Practice Management from Chegg Flashcards
(241 cards)
Construction Manager as constructor CMc-Characteristics not definition
single agreement w owner covering constructionwork broken up into pre construction phase and construction phasecan ONLY use cost plus fee w or w/o gmpused for quick construction time/ complicated building standards and materials or many unknownsoffers construction expertise, cost estimates and schedulingTime then cost and risk
Construction Manager as Adviser CMa-Characteristics not definition
Const Mngr can either be contractor or third party independent who represents owner CMa advises on construct ability No competitive bidding w CMa so price is higher
CMa 3 types of fee structures ??
Fixed Price or Stipulated SumCost Plus fee w gmpCost Plus w/ out gmpW fixed fee if project is under budget owner doesn’t benefitW cost +fee GC states gmp. If cheaper owner doesn’t benefit
AIA A701
Instructions to Bidders
AIA B101
Standard form of agreement between Owner and Architect
AIA C401
Standard form of agreement between Architect and Consultant
AIA A305
Contractor Qualification statement
AIA G701
Change Order
AIA G702
Application for certificate of payment
AIA G704
Certificate of Substantial Completion
Fast Track Delivery Method
Project uses multiple contracts Project uses a Construction MngrMore expensive but shorter loan funding quicker construction time frameUsed when schedule is very tightA and E drawings issued in stages or bid packages
Cost Plus Fixed Fee
used when a project is very complicated with many unknowns
Bridging
Hybrid between Design Build and Design Bid Build where Arch acts as PM or advisor to owner.
Design Assist Project Method
1 Sub contractor is included early to assist on a specific portion of the building2 Takes slightly longer so specific design details can be developed3 used in projects that are complex w vendors being used earlier
IPD Integrated Project Delivery
1 All team members work alongside one another from DD throughout move in. 2 Best design and efficient cost because everyone works together from beginning so there’s no adversarial relationships3 similar to Design Building except in IPD client can have multiple contractors when in DB only uses 1 prime contract4 Owner, end user, arch, engineer, GC and subs all involved early5 Shared Risk/Reward by all6 Indemnification of litigation for those on project team
CMa vs CMc
Construction manager as advisor price can go higher because design work is not completedCMc can only price project using cost of work plus fee w or w/out gmp
GC insurance requirements are located in which AIA Document
A201 General Conditions
Construction Manager as Advisor and Architect work together as……
A Joint Enterprise
CM Advisor is in charge of ….
Schedule and change orders
In Bridging (DB/DBB) Architect acts as an…..
Agent or Project Manager to owner
Net Billings are exclusive of??
Expenses and Consultants
Design Bid Build
1 Linear method 2 lowest bid wins3 lesser quality construction and longer timeframe4 natural conflicts
Design Build
Experienced owner due to establishment of performance and quality parameters Typically Contractor control w Architect contracted underneath Design packages sometimes phased to move fasterArchitect has les control over design due to subs and GC being engaged early w expertise in their areas
Uses form C-441
AIA A133
CMC scope of work and responsibilities