Chap 5 – Submittals Flashcards

1
Q

Administrative and procedural requirements governing submittals during the construction stage are located where? (2 places)

A

…. in the conditions of the contract, and
….Division 01—General Requirements.
CAPG 5.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Both AIA and EJCDC General Conditions require the contractor to issue a schedule of submittals coordinated with the _____________ .

A

….. construction progress schedule
CAPG 5.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Division 01 specification sections expand on the _____________ .

A

….. general and supplementary conditions
CAPG 5.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Division 01 specification sections specify more detailed administrative and procedural requirements for submittals required in _____________ .

A

…..Divisions 02 through 49 of the specifications.
CAPG 5.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The amount of review time needed by the A/E to render professional judgment on submittals is usually stipulated where?

A

…. in Division 01
CAPG 5.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

AIA A201 indicates that the contractor shall perform no portion of the work requiring submittals until ________ .

A

…. the submittal has been approved by the architect
CAPG 5.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

In the traditional D-B-B project delivery method, submittals are processed during the ________ stage of a project.

A

…. construction
CAPG 5.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Four categories of submittals include:

A
  • Action Submittals
  • Informational Submittals
  • Closeout Submittals
  • Maintenance Material Submittals

CAPG 5.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

T/F: The submittal process may be used to approve substitutions.

A

FALSE:
CAPG 5.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

T/F: Approval of submittals does not relieve the contractor of the his responsibility to fulfill the contract requirements.

A

TRUE:
CAPG 5.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Action submittals are submittals requiring __________ .

A

….responsive action by the A/E, normally review and approval.
CAPG 5.3.1 Intro

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Examples of action submittals include:

A
  • Product Data
  • Shop Drawings
  • Samples

CAPG 5.3.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The number of copies of each shop drawing to be submitted, the format size, and whether any accompanying data are required would be listed where?

A

….either the conditions of the contract or Division 01 (or both)
CAPG 5.3.1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

T/F: The contractor is not required to verify that the samples comply with the contract requirements before forwarding them to the A/E.

A

FALSE:

CAPG 5.3.1.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

T/F: Informational submittals require timely and responsive action by the A/E.

A

FALSE: These are submittals not requiring responsive action by the A/E.
CAPG 5.3.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Examples of informational submittals include:

A
  • Coordination drawings
  • Certificates
  • Design Data
  • Test Reports
  • Manufacturer’s Instructions
  • Manufacturer’s Reports
  • Sustainable Design Reports
  • Qualification Statements
  • Construction Photographs

CAPG 5.3.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

T/F: The contract documents should clearly differentiate between submittals that require A/E review and those that do not.

A

TRUE:
CAPG 5.3.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Coordination drawings are usually prepared by the ___________ to show how multiple system and interdisciplinary work will be coordinated.

A

…. contractor
CAPG 5.3.2.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Certificates may be required to certify _____________ of materials, fabrications, or installation.

A

…. quality or characteristics
CAPG 5.3.2.2

20
Q

The ____________ may require data or certification indicating that the design meets local codes or regulations.

A

….the AHJs
CAPG 5.3.2.3

21
Q

Submittals used for the purpose of achieving a certain level of sustainability based on a sustainable rating system are normally required to be separate from _________ .

A

….construction submittals.
CAPG 5.3.2.7

22
Q

To ensure that a company or individual is qualified, specifications may require _____________ from fabricators, erectors, and installers

A

….. qualification statements
CAPG 5.3.2.8

23
Q

Examples of closeout submittals include:

A
  • O&M data
  • Bonds
  • Special warranties
  • Record documents
  • Spare parts and called attic stock
  • Keying

CAPG 5.4

24
Q

T/F: Division 01—General Requirements typically includes a section on submittal procedures containing information applicable to all submittals required for the project.

