Case Study Flashcards
(80 cards)
What form of condition survey did you produce initially relating to CIF?
Condition Report
- Level 1 Survey
- RAG system / CDC Condition Ratings
D1 - A4
Were there any other issues other than the windows?
- Roof felt was exhibiting some defects
- However at the time the windows and piers were priority due to immediate risk for health and safety
- Some spalled brickwork
- Polycarbonate roof at GF level was in poor condition
- Inner courtyard windows were exhibiting some defects
- Internal plaster finishes
- Penetrating damp visible to some areas
- Poor flooring finishes
- Electrical lighting faults
Given the buildings age, what sort of common defects / issues would you anticipated being present?
- Asbestos
- RAAC
- Damp / Condensation
- External brickwork and Mortar
- Roofing defects
- Concrete defects
- Cavity wall tie failure
- Structual issues / Subsidence
- Electrical Systems
- Fire doors
- Fire detection layout
Explain the competitive tender process? How were SDC appointed?
- Produced the design and specification
- Selective contractor competitive tender process
- 4 Contractors were invited to tender for these works
- SDC were appointed due to being the most cost effective as well as a compliant good quality return
- Following due diligence checks on financial accounts and insurance cover and case studies, analysis of tender return contract sum analysis their return was found to be free of errors and within the expected costs
- Usually an annual turnover of 3-4 times the project amount is a good principle to use for financial health status aligning for the project
- Undertook pre qualification queries and was satisfied with the responses provided by SDC
- Agreed a start date of 17th July with a 9 week programme overall for all 3 sections
Did you use a letter of intent / client PO or contract to appoint them?
- Contract was prepared within 2 weeks revisit stage
How did you select the JCT Intermediate WCD 2016?
- Works were of medium scale complexity and cost
- Subcontracted specialist works for concrete repairs
- Design element for fabrication of windows as per specification
- Works required to be split into sections, 3 weeks per section
Programme - How did you calculate the construction phase timeframes?
- Made sensible assumptions based off previous experience and historical data within the team
- Collaboration with contractors to understand capabilities
How did you structure your detailed report?
- Site address and contact details
- Purpose of the survey
- Survey conditions, weather time etc
- Limitations / access
- Photographs and condition ratings
- Conclusions / recommendations
What were the high priority works required?
- Windows to Sports Halls
- Brick pier facade rectifications
- Windows to classrooms and kitchen
- Roof
- Concrete degradation to lintels
- Windows, concrete lintels, and piers were deemed as highest priority due to immediate health and safety risk
How did you assess the windows to be the most urgent?
- Immediate replacement required due to health and safety concerns over the opening of windows and visible deterioration to windows and concrete lintels spalling
How was the budget calculated as sufficient?
- Competitive tender exercise undertaken to form the cost document to prove cost certainty submitted to the DfE
- Professional fees and investigative costs pre calculated
- Provisional sum allowed
- Contingency sum allowed for any unforeseen works
What are the typical defects of a 1960s school block?
- Windows and doors from ageing and poor quality materials
- Roof defects due to ageing and deterioration
- Damp and condensation issues due to failing external elements and poor ventilation
- Cracking and damage to walls from subsidence or settlement
- Electrical faults due to age of systems
- Asbestos containing materials
- Possibility of RAAC
- Internal finishes and material degradation from damp
- Fire door issues
- Fire alarm and detection not providing adequate coverage
- External walls and bricks and mortar degradation
What type of defects would you expect to find in a cavity wall construction?
Cavity wall tie failure
- Corrosion to steel wall ties
- Leads to structural movement of walls
- Leads to degradation of mortars through expansion of ties, leading to further damage
Bootleg lintel defects
- Lintels rotate due to differential loads applied to inner skin and outer skin brick and block
- Lintel degradation due to frost damage and carbonation
Lack of or aged insulation
Condensation
How did you determine a steel and concrete frame?
- Sports hall ceilings were exposed and concrete and steel columns could be seen with steel cross beams for the roof structure
What are the typical defects of steel and concrete frames?
Concrete defects
- Carbonation
- Concrete spalling
- Surface delamination
- Poor worksmanship and concrete mix at time of installation for concrete cast in-situ
Steel
- Corrosion
- Welding defects
- Movement due to subsidence
- Design flaws
What was the roof finish? Was there any defects?
- Bitumen felt roof with tapered insulation
- Exhibiting some defects
- Blistering
- Moss growth
- Blockage of drains
What were the defects you found in the steel windows?
- Unsafe opening widths with no restriction fitted
- Excessive condensation build up due to poor thermal properties and lack of ventilation
- Corroded frames
- Broken glass panes
- Water penetration through edges of windows with no insulation present causing degradation to internal finishes
- Paint finish flaking and peeling
- Rust staining on glass
- Gaps around window frames
What are the risks of reinforced concrete lintels?
- Carbonation leading to alkinity in concrete protection to steels lowering and breaking away
- Steel reinforcement corrosion
- Concrete spalling due to frost damage and multiple freeze thaw cycles
- Exposed to weathering and deterioration
- Increased risk of structural failure over time
- Structural loads and improper design
- Insufficient design methods such as boot lintels
- Expansion and contraction
What do you mean by inception to completion?
- Entire lifecycle of the project from initiation and initial survey to completion of the project
What are typical defects with windows and doors?
- Deteriorated sealants
- Insufficient opening and closing
- Defective hinges and mechanisms
- Corrosion to steels lowering frames
- Insufficient thermal performance
- Insufficient ventilation
- Excessive gaps to surrounds
- Condensation
What were the concrete repairs specified?
- Brush off existing steel corrosion and concrete and prepare surface
- Apply zinc modified primer
- To provide protection for steel, acts as a bonding agent for the concrete, can be sprayed or manually applied - Repair mortars
- To build back up to original profile and restore structural integrity - Pore filler and levelling mortar
- Concrete protection
How were the concrete repairs specified?
- Refer to BS8500 for concrete specifications
- Undertook research on suitable concrete repairs
- Undertake CPDs on appropriate concrete repairs systems
- Checked sika specifications on website technical details
- Used tools such as NBS source
What is the minimum coverage for concrete?
- Minimum concrete coverage is 40mm
- 75mm for concrete in direct contact with soils or in marine environments
What specialist surveys did you coordinate?
Concrete hammer test
- Tool used to rebound a spring to measure compressive strength of the concrete
R&D survey
- Identify any asbestos containing materials associated with the works