Contract Administration - Level 1 Flashcards
(61 cards)
What standard forms of contract are you aware of?
Common standard forms include JCT, NEC, and FIDIC.
What are the timescales involved with an extension of time request on a standard JCT contract?
Typically, the contractor must notify the CA within 14 days of the event causing delay.
Does an instruction need to have an agreed value contained within it?
No, an instruction does not need to have an agreed value.
The contractor fails to complete the project by the completion date, what measures do the CA/EA take and what are the consequences of this?
The CA/EA may issue a non-completion certificate, which can lead to penalties for the contractor.
The CA/EA fails to issue a non-completion certificate on an over running project, what are the consequences of this?
The contractor may not face penalties or liquidated damages if no certificate is issued.
What is your understanding of bespoke contract?
A bespoke contract is tailored specifically to the needs of the project and parties involved.
What do you understand as the difference between a bespoke contract and standard form of contract?
Bespoke contracts are customized, while standard forms are pre-drafted and widely used.
What are your views on the advantages/disadvantages of using a bespoke contract?
Advantages include flexibility and specificity; disadvantages may include complexity and higher costs.
What are your views on the advantages/disadvantages of using a standard form of contract?
Advantages include familiarity and efficiency; disadvantages may include lack of customization.
When was the JCT contract suite last updated?
The JCT contract suite was last updated in 2016.
Tell me about some of the key changes that were made.
Key changes included updates to reflect legal and industry practices.
How was the JCT contract suite modernised through the last update?
The suite was modernised by incorporating clearer language and electronic processes.
How does JCT facilitate electronic working?
JCT provides templates and guidelines for electronic document management.
How does the JCT work alongside the Construction Playbook?
JCT aligns with the Construction Playbook by promoting best practices in procurement.
How has the JCT contract suite incorporated diversity and inclusion?
The suite includes provisions to promote diversity and inclusion in procurement processes.
What is the JCT Fluctuations Hub used for?
The JCT Fluctuations Hub is used to manage price fluctuations in contracts.
Explain the JCT Target Cost Contract to me.
The JCT Target Cost Contract is designed to incentivize cost control and collaboration.
What form of NEC contract might the Target Cost Contract be a good alternative for?
The Target Cost Contract might be a good alternative for the NEC form of contract.
What are the qualities of the NEC form of contract?
The NEC form of contract is known for flexibility, clarity, and a focus on collaboration.
What are the advantages of the JCT form of contract?
The JCT form of contract offers clarity, familiarity, and a well-established framework.
What changes were last made to the NEC form of contract?
The last changes to the NEC form of contract included updates for clarity and efficiency.
When were these changes made?
These changes were made in 2021.
What is the difference between a Relevant Event and Relevant Matter?
A Relevant Event relates to delays caused by external factors, while a Relevant Matter pertains to issues affecting the contractor’s performance.
If a non-completion certificate is not issued, what is the contractual effect?
If a non-completion certificate is not issued, the contractor may not be penalized for delays.