Resource Management Flashcards

(9 cards)

1
Q

What supports the creation of a project RACI?

A
  1. Organisational breakdown structure
  2. Work breakdown structure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When is resource levelling most appropriate?

A

Resource levelling is used where a fixed amount of resource is available and the project can be delayed.
I.e. with the available resource, when will the work be finished?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When is resource smoothing most appropriate?

A

Resource smoothing is used when time is more important than cost.
I.e. what resources do I need to deliver the work on time?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the different types of resources?

A
  1. People
  2. Materials
  3. Facilities
  4. Equipment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the difference between resource smoothing and levelling re. project end date?

A

Resource smoothing prioritises the end date of the project.

Resource levelling may change the end date (i.e. cause an extension)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the key considerations for determining resources?

A
  1. Chosen lifecycle
  2. Skills and capabilities required
  3. When resources are needed
  4. How long resources are needed
  5. Type of resources required for each activity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a RAM or RACI?

A

A RAM or RACI is a communication device to ensure that people working on a project are aware of their role and the work they have to do.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the benefits of a RAM/RACI?

A
  1. Clarifies roles and responsibilities
  2. Streamlines resource allocation
  3. Supports effective task delegation
  4. Serves as a point of reference for the project team
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the benefits of identifying and scheduling resources?

A
  1. Ensures required resource is available when needed
  2. Ensures resource is allocated effectively
  3. Maximises productivity
  4. Reduces risk of overspend
  5. Improves stakeholder/team coordination
How well did you know this?
1
Not at all
2
3
4
5
Perfectly