Test 4 Flashcards

(21 cards)

1
Q

16Which of the following is NOT true about Motivator-Hygiene theory?
SELECT THE CORRECT ANSWER

Hygiene factors are not sufficient to motivate people, and motivating agents provide the best positive reinforcement.

Hygiene factors can destroy motivation, but improving them under most circumstances will not improve motivation.

Motivating people is best done by rewarding people and letting them grow.

Improving hygiene factors will certainly improve motivation.

A

Correct Option:D

EXPLANATION

As per Herzberg’s Motivator-Hygiene theory, hygiene factors are not sufficient to motivate people, and motivating agents provide the best positive reinforcement. Hygiene factors can destroy motivation but improving them will not improve motivation under most circumstances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

21Which of the following is not a tool used for pre-assessment?
SELECT THE CORRECT ANSWER

Ability Test

Structured Interview

Focus Group

Testing

A

Correct Option:D

EXPLANATION

Attitudinal Surveys, Specific Assessments, Ability Tests, Structured Interviews, and Focus Groups are used as pre-assessment tools.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

28You are overseeing a project to build a robot which will operate on electricity as well as solar power. The robot should have face and voice recognition capability; it should help the owner with daily household activities and keep him or her company. The robot should be able to learn from various experiences, develop its memory, and gradually make more complex decisions on its own. In which of the following documents should this information be captured?
SELECT THE CORRECT ANSWER

Project scope

Scope baseline

Product scope

Requirements traceability matrix

A

Correct Option:C

EXPLANATION

Product scope describes the features, functions, and physical characteristics of a product, service, or result. On the other hand, project scope describes the work needed to deliver a product, service, or result with the specified features and functions. Product scope may include subsidiary components, but project scope results in a single product, service, or result. Product scope completion is measured against the product requirements to determine successful fulfillment. and project scope completion is measured against the project plan, project scope statement, work breakdown structure (WBS), WBS dictionary, and other elements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

42Which of the following assessments explores alternatives to overcome or avoid the risk?
SELECT THE CORRECT ANSWER

Backlog Assessment

Skill Gap Assessment

Risk Assessment

Team Assessment

A

Correct Option:A

EXPLANATION

Backlog Assessment or refinement explores alternatives to overcome or avoid the risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

45Which of the following tools is not used to measure team performance?
SELECT THE CORRECT ANSWER

Sprint

Kanban Board

Earned Value

Velocity

A

Correct Option:A

EXPLANATION

Kanban Boards, Throughput metrics, Cycle Time, Quality Metrics, Earned Value, Bar Charts, and Velocity are the various tools used to measure a team’s performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

52In Abraham Maslow’s Hierarchy of Needs, accomplishment, respect, attention, and appreciation are represented as:
SELECT THE CORRECT ANSWER

Physiological

Self-actualization

Esteem

Social

A

EXPLANATION

In Abraham Maslow’s Hierarchy of Needs, accomplishment, respect, attention, and appreciation are represented as esteem.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

57Which of the following is NOT an element of self-regulation?
SELECT THE CORRECT ANSWER

Self Control

Trustworthiness

Adaptability

Agility

A

Correct Option:D

EXPLANATION

Self Control, Trustworthiness, Conscientiousness, and Adaptability are self-regulation elements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

65Which of the following is NOT a tool and technique of the Perform Qualitative Risk Analysis process?
SELECT THE CORRECT ANSWER

Risk probability and impact assessment

Probability and impact matrix

Expected monetary value analysis

Risk data quality assessment

A

Correct Option:C

EXPLANATION

Perform Qualitative Risk Analysis is the process of prioritizing risks by assessing and combining their probability of occurrence and impact on the project if they occur. This fast, relatively easy to perform, and cost-effective process ensures that the right emphasis is on the right risk areas as per their ranking and priority and helps to allocate adequate time and resources. Even though numbers are used for the rating in Perform Qualitative Risk Analysis, it is a subjective evaluation and should be performed throughout the project. Perform Quantitative Risk Analysis is the process of numerically analyzing the effect of overall project objectives of identified risks. It performs numerical analysis using a modeling technique such as expected monetary value (EMV).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

