Conflict Avoidance, Management and Dispute Resolution Procedures Flashcards

(37 cards)

1
Q

What is a conflict?

A

A disagreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When do disputes arise in your role?

A

● Arises because of a failure to comply with a contractual obligation
● Different interpretations of a contract
● Contract drafting issues
● Scope ambiguity
● Incorrect application of contractual mechanisms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What can you do if negotiations break down?

A

Use dispute resolutions procedures e.g. ADR.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is conflict avoidance?

A

Methods or behaviors to avoid conflict including:

● Clear and concise contract drafting
● Negotiating contract obligations transparently
● Adopting proactive conflict avoidance risk analysis
● Managing parties’ expectations through clear communication
● Keeping good records to resolve conflicts before they escalate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is conflict management?

A

Use of processes, tools and skills to find ways to manage disputes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is dispute resolution?

A

Resolving disputes between parties. At the most basic level this could be the parties negotiating to a resolution themselves, up to litigation (resolving in court).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is ADR?

A

Alternative Dispute Resolution - dispute resolution process outside of litigation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the different types of alternative dispute resolution?

A

1) Adjudication
2) Mediation
3) Arbitration
4) Expert determination

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the advantages of ADR?

A

● Speed (less time than court proceedings)
● Informality
● Greater opportunity for negotiation
● Cost - less professional fees than litigation
● Quality of decision making (can by by a surveyor rather than a judge
● Confidentiality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you know what dispute resolution method to use?

A

Checking the contract. E.g. in NEC it is always main option clause W2 in the UK as the Housing Grants, Construction and Regeneration Act 1996 applies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the standard dispute resolution procedure under NEC?

A

NEC it is always main option clause W2 in the UK as the Housing Grants, Construction and Regeneration Act 1996 applies.

1) Adjudication
2) The Tribunal (usually arbitration or litigation)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is adjudication and what is the process?

A

The most common form of ADR.

● The Housing Grants, Construction and Regeneration Act 1996 says that any party to a construction contract can refer any dispute under that contract to an impartial adjudicator to make a decision on how to resolve the issue.
● 28-day procedure for adjudication, although this can be extended for another 14 days by agreement.
● The adjudicator’s decision is binding, although it can be overturned later by a court or by arbitration.
● The parties to a dispute can agree who their adjudicator will be. If they can’t agree, one of the parties can apply to an Adjudicator Nomination Body (ANB) to appoint one for them. RICS is the UK’s leading ANB.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is mediation and what is the process?

A

A less formal form of ADR where a mediator help the parties engage in meaningful dialogue, explore the disputed issues in detail and keep them focused on achieving an amicable outcome.

● If they cannot agree on a mediator, or do not know who to approach, they can ask RICS to make the appointment for them.
● A mediator isn’t there to come to a decision themselves or impose a solution on the parties.
● Mediation tends to be more cost-effective and flexible, and less formal, than some of the other forms of ADR.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is arbitration and what is the process?

A

Both parties agree for a decision to be made by an independent arbitrator (or a panel of arbitrators).

● The process is formal, similar to court proceedings – but, unlike open court, it is private and confidential.
● The arbitrator will usually be an expert in the subject of the dispute.
● The parties put forward their case to the arbitrator, who will assess the evidence and decide which party’s case was most persuasive.
● The arbitrator’s decision (called an award) is final and legally binding, therefore the losing party cannot take the matter to court.
● Arbitration can be a quicker and more cost-effective solution than going to court.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is expert determination and what is the process?

A

Like arbitration, expert determination is a private process where an independent technical expert is appointed (by the parties themselves or by an appointing body such as RICS) to conduct their own investigation and reach a decision on the dispute.

● Expert determination is often used when the dispute focuses on a technical issue rather than a legal one.
● The decision can be binding or non-binding but is usually binding.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What do you know about the RICS Dispute Resolution Service?

A

Largest provider of ADR services in the land, property and construction industries. Provides:

● Arbitration
● Independent Expert Determination
● Adjudication
● Mediation
● RICS Conflict Avoidance Proccess (CAP)

17
Q

What is RICS Conflict Avoidance Proccess (CAP)?

A

A government-endorsed procedure that can be written into contracts (or used ad-hoc) to help parties involved in construction or engineering projects to resolve disagreements out of court. It encourages parties to resolve problems at the time of the event, to nip them in the bud before they escalate to drawn-out, damaging disputes.

1) A CAP Panel of 1 or 3 professionals will be appointed by RICS to help parties resolve the issue/disagreement they are facing.
2) The CAP Panel are experts in the subject at the heart of the dispute so will quickly get to the crux of the matter.
3) The CAP Panel will work alongside the parties to understand the issue(s) they are grappling with.
4) Using their experience and technical expertise, the CAP Panel will then provide a fully reasoned CAP Report setting out a practical means to resolve the issue(s).

