Chap 8 - Interpretations and Modifications Flashcards

1
Q

There are two types of modifications: ______

A
  • those that require a change to the contract sum or time, and
  • those that do not.

CAPG Chap 8 Intro

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Changes that do not affect cost or time are minor changes in the work and may take the form of, ______

A

…substitutions, supplemental instructions (ASI), or field orders.

CAPG Chap 8 Intro

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Information should be stated ______

A

… clearly, but only once.
CAPG 8.1 Intro

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

If similar information appears in both the drawings and specifications but is in conflict, ______

A

…document interpretation or modification will be needed.

CAPG 8.1 Intro

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Disagreement by the contractor and owner on an A/E interpretation of the contract may result in:

A
  • change directive
  • minor change in the work (ASI or Field Order)
  • change order
  • notice of claim
  • claim

CAPG 8.1 Intro

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The contract documents are __________ , and what is required ______ is as ______________.

A

The contract documents are complementary, and what is required by one is as binding as if required by all.

CAPG 8.1.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Contract documents are defined as the _________ that become ________ when the _______.

A

…. legally enforceable requirements that become part of the contract when the agreement is executed.

CAPG 8.1.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Contract documents usually include the _____________ (6 things)

A
  • contracting forms,
  • conditions of the contract,
  • specifications,
  • drawings,
  • addenda, and
  • modifications.

CAPG 8.1.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The AIA A201 states that the contractor is required to do only what is:

A
  • reasonably consistent with the contract documents and
  • reasonably inferable as being required to produce the intended results.

CAPG 8.1.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The conditions of the contract require the contractor to report_____________ to the ________.

A

…errors, inconsistencies, or omissions to the A/E.

CAPG 8.1.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When the A/E makes an interpretation consistent with the intent of the contract documents, he then issues an:

A
  • Interpretation,
  • minor change, or
  • proposal request

CAPG 8.1.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

RFIs asking for interpretation of an item in the contract documents, may be initiated by who?

A
  • the owner or
  • the contractor.

CAPG 8.1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The AIA A201 states that the architect’s decisions regarding aesthetic effect are _____, unless they are _____.

A

….are final, unless they are inconsistent with the intent expressed in the contract documents.

CAPG 8.1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

In order to maintain proper lines of communication, RFIs should be accepted only from:

A
  • the owner or
  • the contractor.

CAPG 8.1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

RFIs may occasionally be an attempt to make a ___________ after expiration of the time limit.

A

…. Substitution of

  • product,
  • material, or
  • system

CAPG 8.1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

AIA A201 and EJCDC C-700 stipulate that the A/E’s decisions will be consistent with the intent of what may be _________________

A

….reasonably inferable from the contract documents.

CAPG 8.1.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The A/E should render interpretations based on the contract documents without ___________

A

….partiality to either the owner or the contractor.

CAPG 8.1.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Claims may be caused by the ______ or _____ disagreement with the A/E’s interpretation.

A

….owner’s or contractor’s

CAPG 8.1.3.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Unresolved claims become __________.

A

…. disputes.

CAPG 8.1.3.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Contract modifications are required whenever a change will ____________ .

A

modify the contract documents, regardless of a change in time or cost.

CAPG 8.2 Intro

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

________ are used to modify the contract documents when time or cost are affected.
________ are issued when neither time nor cost are affected.

A

….Change orders are used to modify the contract documents when cost, time, or both are affected.
….Minor changes in the work (ASI / Field Order)

CAPG 8.2 Intro

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Prior to preparation of a change order, the contractor is usually asked to respond to a __________

A

….proposal request or submit a request for proposal which outlines the cost of the change and schedule impact.

CAPG 8.2 Intro

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Contract modifications are not required when:

A

….an RFI does not affect cost or time.

CAPG 8.2 Intro

24
Q

Circumstances under which modifications to the contract documents will be allowed are described where?

