2.5 Explain the importance of activities performed during the closing phase Flashcards

(12 cards)

1
Q

The project manager prepares to conduct a final phase gate review after the team completes the project work. What is another name for this meeting at this stage of the project?

A

Project closure meeting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A project team has completed and delivered all deliverables to a client. What must they receive from the client to transition to the closeout phase?

A

Documented approval from identified stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A project manager organizes the deliverables as the team begins moving towards a project close-out. What are the key deliverable categories during the closing phase?

A
  • Activities
  • Artifacts
  • Meetings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A project team is preparing to complete the project. The client has received and approved all deliverables. On what must the project sponsor agree to end the project officially?

A

Project closeout report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A project manager has submitted a project to the client for final review. What key items must the stakeholders agree to before they accept the project?

A
  • Completed project deliverables to satisfaction
  • Not accepting change requests
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The project team has submitted all deliverables, and the stakeholders have accepted them. What is the next step before a project team can close the contract?

A

Approval from all stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A project manager (PM) felt the team did an exceptional job during the last project. The PM wants to report possible projects that could benefit the organization. Where in the project closeout report will the PM annotate the possible projects?

A

Future considerations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A project manager (PM) is developing a plan for a project closure meeting as the team nears the end of the project. What are the key elements needed for the meeting?

A
  • Project overview
  • Project highlights
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A project team has entered the resource management phase of the project closeout. How can a project team effectively record and document project successes after the project has closed out?

A

Archive documentation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A project team wants to assess the project’s outcome against its expected impact(final result). What type of evaluation best fits this requirement?

A

Post-project evaluation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A project team is preparing to complete the project. The client has received and approved all deliverables. On what must the project sponsor agree to end the project officially?

A

Project closeout report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A project team is preparing to complete the project. The client has received and approved all deliverables. On what must the project sponsor agree to end the project officially?

A

Project closeout report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly