Contract Administration Flashcards

(7 cards)

1
Q

What were the sections of the NEC building contract?

A

Section 1 - Area by Greggs
Section 2 - Security checkpoint
Section 3 - WS3 Works
Section 4 - Works following delivery of security equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the possession and completion provisions of the NEC contract?

A

● Contractor has access to the site rather than possession.
● Employer takes over the works not later than 2 weeks after completion.
● Employer can take over parts of the works when he begins to use it - PM certifies the date and extent of works that have been taken over within 1 week.
● PM certifies completion with 1 week.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What do capitalised words mean in NEC?

A

Defined terms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What do italisised words mean in NEC?

A

Terms identified in the contract data.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What were the milestones and associated payment for the security equipment?

A

● Contract award - 50%
● Delivery of all security equipment - 20%
● Operation of lanes 1, 2 and 3 - 15%
● Operation of Lane 4 - 5%
● Removal of existing security equipment - 5%
● Issue taking over certificate - 5%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the possession and completion provisions of the MF/1 contract?

A

● Engineer attends SATs and is signed off
● Engineer issues a taking-over certificate following completion of each section (following the tests on completion (SATs)).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Was there any retention on the Cardiff Airport contracts?

A

Building works - 3%
Security Equipment 3%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly