Contract Practice Flashcards
(41 cards)
What are the key differences between JCT Design and Build contracts and Traditional JCT contracts, and when would you recommend each?
Traditional Contracts are when the project is fully designer before being tendered.
This generally places greater risk on the client as if errors are found in the design it is theirs to bare.
In design and build, the project can be tendered at an earlier stage, such as stage 3 and will give the contractor design elements, such as connection details for structural or mechanical elements.
Contractors will include a risk allowance as they take hold of the Employers requirements and if errors are found in these then it is the contractors to bare.
Can you explain the main differences between JCT and NEC contracts in terms of their approach to risk allocation?
JCT’s generally assigned clear roles and responsibilities at the beginning of a project which are arrange by the client.
This can potentially make project adversarial compared to NEC which looks to take a more collaborative approach to risk in the form of risk management during the construction.
What are the essential components that should be included in the Employer’s Requirements for a JCT Design and Build contract?
The EA’s themselves,
Drawings
Structural information
Mechanical information
Surveys
Planning documents
Health & Safety information.
How would you explain the purpose and function of a Contract Sum Analysis in a Design and Build contract?
It provides a clear and transparent breakdown of the contractors costs and forms the basis for the interim valuations.
What are the key considerations when drafting and issuing a Letter of Intent, and what are the risks associated with using them?
The clarity of the intent and the scope of works to be conducted during the period.
The payment terms must also be clearly set out and agreed by all parties.
If not clearly set out the risk is that this could lead to disagreements with the contractor.
What happens when a client side consultant is novated to the contractor?
There is a contractual transfer with the consultant from the client to the contractor.
This in turn creates a liability shift as the contractor assumes responsibility for the entirety of the design produced by that consultant.
What is the benefit of novation?
It creates a continuity of the design specification and transfers the risk from the client to the contractor.
It may also improve communication as the contractor manages both design and construction.
What is the difference between novation and assignment?
Novation transfers rights and obligations, whereas assignment only transfers rights.
Novation creates a new contractual link, whereas assignment retains the original.
What is a loss and expense claim?
This is when a contractor faces direct loss due to a client driven event,
The contractor must provide written notice to the client as soon as it is apparent loss and expense will be incurred due to the event.
The costs incurred can be direct loses, prolongation costs and disruption costs.
Direct loses are elements such as labour, materials, prolongation costs are costs associated with the extended programme, such as site management.
What is meant by the term Quantum Meruit?
Where services have been provided and payment due where no contractual agreement is in place or when work has occurred beyond the scope.
What is a Relevant Event and Relevant Matter and how do they impact the project?
A Relevant Event causes a delay to the completion date and entitles the contractor to an extension of time,
Examples of a Relevant Event are,
Adverse weather
Force Majeure
Delay in giving the contractor possession
Terrorism
A Relevant Matter is when the client causes a delay which materially effects the progress of the works and entitles the contractor to cost.
Examples are,
Variations caused by the client
Delays in receiving instructions from the client
Delay in giving the contractor possession
Discrepancies in contract documents
What is the difference between a Relevant Event and a Relevant Matter in a JCT form of Contract?
They are events that entitle the contractor to an extension of time, a relevant matter entitles them to cost.
What is the difference between sectional completion and partial possession?
Sectional completion is planned from the outset and specified in the contract.
Partial posession occurs when a client wants to take posession of part of the works before practical completion.
What are some types of JCT Contracts?
Design and Build
Standard Building Contract
Intermediate
Minor Works
Major Projects
What is the difference between a Minor Works contract and Intermediate Contract?
A Minor Works Contract
- Simpler in it’s structure
- Suitable for straightforward contracts
- Generally used for projects up to £500k
- Payments are generally based on stage or monthly payments unless agreed otherwise
- Doesn’t allow for phased works
- Doesn’t allow for CDP’s
An intermediate contract is for projects which are more complex, but not appropriate for SBC, it allows for phased works and CDP’s.
- Suited for more complex projects
- Generally used for projects from £500k to £2m
- Payments are generally based on interim valuations
- Allows for phased works
- Allows for CDP’s
What is the value of a minor works contract typically?
Generally, less than £500k.
What is the value of a intermediate works contract typically?
Generally above £500k.
What are the fluctuation options under a JCT?
Option A - taxes, levies, statutory contributions
Option B - materials, labour
Option C - formula based adjustment
What is retention?
It is a percentage of each interim certificate deducted and retained by the employer from each interim payment to the contractor
What is the purpose of retention?
It provides an incentive for the contractor to rectify any defects within the contract defects liability period.
It provides some financial security to the employer in the event of a contractor default.
What is a retention bond?
This is a bond provided by the contractor in lieu of taking retention from interim payments.
It should be equal to the same value as the retention deducted.
The requirement for the bond should be stated in the contract particulars.
A standard form is provided in the JCT contract schedules.
What is a specified Peril?
Specified perils tend to be significant events that would cause very significant damage, such as fire, explosions, earthquakes, flooding and so on. All-risks insurance will tend to cover a broader range of risks, albeit it may not cover every possible risk.
What is subrogation?
A legal technique where the insurer steps into the shoes of the insured in order to take the benefit of any legal rights or remedies they may have against a third party responsible for the loss.
What does ‘joint names’ mean?
Where the employer and contractor are insured under the same policy.
It stops the insurer having the right of subrogation against the other party if they caused the loss.