A

TRUE:
CAPG 5.5

25
T/F: Specific requirements for submittals are listed in the sections in Divisions 02 through 49.
TRUE: CAPG 5.5
26
The contractor reviews each submittal and ___________ to indicate the action taken.
…. stamps it CAPG 5.6 Intro
27
Submittals are reviewed and approved by the contractor to ensure that:
* contract document requirements have been met, * check dimensions, and * coordinate with subcontractors. CAPG 5.6 Intro
28
T/F: The A/E reviews the submittal to determine accuracy and completeness of dimensions or quantities.
FALSE: These are the contractor’s responsibility. CAPG 5.6 Intro
29
The A/E’s review is limited to determining whether the submittal is ___________ The A/E’s review should not go beyond this basic responsibility.
….. consistent with the design intent indicated in the contract documents. CAPG 5.6 Intro
30
Using a stamp, action taken by the contractor and/or A/E is typically one of the following:
* Approved * Approved as Noted * Revise and Resubmit * Rejected * No Action Taken or Required * Not Required for Review CAPG 5.6 Intro
31
T/F: The rejection of a submittal for good cause can create a condition of entitlement for claim on the part of the contractor
FALSE: Rejection of a submittal for good cause is not a cause for a delay claim CAPG 5.6 Intro
32
T/F: The contractor and the A/E accept unnecessary risk by reviewing and approving incomplete submittals.
TRUE: CAPG 5.6.1
33
When partial submittals are necessary to expedite the project, they should be ________________ .
….identified as such. CAPG 5.6.2
34
How should the A/E handle submittals that were submitted, but not required?
Return without review, marked “not required for review.” CAPG 5.6.4
35
What is the difference between the AIA A201 and the EJCDC C-700 with regard to contractor submittals sent to the A/E?
EJCDC C-700 requires each submittal bear a contractor’s stamp (or other written validation) AIA A201 only states that the contractor shall “review and approve”, (no mention of written or stamped endorsement). CAPG 5.6.5
36
If the A/E wants to add language requiring the use of a submittal stamp by the contractor, where would this language be added?
….Division 01 CAPG 5.6.5
37
T/F: A contractor’s submittal stamp becomes a contract document when submitted to the A/E
FALSE: The submittal stamp is not a contract document and cannot be used to add to or deduct from requirements of the contract documents. CAPG 5.6.5
38
T/F: Contract documents require that the A/E and contractor review and approve submittals: therefore language such as “reviewed” or “no exceptions taken” do not suffice.
TRUE: Such statements do not alleviate the obligation to “approve” a submittal. CAPG 5.6.5
39
Subcontractors and suppliers are responsible for:
* Reading and understanding the contract documents * Knowing the construction progress schedule and allowing adequate time for contractor and A/E review * Properly preparing submittals * Submitting in a timely manner * Using a transmittal form * Reviewing other submittals and coordinating with them * Maintaining records and current status CAPG 5.7
40
The contractor is responsible for:
* Reading and understanding the contract documents * Establishing a realistic submittal schedule that allows for re-submittal * Coordinating submittals including work by owner’s separate contractors * Reviewing submittals for compliance with contract documents, site conditions, dimensions * Approving submittals before transmitting them to the A/E * Using a transmittal form * Distributing approved submittals to subcontractors and others * Maintaining copies of all approved submittals at the site for reference * Maintaining logs and tracking progress CAPG 5.7
41
The A/E is responsible for:
* Specifying reasonable requirements * Reading and understanding the contract documents * Verifying that the contractor has reviewed, stamped, and approved submittals * Reviewing and approving submittals in a timely manner or taking other appropriate action * Reviewing submittals for conformance with design intent * Using a transmittal form * Forwarding submittals to consultants and the owner * Maintaining a copy of approved submittals * Maintaining a submittal log and tracking progress CAPG 5.7
42
Consultants are responsible for:
* Specifying reasonable requirements * Reading and understanding the contract documents * Reviewing and approving submittals in a timely manner * Reviewing submittals for conformance with design intent * Using a transmittal form * Returning submittals to the A/E CAPG 5.7
43
Whose responsibility is it to maintain a submittal log?
…. should be maintained by both the A/E and the contractor. CAPG 5.8
44
If any part of a submittal does not conform to the contract requirements, then _____________ .
The preparer should specifically indicate any part of the submittal that does not conform to the contract requirements. CAPG 5.9
45
T/F: When contract documents identify a specific amount of time for the A/E review of submittals, it will be found in the general conditions.
FALSE: AIA and EJCDC general conditions are not specific about the amount of time allotted to the A/E to review submittals. CAPG 5.9.2
46
The A/E’s review time for submittals is usually stated as part of the contract documents where?
….in either Division 01 or the supplementary conditions. CAPG 5.9.2
47
General conditions state that the A/E’s action on submittals will follow the submittal schedule approved by the A/E, or, _______________ .
…. with reasonable promptness CAPG 5.9.2