Contract Practice (L2) Flashcards
(56 cards)
What are the minimum requirements for executing a legally binding contract?
- Offer and Acceptance
- Offer from the builder, acceptance from the employer - Consideration
- Something of value, I.e services - Intention to Enter a Legally Binding Contract
- Legality: The contract must comply with existing laws
- Capacity: Legal capacity, I.e must be of age
- Certainty: Unambiguous terms must be agreed
What insurances do contractors usually have?
- Professional Indemnity Insurance
- Public Liability Insurance
- Employers Liability Insurance
- Plant Insurance, Motor Insurance, Contractors All Risk Insurance
What’s retention? How does this work?
- Moneys held by the employer during contract works and after completion until the end of defects in relation to the contracted works
- As per the contract
- To provide assurances for progress, quality and defects
How did you go about determining an LADs value?
- This is to be done by the employer
- Must be a genuine pre estimate of the potential losses they would incur, should the works not be completed within the contracted completion date
How do you deal with variations?
- Understand the requirement for the change and check the contract and specification to confirm if it is a change
- Review details and submit a change order request to the contractor to advise on cost and programme implications of the change
- Review contractors submission of cost and programme should the variation be instructed
- Review the amended works in relation to the critical path of the programme and review costs against historical data and tools such as BCIS and SPONNE
- Verify value for money and advise the client accordingly
- Act promptly and within the contractors stated date to avoid any delays
- Raise contract instruction as necessary stating details of the change
- Clearly document and keep records of approvals and decisions
What would you typically include in a contract induction?
- Description of the change and reference to any correspondence and agreements
- Date of the variation
- Reference to the project and contract
- Contract sum
- Sum of the variation
- Sum of variations to date
- Adjusted contract sum
- Signature
JCT Digital Service - What is this? How does it work?
- Online platform used for creating JCT contracts
- Used all standard terms of the contract
- User is able to insert the contract particulars relating to their project and make amendments as necessary
- Formulates the JCT contract which can be purchased and exported
- JCT standard terms and conditions are in line with the UK law and any changes to these must be undertaken by a suitably qualified legal representative
NBS Chorus - What is it? How does it work?
- National Building Specifications
- Online platform for creating building and contract specifications
- Standardised approach across the industry for consistence and clarity
- Allows multiple users to promote collaboration
What are the typical timeframes for an interim payment in JCT?
- Valuation date is within the contract
- Due date is 7 days after the valuation date in the contract
- CA’s payment certificate is due within 5 days of the due date
- Date for final payment is 14 days after the due date
- Any pay less notices must be issued at least 5 days prior to the final payment date
When is completion deemed to have been achieved?
- When works are substantially complete as per the contract and specifications
- When all handover information including health and safety file, O&Ms, testing and commissioning certificates, guarantees have been provided
- When site has been cleaned, tidied and made safe for possession to be taken back by employer
Talk me through the End of Defects period on one of your projects?
Hall Green Case Study
- End of defects period as stated on the completion certificate
- Inspection to be undertaken towards the end of this period to identify any defects with the works
- Contractor to close out any last defects in time for the End of Defects date
- Once satisfied all defects have been rectified, issue the certificate of making good which triggers the final payment process for releasing the remaining retention
- Final payment is due 28 days after the End of Defects date or 28 days after the certificate of making good is issued, whichever is sooner
Are interim payments required after PC?
- Usually interim payments are during the construction phase
- Final payment at the end of defects remains after PC
Winshill - What type of tender did you run? What types of tender can you run?
Winshill - Selective Tendering
Open Tendering
- Open for all to submit tender
Selective Tendering
- Pre selected group of tenderers
Negotiated tendering
- Negotiate with one contractor usually
Two Stage Tendering
- Stage 1: Provisional Price
- Stage 2: Detailed Price
Winshill - How did you select tenderers?
- Pre selected group of tenderers on the Staffordshire county council framework of contractors
- Historical project performance of previous contractors used
- Check company financial accounts on companies house to review business financial health
- Check contractor previous track record, case studies etc
- Health and safety record and qualifications and workforce
- Check insurance cover of contractors to ensure appropriate cover in place
Winshill - What contract did you choose and why?
- JCT Minor Works Contract
- Works were simple in nature, window replacements with no specialist input or subcontractor required
- Relatively low contract sum of £80k with a programme of 4 weeks
- All works to be completed within the 5 weeks and one payment to be made at the end of the works
- All works undertaken by one main contractor
What is the risk of using a LOI?
- Not legally binding and subject to execution of formal contract
- Full detailed and contract terms not agreed
- Informal document with risks of miscommunication and misinterpretation
- Full scope of works not detailed
- Financial risk for the contractor due to no clear payment terms
- Risk of further delays of having full contract completed
- Risk of liabilities such as insurance claims are not clear within the letter, therefore a financial risk for the client
- No guarantee for payment of work performed
- Needs to be reviewed and agreed with legal representatives and used as a last resort
- Potential breach of contract, made on assumptions and trust
Winshill - What details did your Letter of Intent include?
- Details of the employer and contractor
- Project description, details, address
- Form of contract intended to be used for the works
- Intended contract sum, start date, completion date, duration, LADs, retention amount
- Terms of the agreement, obligations of both parties
- Signature or both parties
Winshill - Did you advise the client to get a 3rd party to review the Letter of Intent? I.e lawyers
- Yes, I advised the client to have the Letter of Intent reviewed and completed by their legal representative
- I provided the project related details as taken from the tender submission
- Legal terms and agreements to be made by clients representative
Letter of Intent - Is there any case law that highlights these risks?
- Arcadis v Amex
- Appeal case on liability cap for design works undertaken by Arcadis
- Appeal court found that Arcadis were not liable for potential millions as terms were not agreed during for design liability in the interim agreement
What information did you include in your contract document?
- Cover page, details of the parties and project description, and contents page
- JCT Contract
- Drawings and specifications
- Priced schedule of works
- Contract sum analysis / form of tender
- Post tender clarifications and adjusted contract sum if necessary
- Drawing register sheet
- Precontrstion health and safety information
- Reference to the Letter of Intent
- Signatures of both parties
Tell me about the RICS guidance on Appropriate Contract Selection?
- RICS Practice Information on Appropriate Contract Selection (2024)
- Outlines the types of contract and possible routes for the choice of contract to proceed with
- Size, complexity, value of the works
- Employers level of construction knowledge
- Balance of risk/ risk allocation
- Design responsibility
- Control over sub contractors
- Describes how the procurement route can impact the chosen contract
- How to formulate the contract and incorporate any amendments etc
What is your understanding of JCT Intermediate?
- Used for medium scale projects
- More provisions for interim payments, detailed contract clauses in comparison with MW
- Provisions for naming specialists and sub contractors
- Provisions for splitting the works into sections with different sectional completion dates
- Used for more complex projects than MW but less complex than SBC
- Can be used for projects where the contractor is responsible for design of certain elements of the work
- Has provisions for mediation, ajudication and arbitration
What is your understanding of JCT Minor Works?
- Used for smaller simple in nature projects
- Usually works are undertaken by one contractor
- Relatively low value projects, however not always the case, depends on complexity of the works
- Limited payment provisions and usually one lump payment at the end of a shorter programme than Intermediate
- Doesn’t usually include design for the contractor
- More simple provisions for insurance of the works
- Less structured approach for dispute resolution
What other standard form of contract are you aware of?
NEC Contracts
- Used for engineering and construction
FIDIC
- Used internationally for large scale infrastructure projects
- Red Book, Blue Book, Silver Book, Green Book