Lesson 4 Keeping the Team on Track Flashcards

1
Q

power/interest grid

A

grid to classify stakeholders by the two dimensions of power and interest

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

power/influence grid

A

grid to classify stakeholders by the two dimensions of power and influence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

salience model

A

three dimensional model used to classify stakeholders based on power, legitimacy and urgency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

actual costs (AC)

A

actual costs incurred for a project or specific activity; needed to determine cost variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

earned value (EV)

A

a measure of work performed expressed in terms of budget authorized for that work; default formula :
EV = Budget at Completion (BAC) X % Complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Budget at Completion (BAC)

A

the sum of all budgets established for the work to be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Planned Value (PV)

A

the authorized budget assigned to scheduled work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

cost variance (CV)

A

cost variance expressed as the difference between the earned value and actual costs; formula:
CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

schedule variance (SV)

A

a measure of schedule performance expressed as the difference between earned value and planned value; formula:
SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost performance index (CPI)

A

a measure of cost efficiency expressed as a ratio of earned value to actual cost: formula:
CPI = EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Schedule performance index (SPI)

A

a measure of schedule efficiency expressed as a ratio of earned value to planned value; formula:
SPI = EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

To-complete-performance-index (TCPI)

A

a measure of the cost performance required to be achieved with the remaining resources in order to meet a specified management goal; formula:
(BAC - EV) / (BAC - AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Estimate at Completion (EAC)

A

The expected total cost of completing all work for the project taking the sum of the actual costs plus the estimate to complete; formula:
EAC = AC + ETC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Estimate to Complete (ETC)

A

the expected cost to complete the remaining work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Variance at Completion (VAC)

A

the variance between the original budget and the estimate at completion; formula:
VAC = BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

throughput metrics

A

measurement of the team’s work that has moved from one stage to another stage over a certain time

17
Q

cycle time

A

time required from initiation of work until completion of work or delivery

18
Q

value stream map

A

presents a visual representation of a process and the actions in each step to determine efficiencies and waste

19
Q

Tuckman’s ladder

A

the stages of team development: forming, storming, norming, performing and adjourning

20
Q

emotional intelligence (EI)

A

the ability to identify, assess and manage the personal emotions of oneself and others

21
Q

nominal group technique (NGT)

A

a technique that enhances brainstorming with a voting process

22
Q

active listening

A

communication technique that involves acknowledging what you hear and confirming that what you heard is what the sender intended

23
Q

Maslow’s hierarchy

A

theory that places the needs of an individual in a pyramid or triangle; lower-level needs must be satisfied before a high level one can be addressed

24
Q

McGregor’s Theory X and Y

A

Theory X states that people need to be managed to maintain productivity; Theory Y is the opposite: people want to work and do not require constant supervision

25
McClelland's Achievement Theory
people are motivated by achievement, power or affiliation
26
Herzberg's Motivation Theory
success is based on two factors: hygiene factors relate to expected working conditions and are not motivators; motivating factors relate to feelings of achievement, recognition and career growth