Case Study Flashcards
(57 cards)
Please describe what the feasibility evaluation process looked like?
When I first become involved in the project 7 concept options had been developed by the architect ranging from minimal impact to high impact. Key objectives (outside of regulatory requirement) included:
1) Dealing with existing ACMs
2) Dealing with M&E equipment past its design life
3) Improving passenger flow and experience
4) Improving operational efficiency
I chaired several workshops and monthly progress meetings to gain the input of the various airport stakeholders (directors, security team, terminal operations, IT, PRM, commercial, marketing etc.).
Stage report produced at each RIBA Stage 1 - 4 and client approval received.
What were the different types of asbestos encountered on this project?
1) Asbestos insulation board
2) Asbestos sprayed coating on soffit
3) Asbestos lagging
All licenced work.
How are different types of asbestos dealt with?
In accordance with the Control of Asbestos Regulations 2012:
1) Asbestos consultant undertook R&D surveys
2) Asbestos consultant developed scope of asbestos removals
3) Licensed asbestos removal contractor (LARC) (HSE licensed contractor) appointed as part of the WS1 contract
4) ASB5 form submitted 2 weeks prior to works
5) Air monitoring by independent monitor
6) Polythene enclosures with smoke tests and air lock
7) Quilling
How were you able to maintain airport operations?
● Through RIBA stages 1 - 4 I developed phasing plans with temporary hoarding with the client and PD. These plans were included in the ITT.
● I prepared quality questions requiring contractors to outline their proposed methods of maintaining airport operations
● Weekly planning meetings
● Moving of hoarding in line with phasing plans
● CWL marketing teams were aware of the project so could provide social media warning to passengers
What was the communication process to notify airport management / stakeholders of the ongoing works?
● Weekly planning meetings
● Monthly project manager’s report, presented at progress meetings
What M&E Infrastructure was replaced within WS1?
● Replacement of an air handling unit, new MVHR, ducting, diffusers (HVAC)
● Replacement of main switchboard (LV panel)
● Replacement of lighting, new small power, fire detection
What is an AHU?
A device used to regulate and circulate air as part of a heating, ventilating, and air-conditioning system.
What is an MVHR?
Mechanical Ventilation with Heat Recovery - a system that reduces energy usage by transferring heat into fresh air.
1) Draws in fresh air from the outside and filters it
2) Extracts stale air from he space
3) Transfers heat from the outgoing stale air into the incoming fresh air
Within WS1, what type of lift access was provided?
There was an existing lift shaft from ground to second floor, however the lift was only configured to go to the first floor as there was not access route from the second floor (plant room in the way). Once a new corridor was constructed through the plant room (following removal of the AHU, the lift was reconfigured so that that it went to the second floor also (using access card only).
Describe you’re approach to producing the master programme?
● I created an outline programme during the feasibility stage (RIBA 1) and developed this through the RIBA stages.
● I created the programme in MS Project, ensuring tasks were linked with suitable logic, so that any changes would automatically adjust predecessor tasks.
● I colour coded the different stakeholders and added a legend to ensure responsibilities were clear.
● When the contractors were appointed I incorporated their contract programmes into my master programme.
● I updated the master programme during weekly planning meetings.
How did you maintain the programme?
● I created an outline programme during the feasibility stage (RIBA 1) and developed this through the RIBA stages.
● If changes occurred in the contract programmes I amended the master programme accordingly.
● I updated the master programme in weekly planning meetings to reflect progress and any anticipated changes to planned activities.
You were responsible for financial / programme and progress reporting - what were the main heading in these reports?
1) Introduction
2) Programme and progress
3) Financial
4) Change
5) Risk
6) Photos
Please describe what your tender evaluation process looked like?
● Evaluated based on the tender scoring matrix included in the ITT
● Issued the scoring matrix and quality question responses to the scoring panel
● Held and tender consensus meeting chaired by my MD
● Inputted the consensus scores and commercial submissions into the tender scoring matrix
● Prepared a tender report
How many tenderers submitted a tender for WS1?
● BECT
● Carter Lauren
How many tenderers submitted a tender for WS2?
● Leidos
● Nuctech
● Rapiscan
How many tenderers submitted a tender for WS3?
● BECT
●
What was the price and quality weighting for each WS and why?
WS1 - Price 60%, Quality - 40%. Restricted tender list based on competence therefore price a bigger factor.
WS2 - Price 70%, Quality - 30%. Restricted tender list based on competence therefore price a bigger factor.
WS3 - Price 60%, Quality - 40%. Restricted tender list based on competence therefore price a bigger factor.
What quality questions did you ask for WS1 and WS3?
● Method Statement
● Programme
● Organisational Structure and Curriculum Vitae
● Case Studies
What quality questions did you ask for WS2?
● Simulations
● Warranty Aftersales Care and Support
● Commissioning and Training
● Programme
What was Included within your ITT documentation?
● Instructions to Tenderers incl tender deliverables
● Form of Agreement and Contract
● Works Information
● Specifications (building works, ACM removal, mechanical and electrical)
● Site information
● Activity Schedule submission template
● Quality questions submission template
● Tender checklist
● Tender scoring matrix
● Phasing Plan
● PCI
● Cardiff Airport Contractor Guide
What was you’re approach to preparing the construction contracts?
● Utilised the contract documents included in the ITTs
● Used the Contract Data Part Two submitted by the contractor
● ITT requested tenderers submit any comments on the contract and these were openly discussed (e.g. retention changed from 5% to 3%)
Were any amendments included to the standard contract? If so what impact did they have?
Z clauses for:
● Provisional sums
● CASLO
● Cardiff Airport airside passes
● H&S file information to be issued prior to completion certificate
● PWDD = % completion of activities
Please explain the change / programme management process that you were responsible for?
In accordance with the NEC contract:
● Issue PMIs and notify CEs
● Assess CEs and respond within 2 weeks
● CEs assessed as change to defined cost before dividing date and forecast of change to defined cost after the dividing date and the fee
How is defined cost calculated in NEC?
Using the schedule of costs components:
1) People
2) Equipment (not part of the works)
3) Plant and materials (used in the works)
4) Charges
5) Manufacture and fabrication