Project Time Management Flashcards

1
Q

What is the schedule management plan

A

It identifies a scheduling method and scheduling tool, and sets the format and establishes criteria for developing and controlling the project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is plan schedule management

A

Process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Plan schedule management key benefit

A

Provides guidance and direction on how the project schedule will be managed throughout the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Plan schedule management inputs

A

Project management plan
Project charter
Enterprise environmental factors
Organizational process assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Plan schedule management tools and techniques

A

Expert judgment
Analytical techniques
Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Plan schedule management output

A

Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the define activities process

A

The process of identifying and documenting the specific actions to be performed to produce the project deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Key benefit of define activities

A

To break down work packages into activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define activities inputs

A

Schedule management plan
Scope baseline
Enterprise environmental factors
Organizational process assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define activities tools and techniques

A

Decomposition
Rolling waves planning
Expert judgment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Define activities outputs

A

Activity list
Activity attributes
Milestone list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is an activity list

A

A comprehensive list includes all schedule activities required on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are activity attributes

A

They extend the description of the activity by identifying the multiple components associated with each activity. They include the activity ID, WBS ID, and activity label or name

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the sequence activities process

A

Process of identifying and documenting relationships among the project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Sequence activities key benefit

A

Defines the logical sequence of work to obtain the greatest efficiency given all project constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Sequence activities inputs

A
Schedule management plan
Activity list
Activity attributes
Milestone list
Project scope statement
Enterprise environmental factors
Organizational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Sequence activities tools and techniques

A

Precedence diagramming method
Dependency determination
Leads and lags

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Sequence activities outputs

A

Project schedule network diagrams

Project document updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is precedence diagramming method (PDM)?

A

A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What types of dependency are there

A

Mandatory are those that are legally are contractually required or inherent in the nature of the work
Discretionary are sometimes referred to as preferred logic, preferential logic, or soft logic. They are established based on knowledge of best practices within a particular application area for some unusual aspect of the project where specific sequences desired
External involve a relationship between project activities and non-project activities and are usually outside the project teams control
Internal dependencies involve a precedence relationship between project activities and are generally inside the project team control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is a lead

A

The amount of time whereby a successor activity can be advance with respect to a predecessor activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is a lag

A

The amount of time where by successor activity will be delayed with respect to a predecessor activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the estimate activity resources process

A

Process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity

24
Q

Estimate activity resources key benefit

A

Identifies the type, quantity, and characteristics of resources required to complete the activity which allows more accurate cost and duration estimates

25
Estimate activity resources inputs
``` Schedule management plan Activity list Activity attributes Resource calendars Risk register Activity cost estimates Enterprise environmental factors Organizational process assets ```
26
Estimate activity resources tools and techniques
``` Expert judgment Alternative analysis Published estimating data Bottom up estimating Project management software ```
27
Estimate activity resources outputs
Activity resource requirements resource breakdown structure | Project documents updates
28
What is the estimate activity durations process
The process of estimating the number of work periods needed to complete individual activities with estimated resources
29
Estimate activity durations key benefit
Provides the amount of time each activity will take to complete, which is a major input to the develop schedule process
30
Estimate activity durations inputs
``` Schedule management plan Activity list Activity attributes Activity resource requirements Resource calendars Project scope statement Risk register Resource breakdown structure Enterprise environmental factors Organizational process assets ```
31
Estimate activity durations tools and techniques
``` Expert judgment Analogous estimating Parametric estimating Three point estimating Group decision-making techniques Reserve analysis ```
32
Estimate activity durations outputs
Activity duration estimates | Project documents updates
33
What is analogous estimating
A technique for estimating the duration or cost of an activity or project using historical data from a similar activity or project. Uses historical parameter data to estimate the same parameter for a future project
34
What is parametric estimating
And estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters
35
What is three point estimating or PERT
This technique uses three estimates to define an approximate range for an activities duration.
36
What are contingency reserves
Estimated duration within the schedule baseline that is allotted for identified risks also known as known unknowns
37
What are management reserves
A specified amount of the project ration withheld for management control purposes and reserved for unforeseen work that is within scope of the project. It addresses unknown unknowns
38
What is the develop schedule process
The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model
39
Develop schedule key benefit
By entering schedule activities, durations, resources, resource availability's, and logical relationships into the scheduling tool, it generates a schedule model with plan dates for completing project activities
40
Develop schedule inputs (13)
``` Schedule management plan Activity list Activity attributes Project schedule network diagrams Activity resource requirements Resource calendars Activity duration estimates Project scope statement Risk register Project staff assignments Resource breakdown structure Enterprise environmental factors Organizational process assets ```
41
Develop schedule tools and techniques
``` Schedule network analysis Critical path method Critical chain method Resource optimization techniques Modeling techniques Leads and legs Schedule compression Scheduling tool ```
42
Develop schedule outputs
``` Schedule baseline Project schedule Schedule data Project calendars Project management plan updates Project documents updates ```
43
What is the critical path method
A method used to estimate the middle project ration and determine the amount of scheduling flexibility on the logical network paths within a schedule model
44
What is the critical chain method
Schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties. Essentially a resource constrained critical path is known as a critical chain
45
What is resource smoothing
A technique that adjust the activities of a schedule model such that requirements for resources on the project or not exceed certain predefined limits however this technique does not change the project critical path or completion date
46
What is what if scenario analysis
The process of evaluating scenarios in order to predict their effect, positively or negatively, on project objectives
47
What is simulation
It involves calculating multiple project duration is with different sense of activity assumptions, usually using probability distributions constructed from the three-point estimate model to account for uncertainty. A common technique is Monte Carlo analysis
48
What is crashing
A technique used to shorten the schedule duration for the least incremental cost by adding resources. It does not always produce a viable alternative and may increase risk or cost
49
What is fast tracking
Schedule compression technique in which activities are phases normally done and sequins are performed in parallel for at least a portion of their duration. It may result in rework and increased risks
50
What is a schedule baseline
They approve version of a schedule model they can be changed on later formal change control.
51
What is control schedule process
Process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan
52
Control schedule key benefit
Provides the means to recognize deviation from the plan and take corrective and preventive actions and thus minimize risk
53
Control schedule inputs
``` Project management plan Project schedule Work performance data Project calendars Schedule data Organizational process assets ```
54
Control schedule tools and techniques
``` Performance reviews Project management software Resource optimization techniques Modeling techniques Leads and lags Schedule compression Scheduling tool ```
55
Control schedule outputs
``` Work performance information Schedule forecasts Change request Project management plan updates Project documents updates Organizational process assets updates ```
56
Project time management processes
``` Plan schedule management Define activities Sequence activities Estimate activity resources Estimate activity durations Develop schedule Control schedule ```