Contract Practice Flashcards

(20 cards)

1
Q

What are the different suites of construction contracts available?

A
  1. JCT suite of contracts
  2. NEC4
  3. FIDIC
  4. DEFCON
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Give 3 examples of JCT contracts

A
  1. JCT Standard Building Contract
  2. JCT Design & Build
  3. JCT Minor Works Building
  4. JCT Prime cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When would the JCT standard building contract be appropriate?

A

When the design is complete for construction and a detailed BoQ can be provided. When the client wants to retain all control over the design. To get the most competitive form of tender.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When would a JCT design & build contract be most appropriate?

A
  1. When the designs are incomplete
  2. When contractor input is of value or to get an PCSA agreement
  3. To speed up the process so design and construction can overlap
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When do you use a minor works contract?

A

Smaller less complex projects typically for domestic projects where work is valued at no more than £500,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When would a prime cost contract be appropriate?

A

When there is a good relationship between the contractor and client. The scope of works is hard to define. Time is a much higher priority than cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Give the options of contract available under the NEC4

A
  1. Op A priced with activity schedule
  2. Op B Priced with BoQ
  3. Op C target cost with A S
  4. Op D target with BoQ
  5. Op E cost reimbursable
  6. Op F constriction management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What types of projects typically use NEC contracts?

A

Infrastructure projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Explain how an NEC Option C contract works

A

NEC used an activity schedule with a target cost which means if the project cost is over or under the budget there is a pain/gain shared between the client and contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the principles of the NEC contract?

A
  1. Good relationship management
  2. Flexibility, for a variety of projects
  3. Clarity, simple and straightforward
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the key differences between the JCT & NEC

A
  1. NEC includes a contract as a contractual document that is reviewed on a monthly interval
  2. JCT deals with relevant events and relevant matters separately as opposed the CEs that deal with it together
  3. Early warning notices must be raised under an NEC and have time bars associated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the 4 things necessary to form a contract

A

Offer
Acceptance
Consideration
Legality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a collateral warranty?

A

A collateral warranty is a separate document that sits besides the main contract to bridge the contractual gap between designers and subcontractor and the client in the case of the main contractors insolvency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why are collateral warranties needed?

A

Due to privity of contract between the two parties which means only those party to a contract can enforce it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the key elements that make up a JCT contract?

A
  1. Article of Agreement (who)
  2. Recitals (what)
  3. Articles (how much and EA, PD)
  4. Contract Particulars (Dates and insurances)
  5. Conditions
  6. Contract amendments
  7. Employers Requirements
  8. Contractors proposals
  9. Contract Sum Analysis
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Give an example of where you have negotiated a contract

A

On my Bath Road project I negotiated a 2.5% discount on. The Brickwork subcontractor in exchange for a reduction of payment terms from 35 days to 14 day terms

17
Q

What differences would there be in the contract docs between a £1m cladding subcontract and a £25k scaffolding subcontract?

A
  1. Cladding is higher risk and had design so would need more comprehensive contract amendments specific to design.
  2. A detailed programme for cladder
  3. Collateral warranty
  4. Professional Indemnity insurance
  5. More comprehensive construction info and details.
  6. Tender pre start giving details of their construction methodology
  7. Retention, bonds, PCG
18
Q

Give an example of when you might use a Sub-contract Tender Sum and where you would find that in the contract

A

For a remeasurable contract such as fire stopping or diamond drilling where the full scope is undefined and Article 3B in the contract

19
Q

What is the clause for a relevant events and give 3 examples

A

2.26
.2 Employers instructions
.3 Deferment of possession
.8 adverse weather conditions
.14 Force Majeure

20
Q

What is the clause for relevant matters and give 3 examples

A

4.21
.1 Changes
.2 Employers Instructions
.3 any impediment, prevention or default from the employer