PjM_PPI Flashcards
labor and materials bond payment bond
A bond carried by the contractor and the contractor’s surety promising that payment will be provided to the subcontractors and suppliers for labor and materials used in the project. A means to prevent a mechanic’s lien from being placed on the project property.
elemental method
Systems and assemblies cost estimating.
bidding documents
Documents produced by the design team—including documents required by the owner for the construction contract—that allow contractors to produce cost estimations and bid their fee for construction. The bidding documents include, for example,
bid form
contract form
contract conditions
bond requirements
general and supplementary conditions
specifications
construction drawings
addenda
bid bond bid security
A type of insurance that the bidding contractor provides ensuring they will enter into contract with the owner. This protects the owner from selecting a winning bid that will not be executed, putting them at risk for wasted time or increased bids in a second round of bidding. Also protects owner from a contractor placing low, unrealistic bids to successfully execute the project, and against contractors bidding on too many projects at once, winning more than they can execute, and not accepting the project after winning the bid.
supplementary conditions
A portion of the contract documents that may add to, modify, or change the general conditions of the project.
unit rate method
Pricing of a project or portion of a project by providing a cost per area, volume, or other single-unit rate method, such as a hotel project being priced on cost per room.
unit price contract
A contract based on the acceptance of the unit price quote given for various portions of the project.
general conditions
The portion of the contract documents where the rights, responsibilities, and relationships of the parties are outlined, as well as the overall expectation of the execution and delivery of the work. Often includes boilerplate terms that are common to most construction projects.
project manual
A collection of documents required for the construction work, often including (drawings are not included)
‐ bidding requirements, (instructions to bidders)
- contract forms,
- general and supplementary conditions
- specifications
progress payments
In response to the contractor’s application for payment, the architect approves portions of the work completed to allow payment to the contractor for materials and work performed to date. The contract specifies the period for which “progress” will be addressed for payment.
labor and materials bond payment bond
A bond carried by the contractor and the contractor’s surety promising that payment will be provided to the subcontractors and suppliers for labor and materials used in the project. A means to prevent a mechanic’s lien from being placed on the project property.
procurement documents
The documents used to obtain pricing from prospective contractors.
procurement
The transition from the design stage to the construction stage of a project. Involves the bidding, negotiating, and purchasing phases.
bid shopping
The practice of revealing the sub-bid of one subcontractor to obtain a lower price from another subcontractor.
design negotiate build
The owner and contractor negotiate a construction contract in order to achieve mutual benefit and avoid the inherent risks of competitive bidding.
supplementary conditions
A portion of the contract documents that may add to, modify, or change the general conditions of the project.
basic service
The architectural services normally required for a building project, usually consisting of
schematic design,
design development,
construction documents,
bidding or negotiation,
construction contract administration.
What two types of services does AIA Document B101allow the architect and owner to agree on and contract for?
The architect’s basic services, and additional services such as programming and land-use studies can be contracted by these two parties.
What four methods are commonly used to determine the compensation for the architect?
These four methods are
- stipulated sum
- cost plus fee
- hourly billing rates
- percentage of construction cost
Who does the legal concept of agency involve?
This legal relationship involves three parties.
- principal
- agent, who has been authorized by the principal to act on the principal’s behalf
- third party, who enters into a contract with the principal
What is a stipulated or lump-sum contract?
This kind of contract calls for a project to be delivered for a set price.
What are liquidated damages?
This is money paid to the owner by the contractor for every day the project is late, as stipulated in the contract.
What type of bonds must contractor purchase as stated in AIA Document A101-2017?
This party must carry surety bonds.
Who is protected against third-party claims in the standard owner-architect agreement?
Both parties are protected against third-party claims in this agreement, AIA Document B101–2017, to the extent damages are covered by property insurance.