Case Study Flashcards

(31 cards)

1
Q

What are the main differences between a Minor Works Contract and a Intermediate Contract?

A

Minor works has less mechanisms available than intermediate so it doesn’t allow for sectional completion or nominated subcontractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Explain the different completion processes for a minor works contract and an intermediate contract?

A

Practical completion for MW. Sectional completion an option for Intermediate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How long does a contract have to supply a final account under the contract?

A

6 months under a JCT Intermediate contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the procedure for obtaining contractors design for a JCT contract with contractor’s design?

A

Request the CD prior to contract, carry out design review and CDP analysis and produce a written document outlining the analysis for appending to the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Contractor’s Design Portion Analysis?

A

The process of outlining the extent of the contractors design responsibility for each contractors designed portion and the performance or compliance requirements for it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Where would you find information regarding a building elements typical life expectancy?

A

BCIS Component Life resource

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the difference between mediation and arbitration?

A

The enforceability of the outcome. Mediation is informal whereas arbitration is formal.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why did the asbestos survey need to be undertaken twice?

A

Key areas were missed during the first survey so it would have been higher risk to proceed without a revised survey.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who reviewed the survey to decide it needed to be done again?

A

I did.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What regulations cover asbestos?

A

Control of Asbestos Regulations 2012

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What types of asbestos are there?

A

Amosite
Crocidolite
Crysotile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What building materials typically contain asbestos?

A

Pipe lagging
vinyl floor tiles and adhesives
texture ceiling coatings
cement based products like roof sheets or soffits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who takes on design liability for the door repairs as part of the project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Was the fire door design picked up then as part of the contractors design portion of the contract?

A

No, it was dealt with using a contract variaiton.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What documentation is issued at practical completion?

A

Practical Completion Certificate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What documentation is issued at the end of the rectification period?

A

Certificate of Making Good
Final Certificate of Payment

17
Q

What was the payment procedure for the works at Trembaths?

A

Interim Payments.

18
Q

Talk me through how interim payment timescales work?

A

Valuation date stated within the contract
Due date which is 7 days from valuation date
Then have 5 days to issue the certificate
Final date for payment is 14 days after Due Date

19
Q

How would you record changes to a JCT contract?

A

A Schedule of Amendments appended to the contract.

20
Q

What is capital expenditure?

A

The money a company spends on acquiring, upgrading, or maintaining its long-term assets, such as property, plant, and equipment.

21
Q

What was the purpose of the refurbishment project at MHA Trembaths?

A

To create a more appealing space for the home’s residents, continue to achieve market value fees and reduce monthly energy expenditure.

22
Q

Summarise the role of a Lead Designer for the MHA Trembaths project

23
Q

Could Rolton Group have been employed any other way other than directly by MHA?

25
26
How does single stage tendering differ from two-stage tendering?
26
Summarise a single-stage competitive tender process?
27
When would you use two-stage tendering?
28
29
How did you determine whether planning permission was required for MHA Trembaths?
30
How did you determine whether Building Regulations approval was required for MHA Trembaths?