Project Finance Flashcards

(31 cards)

1
Q

What are the key components that should be included in a comprehensive cost report?

A

Executive summary
Assumptions and exclusions
Cashflow
Summary of cost
Instructed Variations
Anticipated Variations
Early warnings
Direct works
Provisional Sums
Contingency breakdown

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How do you differentiate between a provisional sum and a prime cost sum, and what are the financial control implications of each?

A

A provisional sum is a cost for an item which is either defined or undefined in the contract.

A prime cost sum is the cost for materials or subcontracted work where the supplier is nominated by the client.

Provisional sums are paid based on the actual work incurred, whereas prime cost sum is the actual cost of the materials provided by the supplier via invoices.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a Monte Carlo Simulation?

A

A statistical method that runs multiple simulations to predict possible outcomes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How would you create a cashflow forecast?

A

I would need to have access to the construction programme and contract sum analysis and identify when packages would be bought and split out the values accordingly.

Obtaining drawdown schedules from specialist subcontractors and professional consultants can also assist when populating the cashflow.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the valuation rules under JCT Forms of Contract?

A

There are three rules for measurable work:-

If it is of a similar character, quantity and in the same conditions as existing work, then the bill rates should be used.

If it is of a similar character, but different quantity or conditions, the bill rates should be used as a basis but a fair allowance should be made to take account of the difference.

If it is not of a similar character, fair rates and prices should be used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How are non-measurable works valued under the JCT?

A

This would typically be valued by the dayworks procedure based on the cost of labour, plant and materials that have been incurred.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the benefit of a cashflow forecast?

A

It enables the client to understand the financial requirements of a project over a duration and set up funding requirements in advance.

It can also be used to check against valuations and helps to track the progress of the works on site against the contractor spending.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are variations?

A

Addissions, omissions or alterations to the design, quality or quantity of the contract works, site access or working conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why might a change arise?

A

Change to specification

Discrepancies between contract documents

Discrepancies with statutory requirements

Errors or omissions in the design

Missing information in the Employer’s Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Can a contractor object to a variation?

A

Yes, some contracts allow them to object to an instruction in special circumstances, for example,

In the JCT Standard Building Contract, the requirement to comply with a valid instruction is subject to certain exceptions, where,

The instruction might affect the efficacy of the Contractors Design Portions.

The instruction has an impact on the CDM regulations.

Where the instruction relates to a named specialist and the contractor is unable to enter into a contract with that firm.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What can the architect do if the contractor does not comply with an instruction?

A

This depends on the form of contract,

In the JCT Suites, if the contractor does not follow an instruction then a ‘notice to comply’ will be issued to the contractor.

If the contractor still does not comply, the architect can instruct another party and the contractor will be liable for any additional costs incurred.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What 3 methods are there of obtaining a cost for a variation under the JCT forms of contract?

A

This depends on the form of contract, for example in a Design and Build,

  1. Agreement
  2. Schedule 2 quotation
  3. QS valuation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the time periods for a Schedule 2 quotation under JCT Design and Build?

A

The contractor has 7 days to notify that they will not provide one,

The contractor must submit their estimate within 14 days of receiving the relevant instruction, unless agreed otherwise,

The client then has 21 days from receipt of the estimate to either accept or negotiate the amount.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What cost does the Schedule 2 quotation contain?

A

Value of the works

Money incured by direct loss and expense

Fair and reasonable cost of preparing the quotation

Contractors OH&P

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What cost is the contractor entitled to if the Schedule 2 quotation is rejected?

A

The fair and reasonable cost of preparing the quote, as long as the quote itself was fair and reasonable,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What information do you need to assess dayworks?

A

Time sheets.

Names of the individuals.

Plant and materials used.

17
Q

What are the procedures for claiming loss and expense under a JCT?

A

The contractor must make the client aware as soon as they know the loss is likely to be incurred or any other matters which will incur the loss and expense,

They should then submit any information as requested by the QS / Architect to enable the amount of loss and expense to be ascertained,

18
Q

What is the key thing to remember when assessing loss and expense?

A

It should be the actual loss incurred by the contractor.

19
Q

What are the common heads of claim in loss and expense?

A

Prolongation.

Thickening of preliminaries.

Disruption causing plant or labour to be underemployed.

Increases in labour or material costs during the period of delay.

Head office overheads.

Loss of profit.

Finance charges.

Acceleration costs.

Claim preparation costs.

20
Q

What 3 methods are there of obtaining a cost for variations under JCT forms of Contract?

A

Agreement between the parties.

A Schedule 2 quotation.

The Quantity Surveyors valuation.

21
Q

Explain what an S-curve represents in project cashflow forecasting and what factors might cause actual expenditure to deviate from it.

A

The S-Curve represents the natural rhythm of how construction projects develop over time with low expenditure in the beginning, to high cost elements (such as structural or M&E works), to costs tapering off as the project nears completion.

22
Q

How do you differentiate between a provisional sum and a prime cost sum, and what are the financial control implications of each?

A

A provisional sum is a cost for an item which is either defined or undefined in the contract.

A prime cost sum is the cost for materials or subcontracted work where the supplier is nominated by the client.

Provisional sums are paid based on the actual work incurred, whereas prime cost sum is the actual cost of the materials provided by the supplier via invoices.

23
Q

What are the fluctuation options under a JCT?

A

Option A - contributions, such as levies and taxed.

Option B - Labour and material cost fluctuations, including tax changes.

Option C - A formula based on cost indices

24
Q

What costs does the schedule 2 quotation contain?

A
  • Value of the work.
  • Any adjustment of time.
  • Money in lieu of direct loss and expense.
  • The fair and reasonable cost of preparing the quotation.
25
What are ‘fair rates and prices’?
* A market rate. * A rate based on actual costs. * A rate in line with current cost data.
26
What are dayworks?
The prime (actual) cost of all the materials, labour and plant used in carrying out the work, along with a percentage additions to each category as set out in the contract.
27
Can the QS alter hours which he considers to be excessive on a dayworks sheet that is authorised by the architect?
No the hours recorded and signed off should be maintained within the variation.
28
What is loss and or expense under JCT Forms of Contract?
L&E reimburses the contractor for direct loss and/or expense incurred in carrying out additional work or from an employer’s breach of contract.
29
What are the procedures for claiming loss and expense under JCT Forms of Contract?
* As soon as the regular progress of the work is affected, or is likely to be affected, or the contractor becomes aware of any other matter that would cause them to incur loss and expense, they should notify the architect in writing. * The contractor should submit any further information as requested by the architect. * The contractor should also submit any further information as requested by the Architect or QS to enable the amount of loss and expense to be ascertained.
30
What are Relevant Matters under JCT Forms of Contract?
Events listed in the Contract that entitle the contractor to loss and/or expense.
31
What are the relevant matters?
There are 5 relevant matters:- o Variations. o Instructions. o Execution of an approximate quantity that was not a reasonably accurate forecast of quantity. o Suspension by the contractor for non-payment. o Any impediment, prevention or default by the employer.