Contract Administration (L3) Flashcards
(116 cards)
What are the main CA duties?
- Responsible for managing and overseeing the terms of the construction contract
- Contractual Control and Compliance
- Understanding the contract, and rights and obligations of parties
- Ensure compliance and adherence to contract terms - Issuing Instructions
- Instructions to the contractor
- Record keeping, detailed record of all instructions given - Monitoring Progress
- Regular site visits, monitor progress , monitor progress of works against schedule and identify issues early on
- Progress reports - Valuations and Certificates
- Valuation of works before issuing certificates
- Issuing interim payment certificates at agreed stages
- Final account, agree and settle - Variations and Changes
- Manage variations
- Cost control - Extensions of Time
- Assessing delays
- Granting EoT if applicable - Dispute Resolution
- Addressing disputes and resolve between parties
- Determining contractual breaches - Practical Completion
- Inspection for completion
- Issuing Practical Completion certificate - Defects and Rectification
- Snagging inspection before the completion and at End of Defects
- End of defects inspection
- Certificate of making good - Health and Safety
- Compliance, ensure contractor adheres to health and safety regulations
- Site safety audits, conduct or oversee - Communication and Coordination
- Liaison between parties and key communication link between stakeholders
- Coordination of consultants to ensure smooth workflow
What is Building Regulations Part T? What does it cover?
What skills might a CA have?
- Contractual knowledge
- Communication and negotiation
- Technical expertise, construction knowledge, and building practices
- Attention to detail
- Organisation skills
- Financial management, accounting and cost control
- IT and digital skills
- Health and safety awareness
- Ethical and professional standards
What are the key differences in provisions between MW and Intermediate JCT?
- Scope and Complexity
Minor Works
- Small simple projects, requires limited design input
- Only includes provision for the employer to supply basic design
Intermediate
- More complex medium scaled projects which allows for some design responsibility on contractor
- Allows for use of specialist works and sub-contractors - Design Responsibility
Minor Works
- Usually the responsibility of the client to provide a basic design with little input from the contractor
Intermediate
- Provisions for contractors design portion of works if required
- Subcontractor and Specialist Work
Minor Works
- Works are generally undertaken by one main contractor with no provision for nominated subcontractors or specialists
Intermediate
- Detailed provisions for specialist sub-contractor works
- Allows for nominated subcontractors
- Contract Administration and Site Procedures
Minor Works
- Basic powers to issue instructions and manage payments
Intermediate
- Additional powers to issue instructions
- More detailed provisions for coordination
- Variations and Changes
Minor Works
- Simple provisions for variation to works
- Limited provisions for complex changes to scope or design
Intermediate
- Comprehensive provisions for variations and change orders
- Payment Provisions
Minor Works
- Simple payment mechanism, fewer payments and certificates
- Less frequent payment cycles
Intermediate
- More detailed payment provisions
- Regular valuation dates
- Procedures for calculating payments
- Health and Safety / CDM Regulations
Minor Works
- Simpler management needs
Intermediate
- More detailed, including compliance with CDM regulations
- Contractor may be required to coordinate CDM responsibilities
- Insurance and Liability
Minor Works
- Basic provisions on insurance and public liability
- Contractor required to provide all insurance
- Less complex risk allocation
Intermediate
- More detailed insurance provisions
- Handling risk, clearer allocation of risk between the employer and and contractor, in particular CDP
- Subcontractor works and specialists
- Programme and delay
Minor Works
- Basic, carrying out works by set completion date
Intermediate
- Milestone dates
- Sectional completion
- Extension of times due to variations, weather etc
- Termination
Minor Works
- Fewer grounds for terminating
Intermediate
- More detailed
- Employers right to complete works using other contractors
What is the standard format of JCT Contracts?
- Agreement
- Employer and contractor details, company number, address
- Date of the agreement - Recitals
- Description of works, address
- Design portion
- Reference to specifications and pricing schedule / BoQ - Articles
- Contract Sum
- CA, Architect, QS, PD, PC
- Adjudication, Arbitration, Legal Proceedings - Contract Particulars
- Nominees
- Base Date
- Completion Date
- Liquidated Damages
- Defect Rectification Period
- Interim Payments
- Retention
- Insurance
- Adjudication and Arbitration Nominated Bodies - Attestation
- Execution
- Signed by Employer / Contractor - Conditions
- Definitions and Interpretation
- Carrying out the Works
- Control of the Works
- Payment
- Variations
- Injury Damage and Insurance
- Assignment, Performance Bonds and Guarantees and Collateral Warranties - Schedules
What do you know about NEC?
