P & C Signals, Trips & SI's Flashcards

(44 cards)

1
Q

P-4

coincidence

inputs

A

Rx trip and associated bypass breaker open

RTA + BYA (P-4a) 2/2 per train

RTB + BYB (P-4b) 2/2 per train

  • trips turbine
  • closes FRV & bypass w/ Tave < 554 F
  • seal in SI reset
  • steam dumps to Rx trip mode (B)
  • blocks stm dumps 3/4, arms 1/2 (A)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

P-6

coincidence

inputs

A

IR permissive > 10-10 ica

1/2

  • permits manual blocking of SR trip (105 cps)
  • allows de-energizing of SR Ni’s

(provides one decade of overlap between SR and IR)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

P-7

coincidence

inputs

A

P-10 met ( > 10% PR)

or

P-13 met ( >10% Pimp)

1/2

enables trips:

  • Pzr low pressure
  • Pzr high level
  • RCP bkr open
  • RCP bus UF or UV
  • RCS loop low flow

(should not operate above 10% w/ these conditions)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

P-8

coincidence

inputs

A

PR > 35%

2/4

Changes loss flow Trip 2/4 loops -> 1/4 loops

DNB protection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

P-9

coincidence

inputs

A

PR > 50%

2/4

Activates Rx Trip on every turbine Trip > 50%

protects against major LR

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

P-10

coincidence

inputs

A

PR > 10%

2/4

Allows blocking:

  • PR flux Trip (low) 25%
  • IR flux Trip (hi) 25% equivalent
  • IR Rod stop 20% (C-1)

Blocks:

  • Subcooling monitor alarm

Inputs:

  • P-7 (low power permissive)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

P-11

coincidence

inputs

A

Pzr Press >/= 1915 psig

2/3

below:

  • allows blocking of Low Ppzr SI
  • allows blocking of Low Pstmln SI and SLI
  • allows enabling of Hi rate SLI

above:

  • enables Low PPzr SI
  • enables Low Pstmln SI and SLI
  • disables Hi rate SLI
  • sends open signal to Accum isolation valves
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

P-12

coincidence

inputs

A

Tave < 543 F

2/4

Blocks all steam dump valves

(protects against uncontrolled cooldown)

(Group 1 is bypassable)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

P-13

coincidence

inputs

A

Pimp > 10% (turbine power equivalent)

1/2

Provides input to P-7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

P-14

coincidence

inputs

A

L S/G > 90% NR

2/3 sensors 1/4 S/G

  • trips Main turbine
  • trips FWP turbines
  • closes FWI valves
  • closes FW control and bypass valves
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

C-1

coincidence

inputs

A

IR rod stop > 20% (current equiv)

1/2

stops outward rod motion (auto and manual)

can be blocked at P-10

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

C-2

coincidence

inputs

A

PR Rod stop @ 103%

1/4

Blocks Auto & Manual outward Rod motion

Can be bypassed for testing or failed channel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

C-3

coincidnence

inputs

A

OTAT Rod stop and runback

1% below trip setpoint

2/4

blocks auto and manual rod withdrawl

runback = 10% / min

(2400 MW/ min for 1.5 sec…..wait 28.5 sec)

(target is 203 MW, runback clears when cond clears)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

C-4

coincidnence

inputs

A

OPAT Rod stop and runback

1% below trip setpoint

2/4

blocks auto and manual rod withdrawl

runback = 10% / min

(2400 MW/ min for 1.5 sec…..wait 28.5 sec)

(target is 203 MW, runback clears when cond clears)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

C-5

coincidnence

inputs

A

Turbine low power < 15 % Pimp (PT-505)

1/1

Stops auto outward rod motion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

C-7A

coincidnence

inputs

A

10% loss of load/ 140 sec

Pimp (PT-505a, 506a, PT-8)(MSS)

arms group 1 and 2 steam dumps (40%’s)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

C-7B

coincidnence

inputs

A

50% loss of load / 140 sec

Pimp (PT-505a, 506a, PT-8)(MSS)

arms group 3 and 4 steam dumps (35%’s and 10%’s)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

C-9

coincidnence

inputs

A

condensor available

Vacuum > 20” Hg + CWP running (bkr closed)

2/2 (Pcond) + bkr

permissive for steam dump groups 1 and 2 (40%’s)

19
Q

C-11

coincidnence

inputs

A

Control Bank D Rod stop

CB D > 220 steps

stops automatic outward rod motion

20
Q

C-20

coincidnence

inputs

A

PT-505/ 506 > 40% Core thermal power (equiv.)

