Practice Management from Chegg Flashcards

(241 cards)

1
Q

Construction Manager as constructor CMc-Characteristics not definition

A

single agreement w owner covering constructionwork broken up into pre construction phase and construction phasecan ONLY use cost plus fee w or w/o gmpused for quick construction time/ complicated building standards and materials or many unknownsoffers construction expertise, cost estimates and schedulingTime then cost and risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Construction Manager as Adviser CMa-Characteristics not definition

A

Const Mngr can either be contractor or third party independent who represents owner CMa advises on construct ability No competitive bidding w CMa so price is higher

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CMa 3 types of fee structures ??

A

Fixed Price or Stipulated SumCost Plus fee w gmpCost Plus w/ out gmpW fixed fee if project is under budget owner doesn’t benefitW cost +fee GC states gmp. If cheaper owner doesn’t benefit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AIA A701

A

Instructions to Bidders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

AIA B101

A

Standard form of agreement between Owner and Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

AIA C401

A

Standard form of agreement between Architect and Consultant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

AIA A305

A

Contractor Qualification statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

AIA G701

A

Change Order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

AIA G702

A

Application for certificate of payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

AIA G704

A

Certificate of Substantial Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Fast Track Delivery Method

A

Project uses multiple contracts Project uses a Construction MngrMore expensive but shorter loan funding quicker construction time frameUsed when schedule is very tightA and E drawings issued in stages or bid packages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cost Plus Fixed Fee

A

used when a project is very complicated with many unknowns

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Bridging

A

Hybrid between Design Build and Design Bid Build where Arch acts as PM or advisor to owner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Design Assist Project Method

A

1 Sub contractor is included early to assist on a specific portion of the building2 Takes slightly longer so specific design details can be developed3 used in projects that are complex w vendors being used earlier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

IPD Integrated Project Delivery

A

1 All team members work alongside one another from DD throughout move in. 2 Best design and efficient cost because everyone works together from beginning so there’s no adversarial relationships3 similar to Design Building except in IPD client can have multiple contractors when in DB only uses 1 prime contract4 Owner, end user, arch, engineer, GC and subs all involved early5 Shared Risk/Reward by all6 Indemnification of litigation for those on project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

CMa vs CMc

A

Construction manager as advisor price can go higher because design work is not completedCMc can only price project using cost of work plus fee w or w/out gmp

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

GC insurance requirements are located in which AIA Document

A

A201 General Conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Construction Manager as Advisor and Architect work together as……

A

A Joint Enterprise

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

CM Advisor is in charge of ….

A

Schedule and change orders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

In Bridging (DB/DBB) Architect acts as an…..

A

Agent or Project Manager to owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Net Billings are exclusive of??

A

Expenses and Consultants

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Design Bid Build

A

1 Linear method 2 lowest bid wins3 lesser quality construction and longer timeframe4 natural conflicts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Design Build

A

Experienced owner due to establishment of performance and quality parameters Typically Contractor control w Architect contracted underneath Design packages sometimes phased to move fasterArchitect has les control over design due to subs and GC being engaged early w expertise in their areas

