Quantification and costing of Construction Works Flashcards
(51 cards)
What are the various types of pricing documents?
- Bill of Quantities
- Activity Schedule
- Milestone Schedule
- Schedule of Rates
What are the different forms of obtaining prices for works (contract price mechanisms)?
- Fixed Price lump Sum
- Re-Measurable
- Target Cost
- Cost Reimbursable (Cost Plus)
- Guaranteed Maximum Price (GMP)
What is a Fixed Price Lump Sum Contract?
A firm price is agreed between the parties to deliver works by which only changes to the price can be made through implementation of variations or claims.
What is a Re-measurable contract?
Where the rates are pre-agreed and used in calculating the cost of the quantities which are re-measured and reassessed against the original approximate quantities to determine the increase or decrease of the contract price.
What is a cost reimbursable/ cost plus contract?
The contractor is paid for works delivered properly and reasonably in performing the obligations under the contract. The contractor is paid for the cost incurred, plus their OH&P.
When is a cost reimbursable/ cost plus contract best suited?
When quick mobilisation is required to deliver the works as soon as possible, and design certainty is not present and cost certainty is least in priority.
How does a Target Cost contract operate?
A target is set by the parties and is managed through variations or claims in regards to increases or decreases. The contractor is paid through actual cost incurred in providing the works, plus fee. If the actual cost is below the target, both parties receive gain share in the savings, however if it is above the target both parties would be liable for the overspend.
When is a Target Cost contract best placed to be used?
- When a start on site is needed soon
- Risks are not well defined or unknown
- Incentivises/ penalises the contractor in regards to cost management
What is a Guaranteed Maximum Price (GMP)?
There is a maximum ceiling of the contract price and any savings below the GMP is shared between the parties. The risk of overrun on the GMP is held solely by the Contractor. The GMP is only adjusted based on accepted variations or claims.
What are the benefits and limitations with GMP contracts?
Benefits:
- Provides greater cost certainty than target cost
- Incentivises the contractor in coming below the GMP
- The contractor takes on all risks
Limitations:
- The GMP may be high due to all of the risks priced by the contractor
- The ER and scope will need to be well defined to avoid any potential variations
What are some of the risks associated to projects which span over multiple years?
Inflation, Overheads and Exchange Rates.
What are some of the factors which affect OH&P?
- Project location
- Project type
- Market conditions
- Tenderer’s direct and indirect overhead costs
What are Prime Costs?
Rates or costs contained under a BoQ where it is needed in part, i.e. supply only, or installation only, exclusive of OH&P.
What are Preliminaries?
Costs associated with the management of the works, i.e. management staff, site accommodation, plant, etc.
What are some of the factors influencing preliminaries costs?
- Project location
- Project duration/ programme
- Complexity of project
- Value of project
- Level of temporary works
- Time related, mobilisation and demobilisation costs
What are some of the validation checks which can be conducted on a preliminaries cost submission?
- Market testing
- Benchmarking against similar schemes
- Utilising previous estimates, rates and cost plans
- In house cost databases
What is the typical percentage cost of preliminaries?
Typically 11-15% on the construction cost. If higher there may be reasons behind this such as:
- Tower cranes
- Night time/ weekend working
- Road closures/ rail possessions
- Re-routing main services
What is inflation?
The increase of prices due to the economy of a country.
How is inflation considered under construction projects?
Under cost plans or contracts inflation can be factored in. Indices can be used to determine the uplift needed to predict inflation.
What is tender inflation?
The increase in prices between the PTE and the tender return
What is construction inflation?
The increase in prices from the date of tender return and peak of the construction period.
What is Tender Price Index?
Indices which measures the inflation adjustment needed to uplift the tender return prices to current day economic conditions.
How is inflation estimated as per NRM?
Inflation estimate = Tender Inflation + Construction Inflation
If quantities cannot be measured at the point of tender what should you use?
- Utilise approximate quantities, if there are many uncertain quantities there is merit in using a re-measure form of contract.
- If there are a few, then utilise Provisional Sums