You say Wick Hall stage 3 cost plan was significantly over budget who created the budget did you get the budget wrong.
I took over this from another firm as the client was unhappy with their level of service
i believe there was so incorrect quantities and pricing but also the design team had developed the design and there was sufficient advise to rain the design back to the budget.
Once i came on board, it was evident the design was significantly over budget
Carried out VM and VE workshops and omitted pool building incorporated a new build home office into the existing building, reduced the landscaping scheme significantly this was something their gardener could do over a number of years.
On brock house what did you advise on the net to gross efficiency?
^85% originally it was to low and so wouldn’t give the return the client was looking for.
On Walbrook what were the provisional sums ?were these defined ?
Provisional quantities for areas we could not see entireley?
High level masonry repairs
lead roof repairs
If you were to do walbrook again how could you reduce provisional sums?
Start investigations and more earlier have a mute for higher places.
So what did you allow for cost per m2 for metsec external wall system?
£180/m2
Cost for concrete?
in region of £200 -£400 can vary on location if you are doing colums and beams higher up the building involves more work, additionally you need to allow for formwork and reinforcement for concrete separately as well.
Cost for concrete block wall
£20-£40 can vary again if it if fairfaced blockwork
Cost for steel ?
circa £4000/ ton