- New Engineering Contract
- Used for larger infrastructure and engineering projects
- Easy to understand with less contractual jargon
- Promotes collaboration, flexibility and project management
- Differs by promoting proactive management of risk and encouraging corporation between parties to achieve project objectives
- Project manager undertakes the contract administration role
Key Features:
- Collaborative and Proactive Approach
- Early identification of risks - Flexibility
- Allows it to be tailored to various types of project - Clear Risk Allocation
- Provision for unforeseen circumstances and changes - Time and Cost Management
- Clear guidelines for managing time and cost - Dispute Resolution
Mechanisms for early dispute resolution, adjudication
What are the timelines for Interim Payment under JCT?
- Due date for payment is 7 days after after the valuation date
- CA must issue interim payment certificate following valuation no later than 5 days after the due date
- Final date for payment is 14 days after the due date
- Final date for payment is 21 days after the Interim Valuation date
- Pay Less Notice to be issued at least 5 days before the final date for payment if applicable
What are the impacts of issuing PC?
- CA considers works to be substantially complete
- Release of retention
- Beginning of End of Defects Liability Period
- Employer no longer entitled for LADs from the date the certificate is issued
- Insurances of the works passed back to the employer
- Triggers final account and payment
Shipston Safeguarding - Why did you use an intermediate?
- Medium scaled works with a contract value of around £280k, including electrical and design works by sub contractors
- Has provisions for specialist sub-contractor works for access control
- Contractors design element for Electrical works to align with current school network
- Allowed for works to be split into sections for main entrance vehicle and pedestrian gates to be completed during the summer holidays, and remainder of the works around the perimeter during term time
How did you go about reviewing the CDPs?
- Submitted proposals with tender returns
- Reviewed against drawings and employers requirements for the CPD works to ensure that the proposals adhered to the requirements
- Cross referenced against industry standards, and legal and regulatory compliance
- Reviewed with client IT team to ensure compatibility with existing hardware
- Evaluate design for constructability and practicality
- Conduct design review and provide comments / approval
What things do you have on your agenda at progress meetings?
- Introductions / Apologies
- Previous Meeting Minutes
- Contractors Progress Report
- Health and Safety
- Contract Administrator Matters
- Statutory Approvals
- Key Risks
- RFIs
- Client Matters
- Any Other Business
- Date and Time of Next Meeting
- Meeting Schedule
Shipston - What were the timelines for final payment?
- The due date for the final payment, 28 days after the EoD, or 28 days after the certificate of making good is issued
Connexus - Why did you advise a Minor Works?
- Works were simple in nature
- Low in value
- Relatively quick programme of 3 weeks with no provision required for interim payments, with one payment for the works
- Approximately £50k in value
- All works being complete by the main contractor
- Flat refurbishment and kitchen installation
- No need for extensive design input
EIA Landscaping - What things were considerations when choosing the contract?
- The value of works was approximately £600k across the playground areas
- Required specialist surface and ground work contractors, as well as electrical engineer works for access control features
- Required works to be completed with different start and completion dates, sectional completion provision
- Works were not simple in nature and did require multiple sub-contractors to undertake works
- Overall duration of project was 12 weeks
- Payments were made on interim valuation dates
EIA Landscaping - How did you advise the client regarding the other impacts of choosing Intermediate, over other JCT options?
- Due to it being a traditional procurement route, the use of D&B was not required as the client had appointed Ridge to undertake the design and specification process
- The works were of medium scale, and complexity which Minor Works would not have been sufficient for, also the client required sectional completion with playground areas and football pitch works split to alleviate risk on start of term
- Intermediate allows for specialist sub contractor works such as ground workers, soft play installers, football pitch installers, M&E engineers for access control features
Hal Green - Why did you advise a D&B?
- This was decided by previous surveyor on the project. I was assigned to the project during the construction phase
- No need for extensive pre-design by the client
- Faster project delivery, to aid quicker start on site for summer holiday works
- Less risk for the client in terms of project timescales and cost control as this would be the contractors responsibility
- Provided employers requirements for the tender pack
Hall Green - How would your advice have changed if the relevant event had occurred?
