Case Study Flashcards

(57 cards)

1
Q

Please describe what the feasibility evaluation process looked like?

A

When I first become involved in the project 7 concept options had been developed by the architect ranging from minimal impact to high impact. Key objectives (outside of regulatory requirement) included:

1) Dealing with existing ACMs
2) Dealing with M&E equipment past its design life
3) Improving passenger flow and experience
4) Improving operational efficiency

I chaired several workshops and monthly progress meetings to gain the input of the various airport stakeholders (directors, security team, terminal operations, IT, PRM, commercial, marketing etc.).

Stage report produced at each RIBA Stage 1 - 4 and client approval received.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What were the different types of asbestos encountered on this project?

A

1) Asbestos insulation board
2) Asbestos sprayed coating on soffit
3) Asbestos lagging

All licenced work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How are different types of asbestos dealt with?

A

In accordance with the Control of Asbestos Regulations 2012:

1) Asbestos consultant undertook R&D surveys
2) Asbestos consultant developed scope of asbestos removals
3) Licensed asbestos removal contractor (LARC) (HSE licensed contractor) appointed as part of the WS1 contract
4) ASB5 form submitted 2 weeks prior to works
5) Air monitoring by independent monitor
6) Polythene enclosures with smoke tests and air lock
7) Quilling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How were you able to maintain airport operations?

A

● Through RIBA stages 1 - 4 I developed phasing plans with temporary hoarding with the client and PD. These plans were included in the ITT.
● I prepared quality questions requiring contractors to outline their proposed methods of maintaining airport operations
● Weekly planning meetings
● Moving of hoarding in line with phasing plans
● CWL marketing teams were aware of the project so could provide social media warning to passengers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What was the communication process to notify airport management / stakeholders of the ongoing works?

A

● Weekly planning meetings
● Monthly project manager’s report, presented at progress meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What M&E Infrastructure was replaced within WS1?

A

● Replacement of an air handling unit, new MVHR, ducting, diffusers (HVAC)
● Replacement of main switchboard (LV panel)
● Replacement of lighting, new small power, fire detection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is an AHU?

A

A device used to regulate and circulate air as part of a heating, ventilating, and air-conditioning system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is an MVHR?

A

Mechanical Ventilation with Heat Recovery - a system that reduces energy usage by transferring heat into fresh air.

1) Draws in fresh air from the outside and filters it
2) Extracts stale air from he space
3) Transfers heat from the outgoing stale air into the incoming fresh air

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Within WS1, what type of lift access was provided?

A

There was an existing lift shaft from ground to second floor, however the lift was only configured to go to the first floor as there was not access route from the second floor (plant room in the way). Once a new corridor was constructed through the plant room (following removal of the AHU, the lift was reconfigured so that that it went to the second floor also (using access card only).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Describe you’re approach to producing the master programme?

A

● I created an outline programme during the feasibility stage (RIBA 1) and developed this through the RIBA stages.
● I created the programme in MS Project, ensuring tasks were linked with suitable logic, so that any changes would automatically adjust predecessor tasks.
● I colour coded the different stakeholders and added a legend to ensure responsibilities were clear.
● When the contractors were appointed I incorporated their contract programmes into my master programme.
● I updated the master programme during weekly planning meetings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How did you maintain the programme?

A

● I created an outline programme during the feasibility stage (RIBA 1) and developed this through the RIBA stages.
● If changes occurred in the contract programmes I amended the master programme accordingly.
● I updated the master programme in weekly planning meetings to reflect progress and any anticipated changes to planned activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

You were responsible for financial / programme and progress reporting - what were the main heading in these reports?

A

1) Introduction
2) Programme and progress
3) Financial
4) Change
5) Risk
6) Photos

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Please describe what your tender evaluation process looked like?

A

● Evaluated based on the tender scoring matrix included in the ITT
● Issued the scoring matrix and quality question responses to the scoring panel
● Held and tender consensus meeting chaired by my MD
● Inputted the consensus scores and commercial submissions into the tender scoring matrix
● Prepared a tender report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How many tenderers submitted a tender for WS1?

A

● BECT
● Carter Lauren

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How many tenderers submitted a tender for WS2?

A

● Leidos
● Nuctech
● Rapiscan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How many tenderers submitted a tender for WS3?

A

● BECT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What was the price and quality weighting for each WS and why?

A

WS1 - Price 60%, Quality - 40%. Restricted tender list based on competence therefore price a bigger factor.
WS2 - Price 70%, Quality - 30%. Restricted tender list based on competence therefore price a bigger factor.
WS3 - Price 60%, Quality - 40%. Restricted tender list based on competence therefore price a bigger factor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What quality questions did you ask for WS1 and WS3?