Uses form C-441

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

AIA A133

A

CMC scope of work and responsibilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Architect led CmA
1 Fee structure is Gmp, hourly or lump sum 2 Faster completion time3 Big financial rewards4 Risk then Quality
26
Architect led Design Build
Greatest risk to Architecture firm running design, project management and construction. Form C-441 is used Risk then Cost
27
Stages of Development
Feasibility studies and Acquisition, design, financing construction , marketing and leasing. Then operations and management
28
D200
Project Checklist
29
Net Cash Income =
Received Cash minus spent cashRC-SC
30
Net Profit Formula is?
Recieved Cash minus Spent Cash
31
Total project fee =
Net Architect fee plus all consultants. Then take just consult fee and divide into total project cost. Should be (26-35%)
32
Finding Break Even cost of employee??
Net Revenue / TL =Multiplierthen MultiplierxEHR
33
*Net Operating Revenue Formula is?
Fees billed plus reimbursable expenses minus outside consultants minus project related expensesFB+RE-OC-PE
34
Total Expenses include what within a firm? Formula
Employee salary plus Over Head ES+OH
35
Utilization Rate Formula is?
TDL / TL
36
Break Even Rate Formula is ?
Overhead Rate plus 1
37
Break Even Rate calculates ?
Total cost of operations per dollar spent on direct laborTCO:1$ on DL
38
***Overhead Rate Plus 1 gives you what?
Break Even Rate
39
Overhead Rate Equals??
Total Indirect Expenses divided by total direct laborTIE/TDL
40
Utilization Rate Formula is?
Total Direct Labor divided by Total Labor
41
GMP Guaranteed Maximum Price
Used when scope clearly defined Cmc prepares cost estimate the he gets paid at end of construction
42
Unit Prices
Used w unknown site conditions existised for excavation work or projects w repetitive systems (hotels)
43
Cost plus fee
Used when owner doesn’t know exact scope of his needs and design services early in project so construction can move forward
44
Stipulated Sum
Used at the end of a competitive bidding process for a public funded project this is fee owners agree to pay
45
Net Multiplier Formula is?
NOR divided by total direct labor
46
To find % of TDL to NOR
TDL divided by NOR
47
AIA B105
Agreement for small residential projects
48
AIA B104
Agreement for small to midsize project’s limited scope and complexity
49
AIA B101 & B103
Agreement for midsize to large projects and more complicated
50
AIA B200
Scope of Services Document
51
Aia B103
Contains good cautionary language for the fast track project delivery method
52
Construction Manager as Agent
like Cm Advisor they may just assist w constructability of a project but may also work during construction. Typically work for a fixed feeRisk then time are main focus
53
Current Ratio Formula is?
Total current assets divided by total current liabilities. >1 is healthyTCAss/TCL (short term/quick)
54
Solvency Ratio
Total Current Assets/Total Current Liabilities over Long Term
55
Statute of Limitations begins? Statute of repose begins?
A statute of limitations is usually triggered when the defect is discoveredUsually, the statute of repose begins on the date of substantial completion
56
Primary and Secondary Concerns for DBB, DB, CM Advisor, CM Agent, CMC
Design-Bid-Build: Cost (Primary) and Risk (Secondary)Design-Build (Standard): Risk (Primary) and Cost (Secondary)CM-Adviser: Risk (Primary) and Quality (Secondary)CM-Agent: Risk (Primary) and Time (Secondary)CM-Constructor: Time (Primary) and Cost and Risk (Secondary)
57
Profit and Loss Statement utilizes what ratios
Utilization, profit to earnings, Net Multiplier and Overhead rate
58
Healthy Overhead Rate is
1.3-1.5
59
A141
Form of agreement between owner and design builder
60
What is NOR per Employee
Total Revenue/ # Employees
61
Definition of overhead rate
Measures the cost of operations
62
Definition of utilization rate
Amount of employees available hours used for billable projects
63
Definition of net multiplier
Represents the actual revenue generated by a firm
64
Definition of break even rate
Measures total cost of operations per dollar spent on total direct labor
65
Net operating revenue Formula
Fees Billed plus reimbursables minus outside consultants minus project expenses
66
Profit to earnings ratio definition
Indicates effectiveness of firm and completing projects with a profit
67
Definition of net operating revenue per employee
Shows how much each architect is bringing into the business
68
**P/E Ratio Formula
Profits / Net Operating Revenue
69
Which ratios are found on a profit and loss statement
Utilization RateP/E RatioNet Multiplier Overhead Rate
70
Quick Ratio Formula
Total cash + acct receivable + Revenue divided by total liabilities TC+Acr+R/TL
71
(3) tiers in AIA Code of Ethics
ethical standards, cannons, Rules of Conduct
72
Accounting method used by sole practitioner
Cash basis report
73
S Corporations 3 characteristics
Limited to 100Does not pay income taxes stockholders may be personally liable for negligence
74
AIA 195
Standard agreement between owner and contractor for Integrated Project Delivery
75
AIA A101 SP
Owner Contractor agreement for Sustainable Projects
76
AIA A102
Owner Contractor Agreement for cost plus fee w gmp
77
AIA A103
OWNER CONTRACTOR AGREEMENT FOR Cost plus fee w no gmp
78
Healthy Net Multiplier is greater than what #?
