2.2 Given a scenario, perform activities during the project initiation phase Flashcards

(11 cards)

1
Q

A project manager (PM) must understand all the essential players when developing a project. What should the project manager do to find the people they need to communicate with during the project?

A

Identify and assess stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the stakeholders engagement steps?

A
  1. Identify
  2. Categorize and prioritize
  3. Understand
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A new project file includes a section that clarifies the project’s purpose and what stakeholders should expect. Which kind of file consists of this information?

A. Documents
B. Data
C. Success criteria
D. Objectives

A

A. Documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What describes the litmus test that determines if project expectations were achieved?

A

Project success criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does project objectives identify?

A

Milestones or targets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is a project scope statement different from a project charter?

A

A project scope expands on the scope provided in the project charter. The project charter is a brief, formal document that outlines the project parameters.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A project manager describes the team and stakeholder responsibilities in the project charter. What is the purpose of the Responsibility Assignment Matrix (RAM)?

A
  • The RAM is a living document.
  • The RAM is first created during the project initiation phase.
  • The RAM helps the team establish a sense of ownership
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

In preparation for a new project, a project manager defines the project, what it needs to accomplish, and what it does not need to accomplish. What area would best fit this step?

A. Project objective
B. Preliminary scope statement
C. Project success criteria

A

B. Preliminary scope statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A project lead assigns a new team member to the project. What document can the new team member look at to understand the details of the project?

A

Scope statement

Project scope statement expands on the scope provided in the project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A project sponsor needs to pitch a new project. However, the sponsor was given guidance to not get too technical when describing the project. What characterizes a conceptual plan representing how something must work and integrate?

A

Solution design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A project manager (PM) is assigned a project and is new to creating project charters. The PM understands the charter shares high-level risks and the risk register captures all risks and responses throughout the project. What is another benefit of a project charter that the PM should know?

A

Project charter clarifies the project’s purpose