Contract Practice Flashcards

(48 cards)

1
Q

What are the different suites of construction contracts available?

A
  1. JCT suite of contracts
  2. NEC4
  3. FIDIC
  4. DEFCON
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Give 3 examples of JCT contracts

A
  1. JCT Standard Building Contract
  2. JCT Design & Build
  3. JCT Minor Works Building
  4. JCT Prime cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When would the JCT standard building contract be appropriate?

A

When the design is complete for construction and a detailed BoQ can be provided. When the client wants to retain all control over the design. To get the most competitive form of tender.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When would a JCT design & build contract be most appropriate?

A
  1. When the designs are incomplete
  2. When contractor input is of value or to get an PCSA agreement
  3. To speed up the process so design and construction can overlap
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When do you use a minor works contract?

A

Smaller less complex projects typically for domestic projects where work is valued at no more than £500,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When would a prime cost contract be appropriate?

A

When there is a good relationship between the contractor and client. The scope of works is hard to define. Time is a much higher priority than cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Give the options of contract available under the NEC4

A
  1. Op A priced with activity schedule
  2. Op B Priced with BoQ
  3. Op C target cost with A S
  4. Op D target with BoQ
  5. Op E cost reimbursable
  6. Op F construction management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What types of projects typically use NEC contracts?

A

Infrastructure projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Explain how an NEC Option C contract works

A

NEC used an activity schedule with a target cost which means if the project cost is over or under the budget there is a pain/gain shared between the client and contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the principles of the NEC contract?

A
  1. Good relationship management
  2. Flexibility, for a variety of projects
  3. Clarity, simple and straightforward
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the key differences between the JCT & NEC

A
  1. NEC includes a contract as a contractual document that is reviewed on a monthly interval
  2. JCT deals with relevant events and relevant matters separately as opposed the CEs that deal with it together
  3. Early warning notices must be raised under an NEC and have time bars associated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the 4 things necessary to form a contract

A

Offer
Acceptance
Consideration
Legality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a collateral warranty?

A

A collateral warranty is a separate document that sits besides the main contract to bridge the contractual gap between designers and subcontractor and the client in the case of the main contractors insolvency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why are collateral warranties needed?

A

Due to privity of contract between the two parties which means only those party to a contract can enforce it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the key elements that make up a JCT contract?

A
  1. Agreement (who)
  2. Recitals (what)
  3. Articles (how much and EA, PD)
  4. Contract Particulars (Dates and insurances)
  5. Conditions
  6. Contract amendments
  7. Employers Requirements
  8. Contractors proposals
  9. Contract Sum Analysis
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Give an example of where you have negotiated a contract

A

On my Bath Road project I negotiated a 2.5% discount on. The Brickwork subcontractor in exchange for a reduction of payment terms from 35 days to 14 day terms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What differences would there be in the contract docs between a £1m cladding subcontract and a £25k scaffolding subcontract?

A
  1. Cladding is higher risk and had design so would need more comprehensive contract amendments specific to design.
  2. A detailed programme for cladder
  3. Collateral warranty
  4. Professional Indemnity insurance
  5. More comprehensive construction info and details.
  6. Tender pre start giving details of their construction methodology
  7. Retention, bonds, PCG
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Give an example of when you might use a Sub-contract Tender Sum and where you would find that in the contract

A

For a remeasurable contract such as fire stopping or diamond drilling where the full scope is undefined and Article 3B in the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the clause for a relevant events and give 3 examples

A

2.26
.2 Employers instructions
.3 Deferment of possession
.8 adverse weather conditions
.14 Force Majeure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is the clause for relevant matters and give 3 examples

A

4.21
.1 Changes
.2 Employers Instructions
.3 any impediment, prevention or default from the employer

21
Q

What are the responsibilities of the contractor under the JCT?

