Contract Administration - Level 1 Flashcards

(61 cards)

1
Q

What standard forms of contract are you aware of?

A

Common standard forms include JCT, NEC, and FIDIC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the timescales involved with an extension of time request on a standard JCT contract?

A

Typically, the contractor must notify the CA within 14 days of the event causing delay.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Does an instruction need to have an agreed value contained within it?

A

No, an instruction does not need to have an agreed value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The contractor fails to complete the project by the completion date, what measures do the CA/EA take and what are the consequences of this?

A

The CA/EA may issue a non-completion certificate, which can lead to penalties for the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The CA/EA fails to issue a non-completion certificate on an over running project, what are the consequences of this?

A

The contractor may not face penalties or liquidated damages if no certificate is issued.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is your understanding of bespoke contract?

A

A bespoke contract is tailored specifically to the needs of the project and parties involved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What do you understand as the difference between a bespoke contract and standard form of contract?

A

Bespoke contracts are customized, while standard forms are pre-drafted and widely used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are your views on the advantages/disadvantages of using a bespoke contract?

A

Advantages include flexibility and specificity; disadvantages may include complexity and higher costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are your views on the advantages/disadvantages of using a standard form of contract?

A

Advantages include familiarity and efficiency; disadvantages may include lack of customization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When was the JCT contract suite last updated?

A

The JCT contract suite was last updated in 2016.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Tell me about some of the key changes that were made.

A

Key changes included updates to reflect legal and industry practices.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How was the JCT contract suite modernised through the last update?

A

The suite was modernised by incorporating clearer language and electronic processes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How does JCT facilitate electronic working?

A

JCT provides templates and guidelines for electronic document management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How does the JCT work alongside the Construction Playbook?

A

JCT aligns with the Construction Playbook by promoting best practices in procurement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How has the JCT contract suite incorporated diversity and inclusion?

A

The suite includes provisions to promote diversity and inclusion in procurement processes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the JCT Fluctuations Hub used for?

A

The JCT Fluctuations Hub is used to manage price fluctuations in contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Explain the JCT Target Cost Contract to me.

A

The JCT Target Cost Contract is designed to incentivize cost control and collaboration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What form of NEC contract might the Target Cost Contract be a good alternative for?

A

The Target Cost Contract might be a good alternative for the NEC form of contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What are the qualities of the NEC form of contract?

A

The NEC form of contract is known for flexibility, clarity, and a focus on collaboration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the advantages of the JCT form of contract?

A

The JCT form of contract offers clarity, familiarity, and a well-established framework.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What changes were last made to the NEC form of contract?

A

The last changes to the NEC form of contract included updates for clarity and efficiency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

When were these changes made?

A

These changes were made in 2021.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the difference between a Relevant Event and Relevant Matter?

A

A Relevant Event relates to delays caused by external factors, while a Relevant Matter pertains to issues affecting the contractor’s performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

If a non-completion certificate is not issued, what is the contractual effect?

A

If a non-completion certificate is not issued, the contractor may not be penalized for delays.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What guidance is there on contract administration?
Guidance on contract administration includes best practices for managing contracts and ensuring compliance.
26
What are the duties of a CA under JCT contracts?
The duties of a CA under JCT contracts include overseeing contract compliance and managing communications.
27
Do these duties include design?
No, the duties of a CA under JCT contracts do not typically include design responsibilities.
28
When authorising payment for goods or materials stored off site what must you obtain to protect your client in the event of the contractor going bankrupt?
You must obtain a legal charge or lien to protect your client.
29
If you are concerned that a contractor is in financial difficulties, name 3 things as CA you should do?
You should review the contractor's financial status, communicate concerns to the client, and consider withholding payments.
30
What key function does a contract administrator perform on a construction project?
A contract administrator manages the contract and ensures compliance with its terms.
31
Can you name three standard forms of contracts that can be used on a construction project?
Three standard forms of contracts are JCT, NEC, and FIDIC.
32
What insurance provisions are in the JCT and NEC standard forms of contract?
Both JCT and NEC contracts include provisions for public liability and employer's liability insurance.
33
What is loss insurance?
Loss insurance covers financial losses due to unforeseen events.
34
What is all risks insurance?
All risks insurance provides coverage for a wide range of potential damages and losses.
35
Where is the minimum financial cover for the contractor’s liability for injury, death and damages to property other than the works contained?
The minimum financial cover is typically contained within the contract documents.
36
What is a contractor’s all risk insurance or contract works insurance?
Contractor’s all risk insurance covers damage to the works and materials during construction.
37
What do you understand by insurance in joint names?
Insurance in joint names means that both the contractor and client are covered under the same policy.
38
What is a collateral warranty?
A collateral warranty is a contract that provides additional assurance to third parties.
39
What are the three ways that benefits can be transferred under JCT contracts?
Benefits can be transferred through assignment, novation, or collateral warranties.
40
Who might want a collateral warranty?
Clients, lenders, and other stakeholders may want a collateral warranty.
41
How are they requested?
Collateral warranties are typically requested in writing during contract negotiations.
42
What are the common clauses / terms in collateral warranties?
Common clauses include liability limits, duration, and rights of third parties.
43
What is the difference between a bond and a collateral warranty?
A bond is a financial guarantee, while a collateral warranty provides assurance of performance.
44
Are there any alternatives to collateral warranties?
Alternatives to collateral warranties include letters of intent and performance bonds.
45
What is your understanding of what a letter of intent is?
A letter of intent is a preliminary agreement outlining the intention to enter into a contract.
46
What are the advantages of a letter of intent?
Advantages include establishing commitment and allowing work to commence before the contract is finalized.
47
What are the disadvantages?
Disadvantages include potential legal ambiguity and lack of formal obligations.
48
In what circumstances might they be used?
Letters of intent might be used in urgent projects or when negotiations are ongoing.
49
What is their purpose?
The purpose is to signal intent and facilitate early project commencement.
50
Who issues it?
The client typically issues the letter of intent.
51
Who signs it?
The client and contractor sign the letter of intent.
52
What would you say if the client asked you to draft a letter of intent?
I would advise on the implications and ensure it clearly outlines the terms.
53
What is the final account (FA)?
The final account is a statement of the total costs incurred in a project.
54
What must the FA state?
The FA must state the final costs, adjustments, and any outstanding claims.
55
Who prepares the final account in a JCT form of contract?
The contractor prepares the final account in a JCT form of contract.
56
Who prepares the final account in the NEC4 form of contract?
The project manager prepares the final account in the NEC4 form of contract.
57
What is the purpose of a final account?
The purpose of a final account is to settle all financial matters related to the contract.
58
On the issue of the final account, what are the relevant time periods in a JCT form of contract?
The relevant time periods include submission deadlines and review periods.
59
When must the final certificate be issued?
The final certificate must be issued within a specified period after the final account is agreed.
60
Tell me two of the information or statements that must be contained in the final certificate.
The final certificate must contain the total amount due and confirmation of completion.
61
What are the usual constituents of a final account?
The usual constituents include a breakdown of costs, variations, and any claims.