Planning a Project - Step 3 - Mod 102 Flashcards
Step 3 - Define Activities and Costs
estimated based on scope baseline – examines details of project objective and analyze dependencies with one another to help establish the schedule and cost baseline
Step 3 - Define Activities and Costs - Substeps
a. Define activities
b. Estimate costs
c. Sequence activities
d. Identify risks
e. Estimate activity resources
f. Perform qual. risk analysis
g. Plan risk response
h. Estimate activity durations
Step 3a - Define Activities
identifies and documents the specific actions to be performed to product the project deliverables
Activity
distinct, scheduled portion of work performed during the course of a project
Milestone
significant point or event in a project, program, or portfolio
Step 3a - Define Activities - Outputs
Activity list
Activity attributes
Milestone list
Change requests
PMP updates
Activity List
o Includes all schedule activities required on the project
o Provides sufficient details so that project team members can perform work
o Captures other details such as activity identifier and scope of work description
Activity Attributes
extend the description of the activity by identifying the multiple components associated with each activity
Milestone List
identifies all project milestones and indicates whether the milestone is mandatory
Change Requests
as part of the defining activities, submit change requests for work that were uncovered that were not originally in the initial project or product scope
Step 3b - Estimate Costs
develops an approximation of monetary resources needed to complete the project activities. Accuracy will increase with project profession (-25% to 75% during initiation to -5% to 10% later)
Step 3b - Estimate Costs - Outputs
Cost estimates
Basis of estimates
PD updates
Cost Estimates
o represent quantitative assessment of costs required to complete the project work
o include all resources needed by the activity such as labor, materials, equipment
Basis of Estimates
provides a clear and complete understanding of how the estimates were made
Step 3c - Sequence Activities
process to identify and document relationships among the project activities. Defines optimal sequence of activities given all project constraints.
Step 3c - Sequence Activities - Outputs
Project schedule network diagrams
PD updates
Project Schedule Network Diagram
represents the logical relationships (dependencies) of project schedule activities.
Decomposition
divide and subdivide – unless the process is creating the WBS, focus on outputs instead of deliverables (TT)
Rolling Wave Plan
iteratively plan near-term work in detail and plan for future work at a higher level. As more information becomes known, decompose work packages into activities. (TT)