Chapter 8 Flashcards

1
Q

Project

A

A one off endeavour t achieve a specific objective

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Repetitive operations

A

“business as usual” - The normal day to day operations of the business

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Project Owner

A

The person for whom the project is being carried out and as such they are interest in the end result being achieved and their needs being met

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Project manager

A

The leader of the project team, taking the ultimate responsibility for ensuring that the project meets its objective

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Project team

A

Members are given individual responsibility for parts of the project, chosen by the project manager. Good to include internal staff and external specialists

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Project customers/users

A

The end user, may or may not be the same party as the project owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Steering Committee

A

Oversee the entire project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Scope Creep

A

changes, continuous or uncontrolled growth in a project’s scope, at any point after the project begins. This can occur when the scope of a project is not properly defined, documented, or controlled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Project sponsor

A

The person or organisation who provides the resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Project management

A

The term given to the processes undertaken to ensure that a project is completed on time, to budget and to the agreed quality standard

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

PMBOK

A

The project management institute published the body of knowledge guide - documents and standardises generally accepted project management information and processes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Earliest event time

A

The earliest time an activity can be completed by - determine the longest path up to the event and determine the minimum time that we can reach this point

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Latest event time

A

The latest time any preceding activity must be completed by if the project is to be finished by its required completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Critical path

A

Activities in which any delay will lead to a delay in the overall project are for which EET = LET. It is the longest path through the network and the shortest time to complete the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Total Float

A

The time available to an activity less the activity duration i.e. End LET - Start EET

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Free float

A

The delay possible in an activity on the assumption that all preceding and subsequent activities start as early as possible i.e. End EET - duration

17
Q

Independent float

A

The delay possible if all preceding activities have finished as late as possible and all succeeding activities are to start as early as possible i.e. End EET - Start EET - duration

18
Q

EVM

A

A means of measuring the progress of a project by comparing performance on costs and time and thus identifying overruns/slippage. Provides an early warning signal

19
Q

Common measure of EVM

A

The cumulative cost performance index (CPI) - the earned value to date/cost to date.

20
Q

Buffering

A

Involves the inclusion of defined quantities to time within a project schedule to ensure the overall deliver date is met (building in slack to account for risky tasks)

21
Q

Padding

A

The adding of additional time to estimates to provide slack, distorting plans and leading to inefficient allocation of resources

22
Q

Feeding buffer

A

May be added to noncritical tasks that feed into critical tasks

23
Q

Capacity buffer

A

May be used in a multi-project programme to reduce the likelihood of a project being adversely affected by resource usage by another project

24
Q

Resource buffer

A

May be added to key resources to ensure that they are available when required

25
Q

Scenario planning

A

Allowances can be made for the risks associated with a project. It involves considering different sets of circumstances that may occur, and devising a plan to deal with each

26
Q

The project management maturity model (PMMM)

A

Aims to identify opportunities for continuous improvement by learning from past mistakes. There are 5 levels

27
Q

PMMM Level 1

A

Emphasises the importance of staff having basic project management knowledge throughout the organisation

28
Q

PMMM Level 2

A

Common standards and processes should be developed, so that the benefits can be repeated in future projects

29
Q

PMMM Level 3

A

Use of a single methodology throughout the organisation

30
Q

PMMM Level 4

A

Recognises the importance of benchmarking as an aid to improvement

31
Q

PMMM Level 5

A

Continuous improvement and feedback