Contract Practice Flashcards

(36 cards)

1
Q

What is a Contract?

A

A legally binding agreement between 2 or more parties outlining specific terms and obligations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the different types of JCT Contract?

A

Standard Form
Design and Build
Intermediate
Minor Works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the Differet Types of Procurement Methods

A

Management Contracting
Construction Manager
Traditional
Design and Build

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Management Contracting?

A

Client appoints 1 Contractor

Contractor appoints Subcontractors

(Client only has one contract with the main contractor)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a Construction Manager?

A

Acts as an Agent

Manages the multiple contracts between the Client and Contractors

(Client has a contract with each contractor - overseen by Construction manager)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a Tradidtional Procurement Method?

A

Client appoints a designer to design the building to RIBA stage 4

Contractors tender for the work (no design input).

2 Separate stages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a Design and Build Procurement Method?

A

Client appoints 1 contractor for the design and build of the project

Less risk for the client - passed all over to the contractor

Less cost information available for Capital Allowances Purposes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a Lump Sum Procurement Method

A

Lump Sum is a type of traditional procurement

Sum of works is agreed before the contract commences

Contractor takes on the risk to complete the works within the budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are Liquidated Damages

A

Liquidated Damages

A genuine pre-estimate of a loss - agreed pre contract

Contractor pays LADs to the client if the project overruns and the contractor is at fault

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Loss and Expense?

A

Contractor can claim for Loss and Expense if the works take longer than expected but the client is at fault (e.g. changes in design etc)

There must be written notice, and it is restricted to the direct cost incurred by the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is an Extension of Time?

A

Contractor can be granted an Extension of Time if the works take longer than expected.

The contractor must apply for “Reasonable Time”

Contract Administrator needs to approve the “Relevant Event” / “Relevant Matter” (e.g terrorist attacks, natural disasters etc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What do you include in an Engagement Letter?

A

Assumptions / Background
Entitlement to claim
Proposed Services
Information Requirements
Proposed Fees
Standard Terms of Business

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What do you include in your Standard Terms of Business?

A

Payment Terms / Dates
Quality Assurance
Termination of Contract
PII
Money Laundering Information
Data Handling
Complaints Handling Procedure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why are Engagement Letters important?

A

They bind both parties to the contract

Ensure a duty of care

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are Heads of Terms?

A

Non-binding document outlining the main issues relevant to the agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is an Indemnity Clause?

A

Protective Contractual Provision

Requires one party to compensate another for a specific loss.

17
Q

Why are Contract Dates Important?

A

First Year Allowances

SBA Statements
- Practical Completion
- Date brought into use
- Earliest written construction contract

18
Q

What is a Practical Completion Certificate?

A

When construction works are finished and handed over to the client (there may still be snagging)
- Type of Contract
- Contract Date
- PC Date

19
Q

What is the RIBA Plan of Work?

A

Royal Institute of British Architects

Outlines the stages of design from Inception to Completion

8 Stages

2020 Document updated to reflect an update in Sustainability

20
Q

What are the RIBA Stages?

A
  1. Strategic Definition
  2. Preparation and Brief
  3. Concept Design
  4. Spatial Coordination
  5. Technical Design
  6. Manufacturing and Construction
  7. Handover
  8. Use
21
Q

What is a CPSE?

A

Commercial Property Standard Enquiries

Information on the commercial contract pre-sale

Specific Capital Allowances Section

22
Q

What is a Letter of Intent?

A

A document expressing intent to enter a contract in the future

No contractual relationship

Usually sent when recipient is incurring costs and overheads

23
Q

What is a PCSA?

A

Pre-Construction Services Agreement

Allow clients to employ contractors before the main contract has been signed

Outline scope of works required of the contractor during the pre-construction phase

24
Q

What are the Standard forms of Building Contract?

A

JCT - Joint Contracts Tribunal - For construction

NEC - New Engineering Contract - For engineering contracts

FIDIC - International engineering contracts

25
What are the differences between JCT and NEC?
NEC is written in layman's terms - easy to understand NEC - program is a contract document
26
What is Retention?
A sum of money held following each valuation to incentivise contractors to fix defects Usually 3% (half released at PC and half 12 months later)
27
How is Retention usually treated in JCT Contracts
JCT states retention should be 6 months Retention periods are often changed to 12 months to allow for all seasons
28
How do you treat retention for Capital Allowances purposes?
Treat Retention as an accrual for the following year
29
What is an Agreement for Lease?
An agreement between two parties to enter into a lease at some point in the future
30
What is Insolvency?
When someone is unable to pay their debts Individuals are made 'Bankrupt' Companies are put into 'Liquidation' or 'Administration' - Liquidation wind up a company and sell assets to creditors - Administration - Aim to rescue the company - restructuring or sale
31
When would you use a Design and Build Contract?
Larger more complex projects Works can begin on site before all formalities of the main contract are agreed More liability to contractor / less control for the client
32
When would you use a Standard Form Contract?
Generally used on large projects Go into lots of detail for each element Most commonly used contract other than Design and Build Would use Traditional Procurement Method
33
When would you use an Intermediate Contract?
Similar to Standard Contract but generally for smaller projects (between Standard and Minor) Traditional procurement route (generally less than 1 year)
34
When would you use a Minor Works Contract?
Non complex projects Generally lower value projects (under £200,000) but cost cannot be the determining factor Fewer terms in the contract Traditional procurement route
35
What is a Bond?
A promise (usually a deed) to pay another person a sum of money
36
What are the different types of Bond?
Demand Bond Default Bond Performance Bond - Commonly used - insuring a client against a failing contractor (on demand / conditional if they breach contract) Retention Bond - Standard retention on valuations