Name three consultants that are typically licensed excluding MEP structural and civil
Landscape architect
Security consultant
Technology consultant
According to the B101 what must happen so the architect can begin preparing schematic documents
The owner must approve preliminary design
Who is responsible for coordinating the services provided by the owners consultants?
The owner and architect
What three documents stipulate that an IDM is to be used in disputes
A101
B101
A201
Which documents state, directly or indirectly that the architect is not responsible for methods, sequences, procedures, or techniques
A201
B101
How many days does the owner have to respond to a contractor requesting important information necessary for the evaluation of a project?
A201 states 15 days
What three documents would be used if an owner hired a construction manager as constructor
A133
B133
A201
If a contractor furnishes a substitution prior to bid how many days are required before the close of bid for the substitution to be reviewed
10 days
Ideally, when should a code consultant be brought in by the client for the project of a new office building?
Concept Design
Balance sheets use what to calculate them and profit loss statements use what for calculations??? Rates or Ratios?
Profit/Loss = UNPO
Balance Sheets = RDCQ
Current
Quick
Debt to Income
Return on Equity
What is a surety bond?
A surety is a company that guarantees specific work to be completed by a contractor
In terms of quality management name, two areas usually associated with preventative costs
Education
Staff training
Definition for a bid alternate
Portion of work defined in the procurement documents for which separate pricing is to be identified by the bidders
Allowance
An amount of money or quantity of materials identified by bidders for work that is not included in the procurement documents
What is used by contractors when submitting bids in order to manage risk?
A contingency
Typically equipment drawings would start with what suffix
Q
What drawing suffix would Geotech drawings typically begin with?
B
Name some tools and owner can ask the bidders to include in the bid documents to avoid unwanted cost increases during construction
Unit price
Bid alternate
Allowance
Cost plus
During a review of construction documents, if a project manager notices conflicting information regarding codes for the life safety sheet which codes take precedent? 
It depends architect should always design to the most stringent code restrictions
What should be avoided to ensure prompt payments by clients name three items
Sending Late invoices
Not following up on late invoices
Incomplete invoices
Name three requirements in architecture firm could be forced to fulfill in order to offer it services to the public
Corporate ID number
Certificate of authorization
LLC certificate
The general conditions of a contract for Construction require the contractors insurance policy to cover what four items
Damages to vehicles
Bodily injury at site
Injuries or damage after Contractor has left
Workers comp compensation
A cash flow statement does or does not contain information on cash equivalents?
CFS DOES show cash equivalents
The general conditions for a contractor requires the contractors insurance to cover what four items
Damage to vehicles
Bodily injury from the site
Injury or property damage after
Contractor has left the site
Workers compensation