Quantification & Costing Level 3 Flashcards
1
Q
On the Rugby Project, how did you undertake the RIBA Stage 0 estimate?
A
2
Q
On the Rugby Project, what information was available at RIBA Stage 1 to enable you to compile a cost plan?
A
3
Q
On the Stillorgan project, you state that a schedule of works would not have been appropriate. Why was that the case?
A
4
Q
On the Wakefield Pharmacy Project, what did the daywork rates cover?
A
5
Q
On the Wakefield Pharmacy Project, how did you determine the OH&P uplift applied? Was it stated in the contract?
A
6
Q
On the Wakefield Pharmacy Project, had the OH&P not been stated in the contract, how would you advise it be determined?
A
7
Q
Can you provide an example of advising on the appropriate method of measurement?
A