Qunatification & Costing Flashcards

(27 cards)

1
Q

What is NRM?

A

RICS Practice Information called New Rules of Measurement which gives guidance on costing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are NRM 1, 2 & 3?

A

NRM1 - Order of cost estimating and cost planing for capital building works
NRM2 - Detailed measurement for building works
NRM3 - Order of cost estimating and cost planning for maintenance works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is an alternative to NRM2?

A

SMM7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What’s the difference between NRM2 and SMM7?

A

They both categorise each element of works differently eg SMM7 has groundwork’s whereas NRM2 has excavation and filing / ground remediation / piling as separate chapters

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why is NRM2 used?

A

To form a standardised basis on which building elements can be measured and costed for procurement and variation purposes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Give 3 examples of how you might go about costing a variation?

A
  1. Quoted works from S/C with OH&P %
  2. Use rates within the BoQ
  3. Use first principles of labour, plant and materials
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a project feasibility report?

A

A project feasibility report is a preliminary cost and programme assessment of a project based on limited information usually RIBA stage 1 or 2 to give the client a rough budget to see if the scheme is viable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the BCIS?

A

Building Cost Information Service

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How might you use the BCIS?

A

The BCIS can be used to gather constriction data to be used to analyse industry prices per sector and location, can provide average costing data for types of projects to be used as a check for estimates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How did you go about procuring the fire stopping package for your Eastbrook studios project?

A
  1. Understand the scope of what was required
  2. Gathered the project information that would be required, spec, drawings, project info
  3. Produced a BoQ in accordance with NRM2
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How did you create the BoQ for the fire stopping and cavity barriers at Eastbrook Studios?

A
  1. BoQ template with description / qty / unit / rate / total
  2. Use NRM2 work section 31 insulation fire stopping and fire protection
  3. Measured the cavity barriers (m2, thickness, type (batt), internal
  4. Measured the fire stopping (nr, dimension, fire rating, vertical/horizontal, batt and mastic
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you measure cavity barriers?

A

Unit - Area (m2)
Thickness of cavity
Type (batt),
Location - internal/external

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you measure fire stopping?

A
  1. Nr
  2. Dimension of hole
  3. Fire rating of wall (60m etc),
  4. Location vertical/horizontal,
  5. Material - batt and mastic
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What’s the difference between a remeasurable contract and lump sum when it comes to assessing variations?

A

Remeasurable contracts have a BoQ where the whole works are remeasured based on their rates in the BoQ
Lump sum only variations are measured based on the rates, the rest of the works are fixed costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are day works?

A

Day works are a method of valuing variations by agreement when there is no other way to assess the variation using hourly rates signed off once the works are complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are day works?

A

Day works are a method of valuing variations by agreement when there is no other way to assess the variation using hourly rates signed off once the works are complete

17
Q

Give an example of value engineering

A

On my Eastbrook studios project I priced a value engineering proposal to the client to reduce the tiling in the bathrooms to half height and replace with painting

18
Q

What is value engineering?

A

Value engineering is a method of altering the design or spec to improve the value or produce a saving for the client

19
Q

How did you produce a project feasibility analysis for the London Road, Bagshot project?

A

Similarly to how we would price an estimate we priced the works, spoke to the operational team to assess a programme and prelims and allocated the appropriate risk/contingencies for elements that are unknown

20
Q

How did you advise the client on London Road Bagshot?

A

I advised the client through the London Road Bagshot construction build budget and programme so they knew what the land was worth and if the scheme was viable

21
Q

What were some of the risk items that you priced and how did you value them on the London Road Bagshot project feasibility budget?

A

The site contained a house so there was some risk of asbestos, no survey was completed but we did inspect the site and no dangerous items were identified but a budget of 15k was put in and ground contamination 90k risk plus general contingency of 75k 5.4m total

22
Q

What is the purpose of a bill of quanitities?

A

A bill of quantities is the format for which tenderers can price specific items of work to be assessed for a like for like basis

23
Q

What sources of cost data do you use?

A
  1. In house data built up from previous projects
  2. Quoted packages
  3. BCIS
24
Q

What is the difference between GIA and NIA?

A

Net internal area refers to the useable space within the building

25
What software do you use for quantification?
Blue beam and AutoCad
26
What checks do you have in place to ensure your measurement is accurate?
1. Double check measurement 2. Rough measurements 3. Comparison against package budget
27
How do you deal with discrepancies between drawings and spec?
1. Raise and RFI to the client 2. Clarify with the relavant designer 3. Speak to the subcontractors on the best option and communicate to all tenders to price one way 4. Clarify the order or precedence with documents