Lesson 2 Starting the Project Flashcards

1
Q

focus groups

A

a group providing expectations and attitudes about a product, service or result

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

SMART objectives

A

Objective adhering to the SMART criteria: Specific, Measurable, Achievable, Relevant and Time-bound

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

predictive life cycles

A

form of project life cycle where scope, time and cost are determined in the early phases of the life cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

agile life cycles

A

also called adaptive life cycle; form of project life cycle that uses an iterative and incremental approach to define and deliver the results of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

iterative life cycles

A

form of project life cycle where the result or product is developed through a series of repeated cycles with each cycle providing more functionality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

incremental life cycles

A

form of life cycle that delivers the product in functional increments through a series of cycles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

hybrid methodologies

A

methodologies that combine both predictive and agile approaches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

requirements traceability matrix

A

a grid that links requirements from their origin to the deliverables that satisfy them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

agile estimating

A

estimating techniques that use relative estimates as opposed to definitive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

product backlog

A

a prioritized list of customer requirements or user stories

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

scope management plan

A

a component of the project management plan that describes how the scope will be defined, developed, monitored, controlled and validated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

affinity diagramming

A

a technique that allows for large number of ideas to be classified into groups for analysis and review

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

context diagram

A

a visual representation of a product, service or process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

requirements management plan

A

a component of the project management plan that describes how requirements will be collected, analyzed, documented and managed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

project scope statement

A

a document that describes the project scope, the deliverables, exclusions, constraints and assumptions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

WBS

A

(work breakdown structure) - a hierarchical decomposition of the total scope of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

WBS dictionary

A

a document that provides the detail description of each component in the WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

control accounts

A

management control points where scope, schedule and costs are integrated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

planning package

A

a WBS component below the control account with known work content but without detailed scheduled activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

code of accounts

A

a numbering system used to uniquely identify each component of the WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

work package

A

the work defined at the lowest level of the WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

user story

A

a brief description of the definable value for a specific user

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

sprint backlog

A

a list of work items to be completed in a scrum sprint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

definition of done (DoD)

A

a list of the criteria required to be met for the deliverable to be considered complete or ready to use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
acceptance criteria
a set of conditions required to be met before a deliverable can be accepted
26
Rough Order of Magnitude (ROM)
high level estimate developed without basis of detailed of detailed data and usually based on high level historical information; accuracy generally -25% to +75%
27
analogous estimate
a technique for estimating using historical data from a similar activity or project; low level of accuracy
28
parametric estimating
a technique for estimating using parameters or variables and historical data
29
bottom up estimating
also called definitive estimating; most accurate type of estimating using detail from the lowest components of the work
30
three-point estimating
an estimating technique that determines the estimate by calculating the average or weighted average of the optimistic, pessimistic and most likely estimates
31
T-shirt sizing
a technique for determining relative estimates by using t-shirt sizes ((small, medium. large, extra large)
32
velocity
the measure of how much work can be performed in a sprint
33
EVM
Earned Value Management - a methodology that combines scope, schedule and cost measurements to assess project performance
34
estimate at completion (EAC)
the expected total cost of completing all work combining the actual cost to date and the estimate to complete
35
funding limit reconciliation
the process of comparing the planned expenditure of project funds against any limits on the commitment of funds
36
story estimates
relative estimates of value and/or complexity for a specific story
37
task estimates
estimates of the work required for a specific task or activity
38
relative estimating
any technique that provides relative estimates as opposed to definitive work estimates
39
burndown chart
a visual tool used to track the number of hours (or story points) of work remaining
40
burnup chart
a visual tool used to track completed work versus planned work
41
four types of precedence relationships
finish-to-start (fs); start-to-start (ss); finish-to-finish (ff); start-to-finish (sf); finish-to-start is the most used; start-to-finish is the least used
42
milestone chart
a type of schedule chart that shows only milestones or expected completion of major events or deliverables
43
critical path
the sequence of activities that represents the longest path through a project which determines the shortest project duration
44
CPM
critical path method - the technique used to determine the critical path on a project
45
Agile release planning
a top-down approach to planning an agile project; uses high level estimating to determine the number of releases and the number of iterations within each release
46
cost of quality
costs organized by investment of costs to prevent defects and costs incurred due to defects
47
benchmarking
provides a basis for measuring performance by using historical or competitive measurements
48
quality audit
an independent audit to determine whether a project is conforming to standard or expected quality practices
49
verify deliverables
the process of verifying the quality of deliverables
50
validate deliverables
the process of obtaining customer approval of deliverables
51
control charts
graphs used to communicate the variability of a process or project activity over time
52
Pareto chart
a histogram used to rank causes of problems in a hierarchical format
53
statistical sampling
a quality technique that inspects a portion of the population as opposed to the entire population
54
Project plan documents versus project documents
project plan documents are components of the Project Management Plan and once approved can only be changed through change control; project documents are intended to be updated as needed without requiring formal change control
55
Project Management Plan components
documents which make up the Project Management Plan (includes the three baselines and the supporting management plans)
56
scrum of scrums
representatives from multiple scrum teams meet to review each scrum team's progress and to identify any potential conflicts or issues
57
SAFe
Scaled Agile Framework - a holistic view of agile approaches across an organization or enterprise
58
make-or-buy analysis
the analysis used to determine whether a project team should make (build) a product or service or buy the product or service from a third party
59
Statement of Work (SOW)
a document that describes the procurement item in sufficient detail to allow prospective sellers to bid on the work required to deliver the expected product, service or result
60
source selection criteria
set of attributes desired by the buyer which a seller is required to meet or exceed
61
bidder conferences
meetings conducted by the buyer with potential sellers after issuing the RFP but prior to submission of the bids; meetings are used by the buyer for setting clear expectations of the project
62
types of fixed price contracts
Firm Fixed Price (FFP, also called "lump sum"); Fixed Price Incentive Fee (FPIF); Fixed Price with Economic Price Adjustment (FPEPA)
63
types of cost reimbursable contracts
Cost Plus Fixed Fee (CPFF): Cost Plus Incentive Fee (CPIF); Cost Plus Award Fee (CPAF)
64
Time and materials (T&M) contract
contract where buyer pays seller negotiated hourly rate and reimbursement of materials used to complete the project