A
  1. Execution of the work (and design if applicable)
  2. Compliance with building regs
  3. Meet programme
  4. Variations and instructions
  5. Site management
  6. H&S and CDM regs
  7. Communication and reporting
22
Q

Give an example of a variation instruction you received an how you dealt with it under the contract

A

Bath Road access control change
1. Required change
2. Explained what we had priced and that the work would be Vo cost
3. Priced variation based on SC quote
4. Asked for formal instruction
5. Proceeded with the work by instructing the M&E subcontractor

23
Q

What would you find in the contract particulars?

A
  1. Base date
  2. Contract Sum
  3. Retention
  4. Insurance levels
  5. LDs
  6. Date of possession and date for completion
  7. Rectification period of defects
24
Q

What is in the contract recitals under the JCT?

A

What the contract is for eg the build description and what forms part of the contract ERs and CPs

25
When should EW notices be issued?
When they become aware of any matter that could: 1. Lead to an increase in cost 2. Delay completion or key date 3. Impair the performance of the works
26
What follows an early warning notice?
A risk reduction meeting with the client and contractor
27
When is a CE time barred?
8 weeks for contractors and 7 for subcontractors
28
What happens if a CE is raised without prior raising an EW?
If an EW should have been raised prior to the CE and the impact of the CE could have been mitigated by an EW the compensation for the CE can be reduced
29
What happens if a CE notice is not responded to?
The contractor can raise a notice of failing to assess the CE and if they fail to respond again the quote is deemed accepted
30
What are the elements necessary to form a binding contract?
1. Offer 2. Acceptance 3. Consideration 4. legality (purpose must be legal) 5. Intention to create legal agreement 6. Capacity (of age and sound mind etc)
31
Give an example of where you have advised on sub- contract terms?
Eastbrook studios drylining project, agreement to retention released at S/C pc (close to our PC) and in return they agreed to our S/C amendments. Agreement to reduced LDs for Farrat etc
32
Give an example of where you have advised on main contract terms
On the Merstam library tender I advised that Claude 3.9.2 had been struck out so that changes to spec wouldn’t be classed as a change under the contract, which was unfair and should be reinstated
33
What is a contract?
A legally binding agreement by one party to do something for another in exchange for something
34
What are express terms?
The provisions explicitly agreed upon by the parties as part of the contract
35
What are implied terms?
Provisions not expressly agreed but implied by common law or statute
36
What is tort?
Tort is a law concerned around wrong doing that causes the claimant loss or harm usually referring to negligence
37
What is negligence?
Negligence is the breach of a duty of care
38
What is the local democracy economic development act 2009?
It updated the construction act 1996 based on the needs of the industry to include oral and part written contracts, and terms requiring the adjudicatings party to be liable for costs are no longer valid
39
What is the Housing Grants and Regeneration Act?
1. Right to adjudication 2. Outlawed pay when paid terms 3. Must have adequate payment mechanism 4. Payment notices mandatory 5. Payees notice becomes notice by default 6. Right to suspend performance for non payment
40
What is a letter of intent?
A contract agreed by both parties to intend to enter into contract typically issued by the employer
41
What are the disadvantages of a letter of intent?
1. Gives the contractor more leverage to argue terms as they have already started. 2. Unclear terms if disputes arise 3. Limits on work/payment amounts 4. Are often extended again and again rather than getting into contract
42
Why would a letter of intent be used?
To make a quick start before terms are agreed Long lead in periods for materials Trigger external funding or planning consents
43
What is the contract (rights of third parties) Act 1999?
Legislation that gave the right to a third party to enforce terms if the contract explicitly states their ability to do so or if the contract intended the benefit to the third party
44
Give some examples of where a collateral warranty would be used
Employer - sub contractor Employer - consultant Funder - contractor Benefactory/end user - contractor
45
What is assignment?
The transferring of the rights under a contract from one party to another eg employer to benefactory/funder
46
What is a defect?
Work not in accordance with the scope or not in accordance with the law. In lehmans terms it’s something wrong with the building
47
What are patent defects?
Defects reasonably discoverable by inspection rectifiable in 12 months
48
What happens if the client fails to pay the amount due on the final day for payment?
Subject to interest (subject to conditions) Exercise the right to suspend works following contract procedures