What has the rate of inflation in UK construction been over the last 3 years?
2022: peaked at10.4%
2023: slowed to 4.6%
2024: 2.6%
Now at 2.5% and expected to rise to 3.8%
What is a cashflow?
A financial planning tool that predicts the flow of cash in and out of a project.
Typically shown month-by-month and for the duration of the project.
How can a cashflow help clients during the construction period?
How would you produce a cashflow?
Using a cash flow projection or forecast S-Curve tool, ensuring the the parameters and past data the s-curve is based on is similar.
If possible I would use the total cost of the works and a detailed programme to provide a more accurate version.
In your submission you talk around assessing variations and reporting on the cost. If you had a discrepancy in the valuation of a variation with a contractor, what sum would you include within your cost report?
My assessment of the valuation would be included within the cost plan however I would include narrative around the disagreement as a highlight to make the client aware of what is happening.
What factors can affect a cashflow?
Can you tell me what the importance of a cashflow is?
Allows client to understand financial commitment over the duration of the project
Used as a check against valuations and give early indication of financial difficulties
Estimate when extending funding is required
What is the correct contractual procedure for managing provisional sums within the contract?
EAI/CAl issued to expend the provisional sum, this is then omitted from the contract and the actual cost added back into the contract to form part of the agreed final sum.
Can you give me an example of a defined provisional sum you have included in a contract recently?
• Asbestos removal
• Firestopping
• Removal & disposal of FF&E
• Installation of kitchen
How are variations managed in terms of cost under the contract?
The Valuation Rules.
Any additional or substituted works should have consistent values with similar items already included in the contract sum.
If no similar items are included in the contract sum, a fair and reasonable valuation should be made.
Once sum is agreed and Employer’s Agent Instruction has been issued, the contract sum is adjusted to include the additional sum.
Outline a typical change control process that you would implement on your projects?
• Ensure that the process is included within contract prelims.
• If contractor wishes to propose a change to the Employer’s Requirements, it should issue a change request, accompanied by all supporting design and cost information.
• This will then be reviewed by the EA and the QS before seeking approval or rejection from the Employer.
• On agreement of design and cost proposals, the EA will then issue an Employer’s Agent Instruction.
• Contract sum will then be adjusted to incorporate additional sum.
What might it suggest if the contractor’s application for payments are higher than their submitted cash flow?
What might it suggest if the contractor’s application for payments are lower than their submitted cash flow?
Are there any risk factors inherent in construction cask flow forecasting?
What is retention?
Sum of money held by the Employer as a safeguard for defective or non-conforming work or materials provided by the Contractor.
Also latent defects and possible failure to complete the project.
Is there any RICS guidance or project finance?
RICS Guidance documents on:
What is a contingency?
A provision made for unexpected events or uncertainties