Lecture 7- Lean shipbuilding Flashcards

(6 cards)

1
Q

What is Earned value management (EVM)?

A

Is a project performance measurement system used to track how well a project is going in terms of cost, schedule and progress.

EVM uses three measurments
- planned value
- earned value
- actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Tell me the purpose of Earned value management (EVM)

A

To compare
- What was planned
- what has been done
- How much it has cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Name the three key metrics in Earned value management (EVM)

A
  1. Planned value- budget cost of work
  2. Earned value- Budget cost for the work performed
  3. Actual cost- What has it cost?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Lean project planning (LPP)

A

management model that is developed in a shipyard to improve planning by combining

-Lean thinking- For example PDCA

-Last planner system

-Earned value management
Purpose= Improve communication, coordination and standardization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the 7C´s model?

A

Is a lean implementation framework used on Lean Production Planning (LPP) in very complex environments like shipbuilding.

The C´s are
-Champion- A top- level leader who drives lean implementation

-Control- visual tools and systems to track performance

-Compensation- Incentives tied to team and individual performance

-Change process- strategy for transforming the organization

-Commitment- engaging all levels in continuous improvements

-Continuous education- Ongoing learning and training

-Culture- The values, beliefs and behaviors shared in the organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly