Contract Administration Flashcards
(7 cards)
What were the sections of the NEC building contract?
Section 1 - Area by Greggs
Section 2 - Security checkpoint
Section 3 - WS3 Works
Section 4 - Works following delivery of security equipment
What are the possession and completion provisions of the NEC contract?
● Contractor has access to the site rather than possession.
● Employer takes over the works not later than 2 weeks after completion.
● Employer can take over parts of the works when he begins to use it - PM certifies the date and extent of works that have been taken over within 1 week.
● PM certifies completion with 1 week.
What do capitalised words mean in NEC?
Defined terms
What do italisised words mean in NEC?
Terms identified in the contract data.
What were the milestones and associated payment for the security equipment?
● Contract award - 50%
● Delivery of all security equipment - 20%
● Operation of lanes 1, 2 and 3 - 15%
● Operation of Lane 4 - 5%
● Removal of existing security equipment - 5%
● Issue taking over certificate - 5%
What are the possession and completion provisions of the MF/1 contract?
● Engineer attends SATs and is signed off
● Engineer issues a taking-over certificate following completion of each section (following the tests on completion (SATs)).
Was there any retention on the Cardiff Airport contracts?
Building works - 3%
Security Equipment 3%