Commercial Management Flashcards

(16 cards)

1
Q

What is commercial management?

A

Commercial management is the reporting of cash flow, profitability and management of commercial risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are some of the tools used for commercial management

A
  1. Cost Value Reconciliation
  2. Cost to complete
  3. Cost plan
  4. Value plan
  5. Cash flow forecast
  6. Risk radar analysis
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What make up the cost plan?

A
  1. Subcontractor costs
  2. Materials
  3. Fees
  4. Plant
  5. Utilities
  6. Prelims
  7. Risk / contingency
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What makes up the value plan?

A
  1. The contract value
  2. Variations
  3. Other incomes
  4. Work in progress (WIP)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is WIP

A

Work in progress is the adjustment for part completed work not yet ready for billing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Give 3 examples of WIP items

A

Over measure (over claiming - NW)
Under measure (under claiming - PW)
Materials on site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is negative WIP

A

Negative WIP is work I progress not ready for billing e.g work claimed but not yet completed or materials on site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is positive WIP and why can it be a problem?

A

Positive WIP is under measure on items which can lead to a negative cash flow balance for the project because of items that have to be paid to the supply chain but not yet claimed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why must cost and value be taken together?

A

To not show a false margin

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you use a risk register to manage commercial risks

A
  1. Analyse as a team the risks to the project
  2. Evaluate them by likelihood and severity
  3. Based on that you can attribute risk amounts based on the risks materialising
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Give an example of when you managed the cash flow of a project

A

I manage the cash flow on my Bath Road project by doing monthly cash flow forecasts to the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Give an example of how you have managed the profitability of a project

A

On my Eastbrook studios project I reported to my directors on the subcontractor liabilities spreadsheet which gave a detailed breakdown of the forecasted final account of each package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Give an example of where you have managed commercial risk

A

When I came to Devcon I did a commercial audit of the company and found areas that we were at risk including a lack of detailed subcontracts without back to back amendments which I advised was needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Give an example of where you have worked with other stakeholder to manage commercial elements

A

On my Bath Road project I attend design team meetings with the designers to make sure that what is being designed is as per the ERs and we are not adding anything unnecessary (eg extra trees)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Give an example of where you have advised on the profitability of a project.

A

On my Onslow mills project I advised using a CVR exercise that although there was profit in the job it had all been taken previously and the job was now costing us due to delays. My advice was to apply for any variations that had not been claimed for to the client as well as an extension of time. I also advised on subcontractors retention not being held.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Give an example of where you have advised on cash flow

A

I advised on my Eastbrook studios project for the M Price package that we should purchase materials direct and reduce payment terms as VolkerFitzpatrick has the cash reserves to do so