When were T&T appointed?
What caused a delay in the transition?
Some float was added which saved a week.
What was driving the £850k overspend?
Key against the budget which was set by the previous consultant.
This included higher specifications in the Mail Room and Toilets.
What was the focus of the Reconciliation against the previous?
Focused on packages where key differences were noted.
What findings were highlighted following the Reconciliation?
Discussed with Design Team/PM packages likely to be done OOH.
Tallk me through the benchmarking you did for the project?
Key to focus on benchmarking the high cost elements (£/m2)
* Services £/m2
* Finishes £/m2
* Joinery £/m2
* Toilets £/m2
Used 3 projects in the same location of similar works to benchmark against.
Highlighted any key observations:
* Elements done OOHs
* Scope differences (more tiles/higher spec)
* Toilets higher spec
What findings were highlighted following the Benchmark?
This was reflective of the market and deemed valid.
What was the Contingency and how was it calculated?
5% contingency as an overall risk pot
This was advised by the client due to the project forecasting as overbudget.
You talk about high spec? What would you expect to see in a Low - Mid Spec?
Basic level of finishes:
* Carpet/Vinyl Flooring
* Plasterboard/Metal Ceilings
* Painted wall finishes - Timber panels for a mid range
* Basic tables/chairs - Not bespoke joinery.
* Laminate Vanity Units - Corian - Natural Stone (Quartz)
What other Benchmarking could you have done outside of £/m2
Cost per Functional Area (toilets/tea room/games room)
Cost per floor