66You are overseeing a large construction project to build a power plant. Your company has purchased a big piece of land close to a mountain and far away from the city for the plant. One of your team members reports to you that they found some artifacts during construction. Upon initial assessment, you realize these artifacts have some archaeological significance. What should you do in this kind of situation?
SELECT THE CORRECT ANSWER

Ask the team members to keep it a secret and collect all the artifacts for the benefit of the project.

This kind of finding is a norm in construction projects; thus, ignore the finding and proceed with the project as per the plan.

Proceed with the project as planned but inform the higher management about the findings.

Stop digging and call the archaeological department to quickly research the finding.

A

Correct Option:D

EXPLANATION

A project manager should understand the significance of this kind of finding and must consult the experts before proceeding further.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

78Which of the following is TRUE about the request for bid (RFB) or an invitation for bid (IFB)?
SELECT THE CORRECT ANSWER

Buyers request all potential sellers for the details of how work will be performed.

Buyers request all potential sellers to submit a total price bid for the work to be performed.

Buyers request all potential sellers to submit a price quote per item, hour, foot or other unit of measure.

Buyers request all potential sellers to submit a detailed statement of work from the buyer.

A

Correct Option:B

EXPLANATION

Invitation for bid (IFB)/request for bid (RFB): Request from a buyer to all potential sellers to submit a total price bid for work to be performed. Request for proposal (RFP): Buyer’s request to all potential sellers for the details of how work will be performed. Request for quotation (RFQ): Buyer’s request to all potential sellers for a price quote per item, hour, foot or other unit of measure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

81Which of the following processes documents configuration management activities in a project?
SELECT THE CORRECT ANSWER

Collect requirement

Define scope

Plan scope management

Validate scope

A

Correct Option:C

EXPLANATION

Requirements and configuration management activities are documented as a part of the requirements management plan, which is an output of the Plan Scope Management process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

90To improve the proficiency of team members, it is very essential to coach and mentor them regularly. Which of the following can help the project manager ensure the effectiveness of coaching and mentoring?
SELECT THE CORRECT ANSWER

Defining the communication management plan

Determining appropriate feedback

Dedication of the team members

Developing the ground rules

A

Correct Option:B

EXPLANATION

Regular feedback helps in understanding the effectiveness of the coaching and mentoring and helps initiate actions required to improve further.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
96Emotional Intelligence (EI) helps assess and understand the emotions of oneself and others so that conflicts are minimized. Besides, EI is used describe a key set of personal and interpersonal skills. What are the personal skills?
SELECT THE CORRECT ANSWER

Self-awareness, Self actualization

Self-Motivation, Self-Regulation, Self-actualization

Self-awareness, Self-Regulation, Motivation

Self-actualization, Motivation

A

Correct Option:C

EXPLANATION

EI recognizes the personal skills of Self-awareness, Self-Regulation, and Motivation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

121You have been managing a top-secret government project, which has been progressing as planned until recently. Suddenly, one of your team members calls and informs you that the project has encountered an unexpected major problem that was not included in the risk register. What should be your first course of action?
SELECT THE CORRECT ANSWER

Take corrective and preventive actions

Update the risk management plan

Create a workaround

Create a fallback plan

A

Correct Option:C

EXPLANATION

Since the problem has occurred, the first thing you should do as project manager is address the risk by creating a workaround. Once the issue is addressed, you may need to reevaluate your risk identification process, look for unexpected effects of the problem, inform management, update the risk management plan, create a fallback plan, and take corrective and preventative actions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

125For effective evaluation of virtual team engagement, a project manager defines the guidelines based on Project Management best practices. This involves tracking the progress, conducting daily stand-up meetings, using appropriate tools, and ___________.
SELECT THE CORRECT ANSWER

Retrospective

Timeboxing the meeting

Sprint Planning

Sprint Review

A

Correct Option:B

EXPLANATION

Timeboxing the meeting involves having a clear agenda, defining objectives and approach for the meeting, identification of attendees and action items, and adjourning the meeting promptly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

138Which of the following is NOT true about the goal and objective of a bidding conference?
SELECT THE CORRECT ANSWER

All questions are submitted in writing and issued to sellers as an addendum to the procurement document so that all sellers respond to the same scope of work.