2/2

Arms AMSAC

21
Q

SR hi flux trip

coincidence

interlock

purpose

A

> 105 cps

1/2

blockable > P-6, when blocked SR de-energizes

S/U rod withdrawl accident

22
Q

IR hi flux trip

coincidence

interlock

purpose

A

> 25% (current equiv)

1/2

blockable > P-10

S/U rod withdrawl accident

23
Q

PR hi flux Trip (low)

coincidence

purpose

interlock

A

PR > 25%, trips Rx

2/4

Startup accident

Can be blocked > P-10 (2/2 switches)

24
Q

PR hi flux Trip (hi)

coincidence

interlock

purpose

A

PR > 109%

2/4

Unblockable

Overpower (kw/ft), positive reactivity excursion

25
Hi flux rate Trip coincidence interlock purpose
PR \>/= +5% / 2 sec 2/4 seals in, must be reset @ Ni cabinet ejected rod
26
OT delta T trip coincidence interlock purpose
\> 120% +/- penalties (bonus/penalties) 2/4 none DNBR \> 1.17
27
OP delta T trip coincidence parameter change setpoint purpose
\> 107.2% - penalties 2/4 Tave kw/ ft
28
Loop low flow trip coincidence interlock purpose
\< 90% 2/3 sensors 1/4 loops (\> P-8) 2/3 sensors 2/4 loops (\< P-8) \< P-7 trip deactivated (10%) P-8 changes coincidence (35%) DNBR \> 1.17 (\< P-8, 1 low flow and 1 bkr open will initiate Rx trip)
29
RCP Bkr open trip coincidence interlock purpose
bkr open 2/4 trip deactivated \< P-7 (10%) DNBR \> 1.17 (\< P-8, 1 low flow and 1 bkr open will initiate Rx trip)
30
RCP Bus UV trip coincidence interlock purpose
8050 volts 1/2 sensors, 2/2 Buses (12kv D, E) trip deactivated \< P-7 (10%) DNBR \>1.17
31
RCP Bus UF coincidence interlock purpose
54 Hz 2/3 sensors, 1/2 busses (12kv D, E) trip deactivated \< P-7 (10%), also trips RCP's DNBR \> 1.17
32
Low Pressure Trip Coincidence interlock purpose
Ppzr \< 1950 psig (rate sensitive) 2/4 trip deactivated \< P-7 (10%) DNBR limit
33
High Pressure trip coincidence interlock purpose
Ppzr \> 2385 psig 2/4 none RCS integrity
34
Hi Lpzr Rx trip coincidence interlock purpose
Lpzr \> 90% 2/3 trip deactivated \< P-7 (10%) B/U to Hi Ppzr/ prevent water out safties/ RCS integrity
35
L S/G low-low coincidence interlock purpose
L S/G \< 15% 2/3 sensors, 1/4 loops delay time to trip: (Pwr \< 50%, varies with delta T) 0% time delay ~ 500 sec 50% time delay ~ 30 sec loss of heat sink
36
Turbine trip - Rx trip coincidence interlock purpose
Low PAST \< 50psig **OR** SV closed AST 2/3 **OR** SV 4/4 trip deactivated \< P-9 (50%) limit temp/ Press transients in RCS
37
Manual Rx trip coincidence interlock purpose
switch 1/2 none operator judgement
38
SI Rx trip coincidence interlock purpose
SI any "S" signal none limits consequence of accident
39
Seismic Rx trip coincidence interlock purpose
0.30 g 2/3 sensors in same direction (x, y, z) none Seismic B/U trip
40
SSPS General Warning Rx trip coincidence interlock purpose
Train A & B SSPS simultanious GW 2/2 (1 train A + 1 train B) none Trip Rx if failure of protection system
41
Manual SI coincidence interlock purpose
switch 1/2 none operator judgement
42
CNMT Hi Press SI coincidence interlock purpose
PCNMT \> 3 psig 2/3 none Hi energy line break inside CNMT
43
Low Ppzr SI coincidence interlock purpose
Ppzr \< 1850 psig 2/4 blockable \< P-11 (auto unblock \> P-11, (1915 psig)) LOCA
44
Low Pstm line SI coincidence interlock purpose
Pstm line \< 600 psig (lead-lag) 2/3 sensors, 1/4 loops also actuates SLI, blockable \< P-11 (1915 psig), when blocked actuates hi rate SLI Steam line break