Project Finance Flashcards

1
Q

What has the rate of inflation in UK construction been over the last 3 years?

A

2022: peaked at10.4%
2023: slowed to 4.6%
2024: 2.6%

Now at 2.5% and expected to rise to 3.8%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a cashflow?

A

A financial planning tool that predicts the flow of cash in and out of a project.
Typically shown month-by-month and for the duration of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How can a cashflow help clients during the construction period?

A
  • It allows the client to understand their financial commitment over the construction period. Can help them understand if any external funding will be required.
  • Acts as a check against valuations and can either signify financial difficulties or issues with programme.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How would you produce a cashflow?

A

Using a cash flow projection or forecast S-Curve tool, ensuring the the parameters and past data the s-curve is based on is similar.

If possible I would use the total cost of the works and a detailed programme to provide a more accurate version.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

In your submission you talk around assessing variations and reporting on the cost. If you had a discrepancy in the valuation of a variation with a contractor, what sum would you include within your cost report?

A

My assessment of the valuation would be included within the cost plan however I would include narrative around the disagreement as a highlight to make the client aware of what is happening.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What factors can affect a cashflow?

A
  • Retention
  • Sectional completion
  • Advance payments
  • Early material orders
  • Defects liability period
  • Materials on and off site
  • Variations
  • Provisional Sums
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Can you tell me what the importance of a cashflow is?

A

Allows client to understand financial commitment over the duration of the project

Used as a check against valuations and give early indication of financial difficulties

Estimate when extending funding is required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the correct contractual procedure for managing provisional sums within the contract?

A

EAI/CAl issued to expend the provisional sum, this is then omitted from the contract and the actual cost added back into the contract to form part of the agreed final sum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can you give me an example of a defined provisional sum you have included in a contract recently?

A

• Asbestos removal
• Firestopping
• Removal & disposal of FF&E
• Installation of kitchen

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How are variations managed in terms of cost under the contract?

A

The Valuation Rules.
Any additional or substituted works should have consistent values with similar items already included in the contract sum.
If no similar items are included in the contract sum, a fair and reasonable valuation should be made.

Once sum is agreed and Employer’s Agent Instruction has been issued, the contract sum is adjusted to include the additional sum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Outline a typical change control process that you would implement on your projects?

A

• Ensure that the process is included within contract prelims.
• If contractor wishes to propose a change to the Employer’s Requirements, it should issue a change request, accompanied by all supporting design and cost information.
• This will then be reviewed by the EA and the QS before seeking approval or rejection from the Employer.
• On agreement of design and cost proposals, the EA will then issue an Employer’s Agent Instruction.
• Contract sum will then be adjusted to incorporate additional sum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What might it suggest if the contractor’s application for payments are higher than their submitted cash flow?

A
  • They have cashflow issues
  • There’s been an advance material order (materials on site)
  • They are ahead of programme
  • Variations
  • Re-sequencing
  • Contractor accelerating the works (to save on prelims)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What might it suggest if the contractor’s application for payments are lower than their submitted cash flow?

A
  • Adverse weather
  • Behind programme
  • Delay to materials being delivered
  • Materials stored off site (and not claimed for)
  • Re-sequencing of works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Are there any risk factors inherent in construction cask flow forecasting?

A
  • Changes in design spec (sequencing and value)
  • Inflation (value of money)
  • Interest & exchange rates
  • Complexities of the building
  • Estimating error
How well did you know this?
1
Not at all
2
3
4
5
Perfectly