1

Standpipe risers must be painted what color to be in a state of readiness?

Red

2

When freezing conditions may be encountered what two conditions must standpipe systems meet?

Maintained as DRY and must have an air-pressurized alarm

3

How must the Fire Dept Connection be marked?

With a metal sign reading "Standpipe connection" and by a red light at night

4

Standpipe riser may be used by construction personnel for water or compressed air for construction site purposes under what condition?

Atleast one standpipe riser is maintained at all times for firefighting purposes