> than 3
79
AIA A132
AIA Contract CM as Advisor
80
Grossing Factor
Rentable area / Usable Area
81
How to convert a Net Multiplier into break even rate?
Overhead rate +1 is break even break even divided by inverse (opposite) of target profit %
82
Negotiated Bid gets you higher? Competitive bid gets you lower ?
Quality cost
83
Which term represents the most temporary working agreement
Strategic Alliance or Joint Venture
84
Examples of Pass through tax entities
LIMITED LIABILITY CORPORATION AND LIMITED LIABILITY PARTNERSHIP (both pay taxes separately from corporations
85
Profit and Loss Statement Formula
Fees Billed - Outside Consultants
86
3 Indicators found on a Balance Sheet
Liquidity, Return on Equity and Current Ratio
87
What is SPI? How is it calculated?
Scheduled performance index. TCFx%C = X then Fees of /X Total contract fee times percentage complete =X Then fees paid / X
88
What is a responsive bid?
Responsive Bid is a bid that covered entire scope of work in their bid 
89
What should contractors include w application for payment? 
Change order summary $ for completion of project Retainage in place Retainage for stored materials Certificate subs paid 
90
What is used by most firms for profit and loss statements?
Accrual Basis Accounting 
91
Cash Basis Accounting vs Accrual Basis Accounting. Compare. Which is for day to day and which is for taxes?
Accrual day to day, cash for taxesCash is like checking account money in then money received accrual counts money billed but not yet received 
92
Current earnings are earnings that are calculated before or after tax deductions
calculated after taxes are deducted from income?
93
What is the fee for an architect time called
Net Billing
94
Compare a prospect job and a suspect job
A prospect job is a job you have more than 50% chance of getting suspect is less than 50% chance
95
A balance sheet has what measures within it?
Solvency, liquidity, leverage and return on equity
96
Solvency ratio is the same thing as this type of ratio
Current Ratio. Same ratios, but current is for shirt. Short term solvency is long-term.
97
Solvency ratio should be in the neighborhood of ??
Solvency rate should be min 1.5 meaning assets are 50% more than liabilities 
98
Liquidity is also known as ——— ratio. 
quick ratio. 
99
What is a pro forma?
A business plan
100
Government projects would typically use what fee structures?
Stipulated Lump Sum or % of construction 
101
Assets are???
Assets are $$$$ quickly converted to cash (computers, furniture,accounts receivable) 
102
Equity is ???
Equity is  Assets minus liabilities equals balance (balance sheet) 
103
How do i file an ethical complaint against an architect?
Through National AIA ethics council 
104
Most ethical complaints are from???
Most ethical complaints are from other architects and homeowners
105
Efficiency type projects are???
Efficiency type projects are cookie cutter non complicated projects lots of junior staff
106
Experience type are ???
Experience type are hospitals, data centers, hotels, etc more complicated and more talented staff 
107
Expertise type firms are???
Expertise type deep knowledge and exceptional talent. Top heavy w talented staff 
108
Architect does/does not have fiduciary duty to owner?
Architect does not have fiduciary duty to owner?
109
What phase does the Architect provide cost estimate?
SD DD CD
110
When is Retainage money paid from owner
After substantial completion
111
Standard Architect services include ?? At 1 year after substantial completion
Standard Architect services includes visiting site 1 year after substantial completion
112
Per B101 if there is a conflict the sequence is what?
Mediation then court system unless specified otherwise in contract
113
Is the decision rendered by the IDM legally binding
NO.
114
General Contractor Cost of work includes what? 
Contractor materials, contractors labor, contractors profit and contracts overhead 
115
AIAB101 allows for consequential damages or liquidated damages.
Liquidated Damages
116
What are the differences between the Liquidated Damages and Consequential Damages
Liquidated damages are a cost of the delay per day of the delay caused by the contractor agreed on before the project. consequential damages are any additional cost that could have been impacted. Consequential are loss of “potential business” if u had moved in on time 
117
An overlay district may offer a density bonus for using what?
Photovoltaics
118
who approves a planned use development
Zoning Board
119
PUD is initiated by who? Overlay is initiated by who?
Pud-Developer initiative Overlay - City Initiative
120
Master format classifies by ?
Materials
121
Free float time is delay of an ___________ activity. Total float time is total slack available for ________ project
Individual Entire Project
122
What are developed as part of programming phase?
Adjacencies. Budget. Project Goals. Building types
123
Describe Plat vs metes and bounds survey.
Plat (cities) Metes and Bounds (rural or ancient) 
124
Life cycle analysis reviews ???
Life cycle analysis reviews impacts from raw material extraction through installation and maintenance 
125
Life cycle costing is ???
Life cycle costing is economic analysis used in selecting alternates
126
Life cycle costing is a ???
Life cycle costing is a one time decision 
127
Architect should design for ???
