Cost Management Flashcards

1
Q

Value analysis

A

Focus is to find a less costly way to do the same work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Cost risk

A

Cost related risk and crosses across multiple knowledge areas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Plan cost management

A

How you’re going to plan manage and control project costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Return on investments

A

Used to measure the potential profitability of an investment by calculating the benefits received in relation to the cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Discounted cash flow

A

Technique to estimate the attractiveness of an investments by predicting how much money will be relieved in the future and discounting it to its current value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Estimate costs

A

Coming up with cost estimates for each activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Types of costs

A

Variable costs - change with the amount of production or the amount of work ex: materials supplies and wages

Fixed costs - do not change as production changes ex: set-up, rent, utilities

Direct costs - directly attributed to the work on the project ex: travel, team wages, recognition and cost of material used on the project

Indirect Costs - overhead items or costs incurred for the benefit of more than one project ex: taxes fringe benefits and janitorial services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Bottom up estimating

A

Creating detailed estimate for each part of an activity or work package estimates are then rolled up into control accounts and then into an overall project estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

PV

A

Planned value

As of today what is the estimated value of the work planned to be done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EV

A

Earned value

As of today what is the estimated value of the work actually accomplished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

AC

A

Actual cost ( total cost )

As of today what is the actual cost incurred for the work accomplished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

BAC

A

Budget at completion

How much did we budget for the total object effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

EAC

A

Estimate at completion

What do we currently expect the TOTAL project to cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

ETC

A

Estimate to complete

From this point on how much more do we expect it to cost to finish the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

VAC

A

Variance at completion

As of today how much over or under budget do we expect to be at the end of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Cost variance formula

A

EV - AC

Negative is over budget positive is under budget

17
Q

Schedule variance formula

A

EV - PV

Negative is behind schedule positive is ahead of schedule

18
Q

Cost performance Index

A

EV / AC

We are getting x amount worth of work out of every $1 spent

Greater than one is good less than one is bad

19
Q

Schedule performance

A

EV / PV

We are only progressing at x% of the rate originally planned

Greater than 1 is good less than 1 is bad

20
Q

Variance at completion

A

BAC - EAC

How much over or under budget will we be at the end of the project

21
Q

Estimate to complete

A

EAC - AC

How much more will the project cost

22
Q

To complete performance index formula

A

(BAC - EV ) / (BAC - AC)

In order to stay in budget what rate must we meet for the remaining work

23
Q

Estimate at completion

A

AC + bottom up ETC

Calculates the actual costs to date plus a new estimate for the remaining work

BAC / CPI

Used if no variances from the BAC have occurred or you will continue at the same rate of spending

AC + (BAC - EV)

Calculates actual costs to date plus remaining budget

AC + (BAC - EV) / CPI x SPI)

Calculates actual to date plan plus the remaining budget modified by performance

24
Q

Rough order of magnitude estimate

A

Made during project initiating

-25 to +75 percent from actual

25
Budget estimate
Made during project planning -10 to + 25 percent from actual
26
Definitive estimate
+/-10 percent from actual
27
Life cycle costing
Looking at the cost of the life of the product not just the cost of the project
28
Cost management plan
``` Currency Reporting formats to be used Rules for measuring cost performance Control thresholds Cost change control procedures Funding decisions How cost activities will be conducts Rules for measuring cost performance ```
29
Inputs to estimating costs
``` Cost management plan Scope baseline Project schedule HR management plan Risk register Enterprise environmental factors Organizational process assets Project management costs ```
30
How is cost estimating done
``` One-point estimating Analogous estimating Parametric estimating 3 point estimating Bottom up estimating ```
31
Control costs
``` Follow the cost management plan Look at organizational process assets Reserve analysis Determine variances by measuring Use progress reporting Earned value management ```
32
Accuracy of estimates
Estimates should be in a range and over time you can narrow the estimate range Organizations have different standards for different ranges Rough order of magnitude (rom) estimates - initiating Budget estimate - planning Definitive estimate - as the project progresses
33
Determine budget
Inputs - cost management plan - risk register ( for contingency reserves) - scope baseline - project schedule - org process assets - activity cost estimates - basis of estimates - resource calendars - agreements about cost PM must perform risk management activists and include reserves in the estimate