Contract Practice Flashcards
(36 cards)
What is a Contract?
A legally binding agreement between 2 or more parties outlining specific terms and obligations
What are the different types of JCT Contract?
Standard Form
Design and Build
Intermediate
Minor Works
What are the Differet Types of Procurement Methods
Management Contracting
Construction Manager
Traditional
Design and Build
What is Management Contracting?
Client appoints 1 Contractor
Contractor appoints Subcontractors
(Client only has one contract with the main contractor)
What is a Construction Manager?
Acts as an Agent
Manages the multiple contracts between the Client and Contractors
(Client has a contract with each contractor - overseen by Construction manager)
What is a Tradidtional Procurement Method?
Client appoints a designer to design the building to RIBA stage 4
Contractors tender for the work (no design input).
2 Separate stages
What is a Design and Build Procurement Method?
Client appoints 1 contractor for the design and build of the project
Less risk for the client - passed all over to the contractor
Less cost information available for Capital Allowances Purposes
What is a Lump Sum Procurement Method
Lump Sum is a type of traditional procurement
Sum of works is agreed before the contract commences
Contractor takes on the risk to complete the works within the budget
What are Liquidated Damages
Liquidated Damages
A genuine pre-estimate of a loss - agreed pre contract
Contractor pays LADs to the client if the project overruns and the contractor is at fault
What is Loss and Expense?
Contractor can claim for Loss and Expense if the works take longer than expected but the client is at fault (e.g. changes in design etc)
There must be written notice, and it is restricted to the direct cost incurred by the client
What is an Extension of Time?
Contractor can be granted an Extension of Time if the works take longer than expected.
The contractor must apply for “Reasonable Time”
Contract Administrator needs to approve the “Relevant Event” / “Relevant Matter” (e.g terrorist attacks, natural disasters etc)
What do you include in an Engagement Letter?
Assumptions / Background
Entitlement to claim
Proposed Services
Information Requirements
Proposed Fees
Standard Terms of Business
What do you include in your Standard Terms of Business?
Payment Terms / Dates
Quality Assurance
Termination of Contract
PII
Money Laundering Information
Data Handling
Complaints Handling Procedure
Why are Engagement Letters important?
They bind both parties to the contract
Ensure a duty of care
What are Heads of Terms?
Non-binding document outlining the main issues relevant to the agreement
What is an Indemnity Clause?
Protective Contractual Provision
Requires one party to compensate another for a specific loss.
Why are Contract Dates Important?
First Year Allowances
SBA Statements
- Practical Completion
- Date brought into use
- Earliest written construction contract
What is a Practical Completion Certificate?
When construction works are finished and handed over to the client (there may still be snagging)
- Type of Contract
- Contract Date
- PC Date
What is the RIBA Plan of Work?
Royal Institute of British Architects
Outlines the stages of design from Inception to Completion
8 Stages
2020 Document updated to reflect an update in Sustainability
What are the RIBA Stages?
- Strategic Definition
- Preparation and Brief
- Concept Design
- Spatial Coordination
- Technical Design
- Manufacturing and Construction
- Handover
- Use
What is a CPSE?
Commercial Property Standard Enquiries
Information on the commercial contract pre-sale
Specific Capital Allowances Section
What is a Letter of Intent?
A document expressing intent to enter a contract in the future
No contractual relationship
Usually sent when recipient is incurring costs and overheads
What is a PCSA?
Pre-Construction Services Agreement
Allow clients to employ contractors before the main contract has been signed
Outline scope of works required of the contractor during the pre-construction phase
What are the Standard forms of Building Contract?
JCT - Joint Contracts Tribunal - For construction
NEC - New Engineering Contract - For engineering contracts
FIDIC - International engineering contracts