Architect should design for safety health welfare and human dignity 
128
Net worth = ??
Net worth = Assets minus Liability 
129
Cash flow statement show ???
Cash flow statement show the month to month financial situation of affirm
130
Project Manual includes what??
Project Manual includes bidding rqmts, contract info, general conditions and specifications 
131
If during a bid a GC wants to introduce a cheaper material they can request a ???
Substitution
132
When should an Architect issue an addendum?
Before owner contractor agreement is finalized
133
Limited partnerships Don’t employ?
officers or directors 
134
Architect and Contractor must sign a?? prior to commencing a project 
memorandum of understanding prior to commencing a project 
135
How do you increase Net Multiplier? By Increasing the ?? and increasing ??
By Increasing the overhead rate and increasing target profit percentage 
136
??? /??? =Net Multiplier 
Break Even Rate (OH+1) /Opposite Target Profit %=Net Multiplier 
137
If a Building comes in over budget what costing method requires the Architect revise drawings at their own expense?
% of construction cost method
138
If an architect instructs on Construction means and methods, he is violating the ?
B101
139
what requires Architects assist interns in obtaining licensure ??
AIA code of ethics
140
The best fee structure for a hotel or any unit based construction project is ??
Stipulated Sum
141
In order to find A firm’s liquidity you are actually looking for its??
Quick Ratio (Total Cash + Acct Receivable plus revenue billed / Total Liabilities)
142
How do you find Target Profit Percentage?
Break Even Rate / Net Multiplier (then use opposite for inverse)
143
If your main concerns are employees, that can someday run your company and tax liabilities. What is your preferred business structure? limited liability, corporation or C corporation
C Corporation
144
If an Architect has responsibility to do something it’s what type of ethics?
Duty
145
If an Architect follows rules codes and laws it’s what type of ethics?
Contract
146
If an Architect must consider outcomes it’s what type of ethics?
Results
147
If an Architect is being pressured or stressed, showing self control it’s what type of ethics?
Character
148
A Operating budget plan includes what items
Fees billed, billed reimbursables, consultants and project related expenses
149
Profit and Loss Statements formula??
Fees Billed minus outside consultants
150
The equal pay act, Erisa, National Labor Relations, osha requires how many employees be a part of the company?? Age discrimination, and civil rights act require how many employees be employed?? family leave act requires how many employees be employed before its active??
0…..15…….50
151
A general obligation bond is backed by who and by what type of revenue
 city or state and general tax revenue
152
What is a tort?
It’s a civil claim against another party due to injury
153
What governs architecture?
Regulations
154
What types of insurance does a B101 require the architect to obtain?
Professional liability, automobile, general liability, and Worker’s Comp.
155
Using a top down budget approach on a new project would be using what??
Historical data from a similar project with similar scope
156
What are two essential components of a financial management system?
Annual budget and profit plan
157
B 105 is for what?
Small residential projects
158
In a C corporation, business owners pay taxes _________ from their shareholders
Separately
159
What is a statute??
A written law
160
What is a restrictive covenant?
Restricts the use of a property. It’s enforceable if it’s in the interest of the public.
161
What laws would impact both large and small firms?
The equal pay act, osha, Employee Retirement Act and National Labor Relations Act
162
ABI index is typically in what ranges
Contraction 40 to 45 Late contraction 45 to 50 Late expansion 50 to 55 Early phase recovery 55 to 65
163
In order to minimize the sheets in a construction document set, an architect can recommend???
Reduction of redundancy Default scheduling Instructional systems
164
What do outline specifications provide?
Material description, product, data, and quality level
165
What is a canon?
It’s a broad principle of conduct
166
Which document protects the architect from copyright infringement
It’s the a 201 general conditions
167
Gantt Chart is what??
Describes different tasks and resources Overview of project
168
Critical Path Chart
Longest sequence of events that must be finished on time in order for entire project to be completed. Calculates the complete project duration based on time it takes to complete individual tasks. Delay in Critical Path delays entire project
169
Calculating Cubic Yards??
Length x Width x Depth (inches/12) Divided by 27= X cost per cubic yard
170
Break Even Multiplier
Overhead + Total Direct Labor +1
171
Overhead Multiplier
Overhead/Direct Labor
172
Negotiated Select Team
Subset of DBB but fabrication starts early and prioritizes quality then cost
173
Direct Salary Expense Multiplier
Net Revenue/Direct Salary
174
Revenue Factor? (New) also called payroll multiplier.
Utilization Rate X Direct Salary Expense Multiplier (DSEM IS Net Revenue /Direct Salary
175
Davis Bacon Act
Prevailing Wages and Public Works
176
Slowest type of Bid
Invited Bid
177