A

● Method Statement
● Programme
● Organisational Structure and Curriculum Vitae
● Case Studies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What quality questions did you ask for WS2?

A

● Simulations
● Warranty Aftersales Care and Support
● Commissioning and Training
● Programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What was Included within your ITT documentation?

A

● Instructions to Tenderers incl tender deliverables
● Form of Agreement and Contract
● Works Information
● Specifications (building works, ACM removal, mechanical and electrical)
● Site information
● Activity Schedule submission template
● Quality questions submission template
● Tender checklist
● Tender scoring matrix
● Phasing Plan
● PCI
● Cardiff Airport Contractor Guide

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What was you’re approach to preparing the construction contracts?

A

● Utilised the contract documents included in the ITTs
● Used the Contract Data Part Two submitted by the contractor
● ITT requested tenderers submit any comments on the contract and these were openly discussed (e.g. retention changed from 5% to 3%)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Were any amendments included to the standard contract? If so what impact did they have?

A

Z clauses for:

● Provisional sums
● CASLO
● Cardiff Airport airside passes
● H&S file information to be issued prior to completion certificate
● PWDD = % completion of activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Please explain the change / programme management process that you were responsible for?

A

In accordance with the NEC contract:

● Issue PMIs and notify CEs
● Assess CEs and respond within 2 weeks
● CEs assessed as change to defined cost before dividing date and forecast of change to defined cost after the dividing date and the fee

24
Q

How is defined cost calculated in NEC?

A

Using the schedule of costs components:

1) People
2) Equipment (not part of the works)
3) Plant and materials (used in the works)
4) Charges
5) Manufacture and fabrication

