Specialist Joinery

This included higher specifications in the Mail Room and Toilets.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What was the focus of the Reconciliation against the previous?

A
  • Side by side cost plan (focused on elemental packages)
  • Checked rates/quantities allowances - Key differences
  • Any differences checked with designers/checked measures.

Focused on packages where key differences were noted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What findings were highlighted following the Reconciliation?

A
  • Higher costs on MEP, Specialist Joinery, Finishes.
  • No clear methodology for OOH Allowances in their pricing.
  • OOH to (Strip Out/MEP/Finishes/Partitions)
  • Applied 30% for OOH works uplift to areas after benchmarking

Discussed with Design Team/PM packages likely to be done OOH.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Tallk me through the benchmarking you did for the project?

A

Key to focus on benchmarking the high cost elements (£/m2)
* Services £/m2
* Finishes £/m2
* Joinery £/m2
* Toilets £/m2

Used 3 projects in the same location of similar works to benchmark against.

Highlighted any key observations:
* Elements done OOHs
* Scope differences (more tiles/higher spec)
* Toilets higher spec

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What findings were highlighted following the Benchmark?

A
  • Toilets were high (Vanity Units Corian/Quartz Top)
  • Services high but justified by the level Catering involved (this was within 10%)
  • Finishes were high end
  • Most variances were in 5%-10% range

This was reflective of the market and deemed valid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What was the Contingency and how was it calculated?

A

5% contingency as an overall risk pot

This was advised by the client due to the project forecasting as overbudget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

You talk about high spec? What would you expect to see in a Low - Mid Spec?

A

Basic level of finishes:
* Carpet/Vinyl Flooring
* Plasterboard/Metal Ceilings
* Painted wall finishes - Timber panels for a mid range
* Basic tables/chairs - Not bespoke joinery.
* Laminate Vanity Units - Corian - Natural Stone (Quartz)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What other Benchmarking could you have done outside of £/m2

A

Cost per Functional Area (toilets/tea room/games room)
Cost per floor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly