What were the extensive client requirements for Cardiff Airport?
● Maintenance of operations at all times - passenger route to existing checkpoint
● Obstructive work during winter periods (November - April)
● Signage - wayfinding, security checkpoint, FIDS, fire evacuation
● Aesthetics in line with branding guidelines and marketing team’s preferences
● PRM team requirements - lift access, PRM lane, gaps between body scanners
● Security team / UKBF facilities (staff room, training room, search rooms, duty manager’s office)
● Commercial team - advertising space
How did you ensure the extensive client requirements were met?
● Held workshops with the various Cardiff Airport teams (e.g. several with the marketing team and security team on the design of all signage)
● Requested ultimate written approval of designs from the client once completed and before inclusions in ITTs
How did you prepare the cost plan for Cardiff Airport?
Using the principles of NRM1 (Order of cost estimating):
1) Facilitating works
2) Building works (substructure, superstructure, internal finishes, FF&E, services, prefabricated buildings, work to existing buildings, external works)
3) Preliminaries
4) OH&P
5) Professional fees
6) Other costs
7) Risk allowances
8) Tender inflation estimate
9) Construction inflation estimate
10) VAT
What elements do you include in a risk register?
1) Project stage
2) Risk description
3) Risk rating (likelihood, impact)
4) Risk owner
5) Proposed mitigation
6) Residual risk rating
7) Comments
What items were included in the Cardiff Airport risk register?
● Availability of security equipment due regulatory requirement and limited suppliers - procured asap
● Public opinion / customer experience during works - phasing plans, hoarding, weekly planning meetings
What is a development brief?
A document that outlines the vision, objectives, and key principles for a development project.
What did you include in the development brief you prepared for NMW?
1) Executive Summary
2) Statement of Need
3) Site Background
4) Existing / Future Energy Usage
5) Options Identified (Car park canopies, roof mounted, ground mounted)
6) Desktop Feasibility Assessment
7) Recommendations
8) Proposed Next Steps
Appendices:
A - Cost Plan
B - PV Modelling
C - Programme
D - Feasibility Options Scoring
What was assessed within the options appraisal / feasibility assessment for NMW?
● Land ownership
● Salix Funding
● Electrical generation / usage
● Planning / consents (heritage, ecology, archeology, visual impact, flood risk)
● Buildability (structures, civils, maintenance, H&S)
What recommendations did you make in your development appraisal for NMW?
● Surveys - PEA, GPR, GI
● Stakeholder consultation - Cardiff Council, NGED, Salix
● Design Development
● Procurement strategy
How did you prepare the feasibility cost plan for NRW PV panels?
Using the principles of NRM1 (Order of cost estimating):
1) Facilitating works
2) Building works (substructure, superstructure, internal finishes, FF&E, services, prefabricated buildings, work to existing buildings, external works)
3) Preliminaries
4) OH&P
5) Professional fees
6) Other costs
7) Risk allowances
8) Tender inflation estimate
9) Construction inflation estimate
10) VAT
Did you include any exclusions or limitations in the development brief for NMW?
Clarified within the report that it was a RIBA Stage 1 (preparation and briefing) brief only and that information was from desktop study only. Surveys and consultation required to confirm third party information.
What did you include in the development brief you prepared for NGED?
1) Executive Summary
2) Statement of Need
3) Siting strategy
4) Site background / progress to date
5) Sites identified
6) Screening of sites
7) Desktop feasibility assessment
8) Recommendations
9) Proposed next steps
Appendices:
A - Cost Plan
B - PV Modelling
C - programme
D - Feasibility Options Scoring
What was assessed within the options appraisal / feasibility assessment for NGED?
● Land ownership
● Highways and access
● Ground conditions
● Proximity to existing electrical infrastructure
● Easement requirement
● Planning / consents (heritage, ecology, archaeology, visual impact, flood risk)
● Buildability (structures, civils, maintenance, H&S)
What was the statement of need for the new NGED primary substation?
The City of Newport is currently fed by three substations at Newport South, Newport East and Newport West which together supply in the region of 47,500 customers.
There is currently minimal demand headroom at the existing BSP substations with the majority of spare capacity already secured by contracted demand and committed developments.
The electrical demand across Newport City is expected to grow in the coming years predominantly due to the UK Government’s 2050 net zero target, which will drive significant growth in low carbon technologies such as electric vehicles, heat pumps and hydrogen gas production.
To accommodate this demand growth across Newport City Centre and prevent the distribution network becoming a ‘blocker’ to the connection of low carbon technologies, it is necessary to establish a new 33/11kV Primary Substation.
What recommendations did you make in your development appraisal for NGED?
Make a recommendation on a site in Alexandra Dock.
Surveys and report proposed by planning consultant for a planning submission:
● Planning statement
● PEA
● Substation design
● Highways design
● Drainage strategy
● Landscape design
● Arboricultural impact assessment
● Flood consequent assessment
Proposed stakeholder consultation:
● LPA
● NRW
How did you prepare the cost plan for NGED?
Using the principles of NRM1 (Order of cost estimating):
1) Facilitating works
2) Building works (substructure, superstructure, internal finishes, FF&E, services, prefabricated buildings, work to existing buildings, external works)
3) Preliminaries
4) OH&P
5) Professional fees
6) Other costs
7) Risk allowances
8) Tender inflation estimate
9) Construction inflation estimate
10) VAT
What were the feasibility options for Cathays cons club?
4 Options to convert existing buildings into mixture of HMO, student accommodation bedrooms and studios. 23, 28, 32 or 43 units.
Option 5. Complete Demolition. New build Construction (31 units).
What did you include in the programme for Cathays cons club?
1) Pre-application (as recommended by the planning consultant)
2) RIBA 3 design
3) SAB and planning application
4) Planning determination
5) RIBA 4 design
6) Procurement
7) Construction
What did you include in the feasibility programme for NGED?
1) Site surveys
2) Outline design for planning / SAB
3) Detailed design
4) Contractor procurement
5) Construction
What did you include in the feasibility programme for NMW?
1) Site surveys
2) Outline design for planning
3) Salix funding application
4) Detailed design
5) Contractor procurement
6) Construction
What are the RIBA plan of work stages?
0 - Strategic definition
1 - Preparation and briefing
2 - Concept design
3 - Spatial coordination
4 - Technical design
5 - Construction
6 - Handover
7 - Use
What are the outcomes and key actions of each RIBA plan of work stage?
0 - Strategic definition - The best means of achieving the Client Requirements confirmed (business case)
1 - Preparation and briefing - Project Brief approved by the client (feasibility studies, site surveys, procurement strategy)
2 - Concept design - concept design aligned to brief and approved by the client (outline specification and cost plan)
3 - Spatial coordination - architectural and engineering information spatially coordinated (aligned with updated cost plan and specification)
4 - Technical design - design ready for construction (appoint contractor)
5 - Manufacturing and Construction - construction and commissioning completed (H&S file and O&M manuals)
6 - Handover - building handed over and aftercare initiated (feedback)
7 - Use - building used, operated and maintained (post-occupancy evaluation, update H&S file as necessary)
What are the statutory approvals of each RIBA plan of work stage?
0 - Strategic definition - planning considerations
1 - Preparation and briefing - source pre-application planning advice
2 - Concept design - obtain pre-application planning advice / submit outline planning application
3 - Spatial coordination - review design against building regs, submit planning application
4 - Technical design - submit building regulations application (initial notice), discharge pre-commencement planning conditions, submit F10
5 - Construction - comply with CPP and planning conditions
6 - Handover - comply with planning conditions
7 - Use - comply with planning conditions