What provisional sums did you include within the Cardiff Airport building contract?
● ACM removal within Caffi Cwtch, Burger King and BOH areas subject to R&D survey - £110k
● ACM removal in second floor plantroom
● Employer’s Contingency - £250k
What was the final account of the Cardiff Airport project?
Building Works - £6.7m
Security Equipment - £2.2m
Professional Fees - £800k
Total = £9.7m
What is the pain / gain allocation for the Bro Tathan project?
● Less than 95% = 10%
● 95% - 105% - 50%
● 105% - 115% - 62.5%
● More than 115% - 75%
How do you calculate the anticipated pain/gain allocation?
I input the Contractor’s forecast of the total defined cost into the sheet I created within the CAD to calculate this.