There is no collusion among sellers and/or buying agents.

Sellers do not save questions for later private meetings in order to gain a competitive advantage.

The seller who is best capable of performing the project work is selected.

A

Correct Option:D

EXPLANATION

A bidder conference is an open dialogue dealing with questions and clarifications around an RFP. Selecting a seller is done through an internal process after proposals are submitted to the RFP.

17
Q

143Your team has estimated that there is a 40 percent probability of a delay in the receipt of required parts with an additional cost of $15,000 to the project. This delay will cost the company $20,000 in lost business. Upon further investigation, you identified that if an existing component could be adapted, it would save the project $10,500 in engineering costs. There is a 30 Percent probability that the team can take advantage of that opportunity. What is the total expected monetary value (EMV) of these two events?
SELECT THE CORRECT ANSWER

10850

-10850

14000

3150

A

Correct Option:B

EXPLANATION

EMV is a form of decision tree analysis used to select the best of several alternative courses of action. Each decision note has an input based on the cost and its probability, which produces an output. In this case, one of the branches of the decision tree would be a 40% chance of an $15,000 in additional costs and a resultant loss of $20,000 in revenue, so the total impact would be .4 * (-$15,000 + -$20,000) = -$14,000 . The other branch for the new component has $10,500 in cost savings, so the net effect is $10,500 * .3 = $3,150. We add the -$14,000 and the $3,1,50 to get the Expected Monetary Value of both decision tree paths, which equals -$10,850

18
Q

144You are overseeing a project to implement a payroll application and are currently in the Identify Risks process of identifying and documenting the projects risks. Which of the following information gathering techniques is NOT used in the Identify Risks process?
SELECT THE CORRECT ANSWER

Checklist analysis

The Delphi technique

Interviewing

Brainstorming

A

Correct Option:B

EXPLANATION

Delphi technique is not used in identify risk process. Delphi technique is a secret balloting typically used while gathering information. This can be used before unanimity under the voting technique while collecting requirements.

19
Q

149Which of the following statements is FALSE about qualified sellers list in a project?
SELECT THE CORRECT ANSWER

It is a list of preapproved or prequalified prospective sellers interested in and capable of doing contract services for the organization.

It is a part of the project management plan.

It is a list of prescreened sellers.

It is a tool in the Conduct Procurement process.

A

Correct Option:D

EXPLANATION

A qualified sellers list is a list of preapproved or prequalified prospective sellers interested in and capable of doing contract services for the organization. Prequalified sellers for a project are entered into the procurement management plan, which is a part of the project management plan, as an output of the plan Procurement process. The qualified seller list is used as an input in the Conduct Procurement process, not as a tool and technique.

20
Q

165When conflict occurs in a project, it has to be resolved following a specific approach based on the conflict type. Which of the following is NOT a conflict resolution technique?
SELECT THE CORRECT ANSWER

Collaborate

Accept

Compromise

Smooth

A

Correct Option:B

EXPLANATION

Collaborate, Compromise, Smooth, Force, and Withdraw are the conflict resolution techniques.

21
Q

175The constant contribution by team members results in the continual delivery of the project outputs and outcomes that compliment project objectives. Which of the following are important for making team members more proficient?
SELECT THE CORRECT ANSWER

Coaching and Mentoring

Collaboration and Controlling

Training and Evaluation

Communication and Controlling

A

Correct Option:A

EXPLANATION

Coaching and mentoring helps team members to become more proficient.