- I would have undertaken my assessment of the extension of time application
- Review the timeframe in which the delays were incurred and cross referenced with my site inspection report for that period
- Understood the impact along the critical path of works and ascertain whether the claim for delay is reasonable
- Check weather verified weather channels such as Met Office for historic weather data in the area to determine exceptionally adverse weather conditions, I.e once in 10 years
- Contractor submitted 5 days during July due to rain
- I would have issued the extension of time, stating the new contract completion date and duration of extension onto the contract following approval from the client
Hall Green - What advice would you give to your client about LADs?
- Must be a genuine pre estimate of potential losses incurred should the project not be completed within the contracted completion date
- Advised my client of their right to claim LADs,
- Client decided not to proceed with LADs and contractor allocated extra resource and utilised weekend working to complete works promptly
If they had decided to proceed with LADs, how does that actually work in practice? What steps would you need to take?
- CA would need to issue a certificate of non completion
- Employer would need to notify the contractor before the date of final payment that he may withhold or deduct liquidated damages
- Notice would need to state the period between the completion date and the date of practical completion of the works or that section
- Deduct or withhold liquidated damages at the rate stated in contract particulars
- Document the delay, review the contractors response, assess the contractors justification of the delay, seek to use mediation to agree position should a dispute arise, if it does, enforce the claim, either deduction or raise a PO, in the case of non-payment, the client may need to pursue litigation or enforcement through court proceedings, in this case the client should seek legal advise
What forms of contract are you aware of?
- JCT contracts, I have worked with
- NEC contracts, I am aware of but have no experience with
- FIDIC, internationally recognised contracts for large scale infrastructure projects. FIDIC Red Book, Yellow Book, Silver Book, Green Book
What are the main differences between JCT MW/Intermediate/D&B?
Minors Works
- Used for smaller scale projects, simple in nature
- Usually one main contractor undertaking the works
- Relatively quick programme, usually one payment at the end of the works
- Generally lower in value compared to other contracts
- Specialist or named sub contractors or specialist works not required
- Limited design input required
- Usually employer provides design and specification of the works to be implemented by the contractor
Intermediate
- For medium scaled works more substantial than MW
- Lengthier programme than MW
- More detailed provisions for interim payments
- Provisions for design input from contractor through CDPs
- Provisions for splitting the works into sections
- More complex works than MW, and provisions for use of specialist sub contractors
- Higher in value than MW
- Provisions for employer to appoint a quality inspector, I.e Clerk of Works
Design and Build
- Contractor responsible for undertaking the design and construction process
- Design risk is removed for the employer
- Employers requirements set out the requirements to be met by the contractor
- Ideal for clients with less construction knowledge
- Allows for quicker construction and design stage
What are the implications of sectional completion a contract? E.g insurances, access, valuation etc?
- Sectional completion will in effect sign off completion of that section of works
- The final payment and release of retention relating to the specific section will be released
- Defects liability period on this section begins
- Considered works are substantially complete and employer takes back possession
- Insurances related to this section back to employers responsibility
- Safe and clear access to be maintained by both the contractor to the respective completed areas and sections still in progress
- Valuation should be split so to release retention for sections completed and withhold for sections which are not complete
Explain your role as a CA under a Traditional Minor Works contract?
- Manage the contract and ensure parties adhere to their contractual obligations
- Have a clear understanding of the contract and mechanisms in the contract
- Facilitate communications between stakeholders holders
- Negotiate and provide solutions in the case of any disagreements
- Undertake inspections and ensure the works are being constructed as per the contract
- Issue instructions and payment certificates following valuations as necessary
- Agree final account
- Issue completion / non completion certificates
- Cost control and keeping clear records of all instructions and key decisions
- Facilitate end of defects and issue certificate of making good
What are LADs, when do they apply and how are they calculated?
- Liquidated ascertained damages
- Apply when the works are not complete within the contract completion where the contractor is not entitled to an extension of time and a certificate of non completion has been issued, the employer would also be required to issue a notice to the contractor at least 5 days prior to the final date of payment outlining their intention to withhold or deduct liquidated damages for the period in line with the contract
- Needs to be calculated by the employer and must be a genuine pre estimate of the potential losses incurred if the project is not completed within the contracted completion date