What protects owner from defaulting Contractor (2)
Bid Bond or Performance Bond
178
Contractor warranty length is typically?
1 year
179
Public space is considered ## Ft?
>25 ft
180
Net profit equals??
Profit minus operating expenses minus taxes
181
LLC Describe
Max Flexibility, No board directors required, unlimited owners, no personal tax liability, cannot go public Requires operating agreement
182
S Corporation
US Resident, small corporation, <100 people, Not liable for business liability, Requires board of directors, Many Rules
183
C Corporation Describe
Can go public, unlimited ownership, not personally liable, board of directors, admin Rules
184
Sole Proprietorship describe?
Easy set up, no paperwork, one owner, personally liable, no protections
185
What are the three tiers of a corporation?
Stockholders (owners), Directors and officers
186
Chargeable Rate Formula??
(Salary) * (Break Even Multiplier) + Profit = Chargeable Rate
187
Change Order
Issued when GC Owner and Arch all agree on changes that alter scope cost or schedule
188
Construction Change Directive
Issued when GC Owner and Arch do not agree on changes that alter scope cost or schedule but work needs to proceed
189
How many gallons per cubic ft of water
7.5 gallons
190
How to convert inches to feet?
1ft / 12” then multiply by inches noted in question
191
Chargeable Rate Formula
Salary x Break Even Multiplier + Profit
192
Wall schedule CPM Schedule Bar Ghant Chart Milestone chart
Wall- Suited for medium to large scale complex projects. Integrates tasks for all parties and is very flexible CPM- Larger and more complicated projects. Critical path, schedules, activities, durations, and dependencies between activities. Bar/Ghant- Most often used easy. Work is broken down into Rows on the left-hand side with start and end dates. Milestone - easiest type of schedule
193
How many days does an architect have to dispute a consultant invoice from receiving it?
10 days
194
If size and budget are not yet established what type of fee structure is most ideal?
% of construction
195
Cost of construction work to owner should exclude what?
Land Acquisition, Architect fees and Contingencies
196
What is negotiated select team?
A hybrid of design bid build in which quality than cost are the main driving factors fabrication starts early
197
What is the complete order of a project from beginning through completion?
RFP, architect selected, pre-design, schematic design, design development, construction document, bidding, contract awarded, Construction administration, punchlist, certificate of occupancy, substantial completion, final completion
198
Describe the difference between open specification, proprietary, and descriptive specifications
Open specifications allow 3 to 5 appropriate materials or products. Contractor can use any of them if the performance is matched. Proprietary specifications require a specific material or product to be listed and there are no substitutions allowed Descriptive specification all of the components products and their arrangements are described
199
Describe the difference between performance reference and cash allowance specifications
Performance specifications are similar to open specifications, except instead of listing the specific manufacturer, new list, performance expectations, and requirements Reference specifications require a certain standard or requirement to conform to a specific testing authority Cash allowance is just that specific dollar amount that allows a product or system to be proposed if it has not yet been completely figured out
200
If an owner stops paying an architect, the architect can write the owner saying that they have X amount of days to pay or Services will be stopped. Both owner and architect can terminate the contract X days after written notice to the other party that the agreement has been violated. The architect also has the same amount of time to dispute the contractors application for payment.
7 Days
201
If the contractor discovers contaminated soil or asbestos as a concealed existing condition that will change the project, he has X amount of days to tell the owner and the architect. Also, if the architect thinks one of the subs of the Contractor is incompetent or unqualified, the architect has X amount of days to notify the contractor of their objection.
14 Days
202
The owner’s final payment to the contractor is due maximum amount of days after the architect issues the final certificate of payment
30 Days
203
The Architects construction administration services ends X amount of days after substantial completion. Also, if a dispute arises between the owner and architect the claim will sit in mediation for amount of days before advancing to arbitration or litigation.
60 Days
204
If the owner pauses a project for more than X amount of days, the architect can terminate or renegotiate the contract
90 Days
205
Independent float time accounts for what in the schedule
No slack No delay
206
What is retainage?
Money that is owed to the contractor, but intentionally not paid until after substantial completion
207
Schedule of values is controlled by which party
General contractor values are for drywall studs, HVAC foundation, etc.
208
What type of insurance protects your Firm from a wrongful termination suit
Employment practice liability insurance
209
Contractual liability is normally covered under what type of insurance