Recommendations are no binding.

18
Q

What is an expert witness?

A

● when a surveyor provides evidence to a tribunal e.g. court, arbitrator, independent expert
● primary duty of care is to the court not to the client
● surveyors should only accept if they have the knowledge, experience and qualifications and training
● give an objective and unbiased opinion

19
Q

What is the difference between and expert witness and an independent expert?

A

Expert witness = provides evidence to a tribunal e.g. court, arbitrator, independent expert
Independent Expert = provides a decision in expert determination ADR

20
Q

What is an advocate?

A

Surveyors acting as advocate represent their client at a judicial hearing/tribunal. Has a duty to the client and tribunal.

21
Q

What RICS guidance do you know relating to dispute resolution?

A

There are various guidance notes from RICS including:

● Acting as expert witnesses
● Acting as advocaters
● Acting as arbitrators
● Acting as independent experts

22
Q

What are the benefits of clear contract documentation?

A

Makes disputes less likely as all parties are aware of their obligations.

23
Q

How can good record keeping avoid conflict?

A

Provide written evidence of the agreements made.

24
Q

What are the three pillars of dispute resolution?

A

1) Negotiation - communication between parties
2) Mediation - neutral third party facilitates discussion
3) Adjudication - neutral third party makes a legally binding decision (e.g. adjudicator, arbitrator, court)

25
How do mediation and conciliation differ globally?
Mediation primarily focuses on facilitating discussion and communication between parties, allowing them to reach their own agreement. Conciliation, on the other hand, may involve the conciliator offering suggestions or proposals for settlement, taking a more active role in the process.
26
What is the Technology & Construction Court and what is its role?
The Technology and Construction Court (TCC) is a specialist court within the High Court of England and Wales that handles disputes related to building, engineering, and technology. Its primary role is to adjudicate on disputes arising from construction contracts, professional negligence claims, and other technology-related legal issues.
27
If you work with contracts, explain how dispute resolution works in a contract you have worked with?
NEC it is always main option clause W2 in the UK as the Housing Grants, Construction and Regeneration Act 1996 applies. 1) Adjudication 2) The Tribunal (usually arbitration or litigation) - only once adjudication has been done
28
What is a Dispute Review or Recommendation Board (DRB)?
Standing = stays up to date throughout the project Ad-hoc board = only involved if a dispute arises A standing group of typically, three independent and impartial persons selected by the contracting parties. The Dispute Board knows the parties, knows their goals and objectives, and can act efficiently to prevent a dispute from arising or, if one does, to give a decision in some cases. A standing Dispute Board will stay up-to-date on the project’s progress and any potential problems through regular site visits and meetings. They will also respond to issues by offering formal guidance and recommendation. If a dispute occurs, the Dispute Board will review the situation and provide a resolution, which could include non-binding advice (Dispute Review Board), binding decisions (Dispute Adjudication Board), or a mix of both.
29
Explain the various adjudication services provided by RICS.
● Construction adjudication - construction industry disputes (can be complex) ● Low value adjudication (less that £10k) ● Summary adjudication (straightforward and less than £20k) ● Homeowner adjudication (between homeowners and contractors
30
What is the role of RICS in dispute resolution?
1) Dispute Resolution Service 2) RICS Adjudicator Nomination Body (ANB) 3) RICS Conflict Avoidance Proccess (CAP)
31
What is an Adjudicator Nominating Body (ANB)?
An organisation that appoints adjudicators to resolve disputes in the construction and engineering industries. RICS is a globally recognised ANB.
32
What tribunals are you aware of?
Technology and Construction Court (TCC).
33
Which dispute resolution procedures lead to a binding decision?
1) Litigation 2) Arbitration 3) Adjudication 4) Expert determination (usually)
34
Explain the RICS conflict avoidance pledge to me.
● A pledge companies can make to work collaboratively on projects and try to avoid conflict. ● The pledge was initiated by several UK professional bodies in construction and engineering including RICS, ICE and RIBA. ● Demonstrates you are a good business to work with and maintain good business relationships.
35
Explain the Thomas Kilman model to me?
A model that categorizes five distinct conflict handling styles based on two dimensions: assertiveness and cooperativeness. 1) Competing 2) Collaborating 3) Compromising 4) Avoiding 5) Accommodating
36
What did you learn from reading the RICS Guidance Note on Conflict Avoidance and Dispute Resolution in Construction (2012)?
The 3 pillars of dispute resolution - Negotiation, mediation and adjudication). ADR methods.
37
What is the early warning proccess in NEC?
1) PM or Contractor notify the other when they become aware of something that could increase the total of the Prices, delay completion, delay meeting a key date or impair the performance of the works in use. 2) PM or Contract can instruct the other to attend and EW / risk reduction meeting 3) All parties discuss how the matter can be resolved 4) PM revises the risk / EW register and issues to the Contractor.