EOPS Flashcards Preview

NERC > EOPS > Flashcards

Flashcards in EOPS Deck (42):
1

Interruptible Load or Interruptible Demand

Demand that the end-use customer makes available to its Load-Serving Entity via contract or agreement for curtailment

2

BA's shall have operating agreements with who?

adjacents BA's, these contain provisions for emergency assistance including support from remote BA's (BA's that do not touch your BA boundary)

3

What is the primary objective of each BA during a capacity or energy emergency?

return ACE to an acceptable value

4

The development of emergency load reduction plan for all IROL violation is the responsibility of who?

TO

5

What are the 4 types of plans each TO and BA are required to develop, maintain and implement

Generation shortage capacity, transmission systems emergency, load shedding and system restoration

6

What are required to be in the plans

communication protocols, control actions (things that will resolve emergency), coordination with other BA's and TO's and staffing levels

7

each emergency plan is updated how often

annually, and plans are provided to RC and neighboring TO's and BA's

8

______ is the rated continuous load carrying ability of generation, transmission or other electrical equipment expressed in MW

capcity

9

What are the four things a BA must do prior to having an EEA declared

Bring on all available generation, postpone equipment maint., scheduling interchange purchases in advance, being prepared to shed firm load load.

10

When using voltage reduction for energy emergencies, what is the rule of thumb.

a 5% reduction in voltage results in a 3% reduction in load

11

When an EEA is issued what does the RC do?

Start actions to mitigate the emergency (request emergency assistance if needed) and notify all BA's and TSP in its area also notify all other RC's

12

There are two reasons an LSE would require an EEA

They cannot locate available resources to purchase and they cannot schedule due to available transmission limitations

13

Describe EEA1

all available resources are committed to meet firm load, firm transactions and reserve commitments and non firm wholesale sales have been curtailed.

14

Describe EEA2

no longer able to provides the customers expected energy requirements and has started procedures to make up the insufficient energy, like public appeals, voltage reduction, interruptible loads

15

Describe EEA3

firm customer load is being shed, during EEA3 the deficient BA must give hourly updates to the RC

16

What are the two types of automatic load shedding

undervolatge and underfrequency

17

describe undervolatge load shed

load shed that is designed to prevent local area voltage collapse from lack of reactive resources

18

describe underfrequency load shed

load that is shed to re-balance load and generation within an electrical island caused by a system disturbance

19

low frequency causes damage to what kind of turbine

low pressure blades in steam turbine

20

UVLS is designed to drop loads in

pre-selected blocks

21

Each Transmission Operator and Balancing Authority shall establish plans for automatic load shedding for __________ or ___________ conditions

underfrequency or undervoltage

22

Which entities has the responsibility to establish plans for load shedding

TO and BA

23

why are reports sent to NERC

to note lessons learned and implement corrective actions

24

timeframe an entity has to report to NERC

initial report is due 24hrs, except if it's an IROL violation then its 72 hours. final report due in 60 days

25

NERC reporting guildlines are

system sepration, firm load shed of 100mw or more, IROL violation, operator error, loss of generation, loss of BES component affecting system integrity, equip. failures or system operational actions resulting in loss of firm system demands for more than 15 mins.

26

define disturbance

An unplanned event that produces an abnormal system condition or any perturbation to the electric system or the unexpected change in ACE that is caused by the sudden failure of generation or interruption of load

27

entity experiencing a reportable incident shall provide a preliminary written report to

NERC & RRO

28

TO's shall have restoration plans in the event of partial or total system shutdown, plans must be....

updated to reflect changes, reviewed at least annually, developed for restoring interconnection and coordinated with neighboring systems

29

if load must be shed in an island and good rule of thumb is

shed 6-10% of connected load will increase frequency by 1hz

30

when restoring load in an island. how much load to be restored at one time.

5% of online generations capacity

31

if you are in a island trying to pick up load and there is one 1000 MW generator online generating 500MW, how much load could you pick up?

50MW, 5% of 1000

32

When re-synchronizing what are the 3 things that are measured

Phase angle. voltage and frequency...if possible phase angle should be 10 derees or less

33

what are some things an operator can do when syncing two islands together when there is a large phase angle

re-dispatch generation, change system configuration, shed load

34

True or False: the RC is required to have an RC area restoration plan

True

35

What document must RCs sign because of market transaction

NERC Reliability Coordinator Standards of Conduct

36

Re-synchronizing with the interconnection should only be attempted where

breaker with sync check or generating plant

37

are reliability entities required to have a backup control center

no, but they are required to have plan to continue reliable operations, including procedures to address the loss of voice and data...... primary control center is also not required to have redundant power supply

38

What must be included in a plan for the loss of a primary control center

basic-tie line control, hourly accounting of all schedules, time and frequency control

39

Implementation of the Capacity and Emergency plan is required and appropriate to

reduce risk to the interconnected system

40

Verification of the restoration procedure shall be confirmed by

actual testing or by simulation

41

If a Transmission Operator operates a system at a voltage of less than 100 kV, and experiences a restoration event, does this change the Reliability Coordinator's role in the restoration process

no, Standard EOP-006 does not address specific voltage requirements when discussing the role of the Reliability Coordinator in the restoration process

42

most critical issue in implementing a backup control center is its access to

voice and data communications