General liability insurance
210
Matters affecting basic, legal rights and responsibilities of parties to a contract should be handled within what AIA document
The supplementary conditions
211
What do privity laws protect against?
Lawsuits between parties that have no contract. Direct relationships are required.
212
What is the easiest type of corporation to set up?
LLC
213
Project cost accounting tracks what
Revenue expenses, and profit by individual project
214
Project cost accounting tracks what
Revenue expenses, and profit by individual project
215
What does an office earnings report summarize?
Revenue generated, expenses incurred, unbilled services, percentage of completion and profit
216
What does an office earnings report summarize?
Revenue generated expenses, incurred unbuild services, percentage of completion and profit
217
Which document requires the architect to maintain professional liability insurance
B101
218
What’s the difference between professional liability insurance property insurance, and personal Injury insurance?
Professional liability protects the architect against mistakes in the drawings or injuries caused by mistakes in the drawings property insurance protects the Architects building against physical damages, fire, theft, flood, etc. personal injury protection protects the architect from libel, slander or defamation attacks
219
What’s the difference between professional liability insurance property insurance, and personal Injury insurance?
Professional liability protects the architect against mistakes in the drawings or injuries caused by mistakes in the drawings property insurance protects the Architects building against physical damages, fire, theft, flood, etc. personal injury protection protects the architect from libel, slander or defamation attacks
220
Owners insurance requirements are located in which document
A201 general conditions
221
Describe type of maps. Which shows boundaries and ownership? Choropleth, Satellite, Cadastral and Thematic
Choropleth, Census Map Satellite, Aerial Images Cadastral boundaries and property ownership Thematic socioeconomic status
222
Under what business format is an operating agreement required
LLC
223
Schedule of performance is provided by whom. Schedule of values is provided by home.
Performance is provided by architect Values is provided by Contractor
224
Are S corporations and C corporations taxed double or not?
S corporations are not taxed double C corporations are taxed double
225
Describe Type 1A Construction
Commonly found in high-rise buildings Three hour exterior wall three hour structural frame 2 hr floor ceiling
226
Describe 1B Non Combustible Construction
Typically found in mid rise office building and group R buildings 2 hr exterior wall 2 hr Structural frame 2 hr Ceiling floor assembly 2 hr Ceiling roof assembly
227
Describe type 2A protected noncombustible construction type
Typically found in newer school buildings 1 hr exterior walls 1 hr structural frame 1 hr floor/ceiling roof protection
228
Describe Type 2b unprotected noncombustible construction
Typically used in commercial buildings Usually constructed of non-combustible materials, but materials have no fire resistance
229
In construction manager as constructor delivery format, when does construction administration begin?
control estimate. Approved contractors GMP approved notice to proceed.
230
A restrictive covenant is implemented why?
To protect property owners
231
Explain Type 2B Construction
Most common in commercial buildings. Non combustible materials but materials have no fire rating brick block cmu
232
Explain Type 3A construction
Ordinary construction w brick or block walls Ext 2 hr Struct frame 1hr Roof flooring wooden ceiling 1hr
233
Explain Type 3B construction
Unprotected combustible also known as ordinary construction brick or block walls w wooden roof and floor assembly which is not fire protected 2 h exterior walls No other ratings
234
Explain Type 4 construction
Heavy Timber all wooden members must be 8” nominal dimensions Exterior 2hr Structural frame 1 hr No ratings on for ceiling
235
Explain Type 5A construction
Protected wood frame no visible wood Exterior 1 hr Structural frame 1 hr Floor and ceiling 1 hr
236
Developing a project budget using a top down approach would mean using what
Historical data from a project of similar scope and size
237
What are the three delivery types that allow pricing to be established before construction documents are started
Construction manager as constructor Design Build Bridging, hybrid design build
238
What document defines design services as being standard services versus additional services
AIA B101
239
Describe the difference between SD phase and DD phase
In SD phase, typically you have floor plan reflected ceiling plan roof plan, elevations a few sections, possibly site plan in a narrative of possible building systems In the DD phase, by the end of it, you should have the layout refined building systems, selected scope, size and scale should be nearly completed
240
Design quality during programming can be controlled using what for variables?
Controlling cost per square foot Grossing factor net assignable areas budget
241
How long after a project is completed does an architect need to retain the added insurance required for the project?
Years