25
How does good change management benefit the project?
● Ensures the client gets the end product they want ● Ensures contractors are fairly compensated for the work they do ● Ensures good working relationship is maintained ● The early and more proactively changes are made the less cost impact
26
How are assessments (payments) made under NEC3 Option A?
● AfPs submitted at intervals stated in the contract data based on the AS ● Amount due = PWDD - retention ● PM certifies the payment within 1 week ● Payment made within 3 weeks of assessment date (YUK2) unless different date stated in CD
27
Why was IET MF/1 used on WS2 as opposed to NEC3 Option A?
Due to clauses specific to M&E e.g. factory acceptance tests, Site acceptance tests.
28
What was your approach to developing the procurement strategy?
● Liaised with the client to understand their priorities ● Used the procurement strategy template I had created providing the options available ● Produce a draft PS and ran through with the client explaining the reasoning for my advise ● Issued to the client for approval
29
What factors did you consider when developing the procurement strategy?
● Client / project analysis ● Risk ● Client priorities (finite budget, fixed completion date, required quality) ● Design - complexity, level of client control, cost / programme certainty ● Market analysis - capacity / capability
30
Regarding Option 1, did you check with any contractors If they would be willing to offer a fixed price?
Yes - suggested that they would be able to offer a fixed price for the first phase of works but would want cost reimbursable / target cost for the whole works.
31
What was the programme Impact of adopting option 2 rather than option 1?
Reduced pressure on the programme by continuing with building works.
32
Given there was an Issue with the security equipment, could you have approached the regulatory body with a view to extending the deadline as this was an issue outside of your control?
Yes, CWL and the security equipment contractor liased with the DfT and CAA throughout the delay and an alleviation to January 2025 was granted.
33
If there was no timescale given for the fault with the equipment to be resolved, what risk was there that various packages were completed far too in advance of the equipment arriving on site?
Potential risk, however this would have been a reduced risk than stopping straight away as at least more work would have been completed.
34
What was included in your 'detailed week by week planning'?
● Weekly planning meeting focused on the master programme ● Included things such as security passes and required escorting, works activities and any impact on passengers e.g. noises or smells
35
What is the importance of issuing meeting minutes?
● Very important as it provides an audit trail of the discussions and agreements made. ● Can also be used as defense in claims for negligence.
36
What is the purpose of liquidated damages?
To compensate the party for losses incurred.
37
How was the damages amount calculated?
Based on the anticipated prelims cost of the building works contract - established using the cost plan based on NRM1.
38
What other factors led to the delay - why was the WS2 supplier not entirely at fault?
Issue with a component in manufacturing in the US.
39
What grounds would the WS2 supplier have for going to dispute resolution?
I do not believe they had any grounds to go to dispute, however their claims were not factual based on the contract and they had poor records. The client was keen to reach a settlement.
40
What would you do differently next time?
Have better
41
How did you act ethically?
Acted with honesty and integrity at all times e.g. building contractor was not very contractual so I ensured they received their entitlement in terms f compensation.
42
What were your key achievements?
● Maintaining airport operations ● Securing £345k of LDs ● Maintaining a strong cohesion between all parties and a collaborative working ethos
43
What was considered in terms of fire safety?
● A fire consultant was appointed under the M&E designer ● The airport's existing fire strategy was reviewed and updated ● A drawing showing the fire exits, maximum distances and occupancy was produce in collaboration with the registered building officer ● Fire compartmentation (fire rated walls and doors and duct dampers) was incorporated ● Void detection installed where ceiling voids were more than 800mm ● Fire detection and connection to fire alarm system was included in the M&E design
44
What was the specification / requirement of the security equipment?
● Must be regulatory compliant ● Must meet throughput of 180 passengers per hour for each lane (720 total) ● Uninterruptible power supply of 30 minutes minimum ● Staff training - operator, supervisor, train the trainer ● Corrective maintenance and preventative maintenance
45
What were the sections of the NEC building contract?
Section 1 - Area by Greggs Section 2 - Security checkpoint Section 3 - WS3 Works Section 4 - Works following delivery of security equipment
46
What are the possession and completion provisions of the NEC contract?
● Contractor has access to the site rather than possession. ● Employer takes over the works not later than 2 weeks after completion. ● Employer can take over parts of the works when he begins to use it - PM certifies the date and extent of works that have been taken over within 1 week. ● PM certifies completion with 1 week.
47
What were the milestones and associated payment for the security equipment?
● Contract award - 50% ● Delivery of all security equipment - 20% ● Operation of lanes 1, 2 and 3 - 15% ● Operation of Lane 4 - 5% ● Removal of existing security equipment - 5% ● Issue taking over certificate - 5%
48
What are the possession and completion provisions of the MF/1 contract?
● Engineer attends SATs and is signed off ● Engineer issues a taking-over certificate following completion of each section (following the tests on completion (SATs)).
49
What was the final account of the Cardiff Airport project?
Building Works - £6.7m Security Equipment - £2.2m Professional Fees - £800k Total = £9.7m
50
What provisional sums did you include within the Cardiff Airport building contract?
● ACM removal within Caffi Cwtch, Burger King and BOH areas subject to R&D survey - £110k ● ACM removal in second floor plantroom ● Employer's Contingency - £250k
51
What sections were included in your Cardiff Airport procurement strategy?
● Introduction ● Progress to date (feasibility and design) ● Project Analysis (Client objectives / constraints / market analysis) ● Legislation (Public contracts regulations) ● Works Packaging ● Procurement Route ● Tendering Strategy ● Contract Strategy ● Summary of Recommendations
52
What options did you have in the Cardiff Airport Procurement Strategy?
● Works packaging - single or multiple ● Procurement Route - traditional, D&B ● Tendering strategy - restricted, open ● Contract strategy - fixed price / cost reimbursable / forms of contract
53
Why did you chose NEC for the Cardiff Airport building works?
● Proactive and collaborative mechanisms e.g. early warnings, programme submissions, agreeing CEs as they happen ● Familiarity of myself and contractors ● Option A - defined scope and cost certainty
54
How did you effectively deal with the security equipment delay and secure the LDs?
● I tracked the LDs accumulated, informing the Client of the latest figure periodically, and ensured the WS2 contractor remained aware of the LDs accumulating. ● Through email exchanges I stayed professional and factual references the contractual mechanisms and checking responses with the client and my MD ● Held a meeting having discussed ZOPA with the client, stayed professional ● Security equipment contractor made offers of £235k, £315k and finally £345k
55
Why did you not pursue the full LDs if the contractor was fully culpable?
● The client was keen to reach a settlement ● LDs are meant to provide compensation for losses, rather than being a penalty, therefor I considered it fair as the building works costs were covered ● To mitigate risk on the programme
56
What was the critical path of the project?
1) ACM removal 2) Demolitions 3) M&E installations 4) Security equipment 5) Removal of existing security equipment 6) Work where security equipment removed
57
How did you prepare the cost plan for Cardiff Airport?
Using the principles of NRM1 (Order of cost estimating): 1) Facilitating works 2) Building works (substructure, superstructure, internal finishes, FF&E, services, prefabricated buildings, work to existing buildings, external works) 3) Preliminaries 4) OH&P 5) Professional fees 6) Other costs 7) Risk allowances 8) Tender inflation estimate 9) Construction inflation estimate 10) VAT