1.6 Given a scenario, apply schedule development and management activities and techniques. Flashcards

(17 cards)

1
Q

An agile team is developing a software application that should take several months to complete. What type of deliverable is the team likely developing?

A

Epic

It’s a deliverable in an agile team that is equivalent in size to a project that last several iterations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Calculated buffer of time and cost that covers documented risks. These risks are called “known unknowns”

A

Contingency reserves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Unique re-baselining characteristic

A
  • Analytical activity that can change the project’s cost, scope, or schedule
  • A response to general variance
  • Baseline adjustment that is not driven by a change request
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Soft logic is also known as _______

A

discretionary dependency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Hard logic is also known as _______

A

mandatory dependency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A Scrum master is documenting tasks for a team. How are tasks different from sprint goals?

A
  • They are smaller than a work package or user story
  • They describe specific steps to take
  • They are the action taken to complete deliverables
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Epics are large deliverables usually triggered by _________

A

business cases

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A product owner is reviewing details for a project. In what instance owner use the term epic?

A
  • When work will last several iterations or months
  • When it is a large deliverable triggered by a business case
  • When the scope is equivalent in size to a project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

After convening with the team, a Scrum Master is documenting the sprint goal. What benefit is there to having sprint goals?

A
  • Defines a primary value that a team plans to deliver in a given sprint
  • Sets an objective that reflects the expected outcome at the end of the sprint
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which type of dependency is the rarest?

A

Start-to-finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Start time is not relevant in which dependency?

A

Finish-to-finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is unique to a finish-to-start dependency type?

A
  • 2nd activity starts after 1st activity finishes
  • Most common dependency type
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A Scrum team is planning to deliver a primary value at the end of a sprint. This primary value is known as what?

A

Goal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

In the context of agile development, a _______ is smaller than an epic but still sizeable (1-3 iterations)

A

feature

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Unknown unknown

A

Setback the team has not forecasted.

For this, management reserve is used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

CPM Steps:

A
  1. Draw the project activities and dependencies
  2. Calculate PERT
  3. Complete a forward pass to calculate the early start and early finish
  4. Complete backward pass to calculate the late start and late finish
  5. Calculate the total float