A
  • Conditions of the contract, and
  • Division 01

CAPG 8.2.1

25
Contract document modifications may be necessary when:
* intent of the documents is not “reasonably inferable” * corrections required for errors, omissions, discrepancies, or design deficiencies. * unknown conditions necessitate * owner’s requirements change * changes in the regulations after issuance of a permit. * time between bid acceptance and contract execution is long. * interpretations of the regulations by AHJs. * product is no longer available. * A new product offers cost savings. * New information about a specified product * difference in actual product cost -vs- specified allowance * quantity of work for unit price is changed. * Unattainable requirements exist CAPG 8.2.1
26
A request for a contract modification can be initiated by\_\_\_\_\_\_\_\_
* owner, * contractor, or * A/E. CAPG 8.2.1.1
27
Methods available to request and make contract document modifications include:
• Change Order • Change Directives  construction change directive (AIA)  work change directive (EJCDC) • Minor Change  architect’s supplemental instructions (AIA)  field order (EJCDC)  written interpretation or clarification (EJCDC) • Written Requests  proposal request  change order request  request for substitutions CAPG 8.2.1.1
28
What is the difference on who issues a Change Order Request versus a Proposal Request?
Proposal Request: Prepared by A/E ……. submitted to Contractor Change Order Request: Prepared by Contractor ……. submitted to Owner (in response to the Proposal Request) CAPG 8.2.1.2
29
The A/E can initiate a proposal request by issuing AIA form:
….AIA G709, Work Changes Proposal Request. CAPG 8.2.1.2
30
….AIA G709, Work Changes Proposal Request. CAPG 8.2.1.2
….the reasons for the proposed change, along with: * itemization for costs of labor, * material, * taxes, * subcontracts, * bonds, * insurance, and * overhead and profit. CAPG 8.2.1.3
31
The change order request should not be confused with:
* a proposal request. CAPG 8.2.1.2 * a substitution request. CAPG 8.2.1.3
32
A substitution request proposes a change of \_\_\_\_\_, \_\_\_\_\_, \_\_\_\_\_, or ______ from the requirements of the contract documents, along with any cost implications.
* manufacturer, * product, * material, or * system CAPG 8.2.1.3
33
Approval of a substitution request should be documented how?
….in a change order. CAPG 8.2.1.3
34
Minor changes in the work may be initiated by:
* the architect’s supplemental instructions, or * the engineer’s field orders, or * another document identified in the contract documents CAPG 8.2.1.4
35
Who has authority to execute a change order?
….only the owner. CAPG 8.2.1.6
36
Change orders may originate by issuance of a:
* change directive, * change order request, or * proposal request. CAPG 8.2.1.6
37
The cost adjustment for a change order may be determined on the basis of:
* stipulated sum * Unit prices * costs plus a fee CAPG 8.2.1.7
38
Where should the A/E stipulate the modification procedures and data required to substantiate claims for extra costs?
….in a Division 01 section of the specifications. CAPG 8.2.1.7
39
After a change order has been issued, the contractor should adjust the:
* schedule of values * construction progress schedule CAPG 8.2.1.7
40
Once a modification has been issued, it should be posted to the:
….A/E’s and the contractor’s sets of the contract documents. ….”record” set of the contract documents. CAPG 8.2.1.10
41
The AHJ could issue a stop work order upon discovering:
….a failure to report code-related changes to the approved “Permit Set.” CAPG 8.2.1.10
42
If the contractor encounters conditions materially different than indicated on the contract documents, the conditions of the contract allow:
….the work to proceed while the contractor and the owner agree on a fair and equitable adjustment. CAPG 8.2.2
43
AIA A201 and EJCDC C-700 state that upon encountering suspected hazardous materials, the contractor shall:
* stop work in the affected area * notify the owner and A/E of the condition. CAPG 8.2.2.1
44
T/F: When hazardous materials are encountered, the contractor is usually required to remove or encapsulate them.
False: A separate specialty contractor is usually employed to remove or encapsulate the hazardous materials CAPG 8.2.2.1
45
T/F: When notified by the contractor of suspected hazardous materials, the A/E will recommend corrective or remedial measures.
False: The A/E will not recommend corrective or remedial measures. CAPG 8.2.2.1
46
When notified by the contractor of suspected hazardous materials, the A/E may recommend that a qualified expert be employed by:
….the owner. CAPG 8.2.2.1
47
The owner is responsible for hazardous materials unless:
….the materials were brought to the site by the contractor. CAPG 8.2.2.1
48
Concealed conditions are conditions that:
* are not documented, or * could not have been observed at the site at the time of the pricing. CAPG 8.2.2.2
49
The observing party of the concealed or changed condition is required to \_\_\_\_\_\_\_\_\_\_\_\_
….promptly give formal notice before the condition is disturbed. CAPG 8.2.2.2
50
Procedures regarding substitutions proposed after execution of the agreement are described:
….in Division 01. CAPG 8.3 Intro
51
Charges for A/E services to evaluate substitutions initiated by the contractor, or to make revisions resulting from a proposed substitution should be:
* addressed in the owner-A/E agreement, and * added to supplementary conditions or Division 01—General Requirements. CAPG 8.3 Intro
52
EJCDC C-700 has a provision that requires _______________ for the engineer’s time in reviewing and evaluating a substitution, whether or not the proposed substitution is approved.
…. the contractor to reimburse the owner CAPG 8.3 Intro
53
Whether or not the A/E may consider substitution requests during the construction stage will be stipulated where?
….in Division 01. CAPG 8.3 Intro
54
Substitutions should not be considered when:
* The substitution request is made as an RFI. * The substitution is indicated or implied on shop drawings * The submitted substitution request has not been reviewed and approved by the contractor. * Acceptance will require substantial revision of contract documents * The substitution request does not include an itemized comparison CAPG 8.3 Intro
55
Work not complying with the contract documents, which include unapproved substitutions, may be:
….considered defective and be rejected. CAPG 8.3 Intro