PMBOK Acronyms Flashcards

(60 cards)

1
Q

AC

A

actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

BAC

A

budget at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CCB

A

change control board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

COQ

A

cost of quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CPAF

A

cost plus award fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CPFF

A

cost plus fixed fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CPI

A

cost performance index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CPIF

A

cost plus incentive fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

CPM

A

critical path method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

CV

A

cost variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

EAC

A

estimate at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

EF

A

early finish date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

ES

A

early start date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

ETC

A

estimate to complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

EV

A

earned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

AC

A

actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

BAC

A

budget at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

CCB

A

change control board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

COQ

A

cost of quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

CPAF

A

cost plus award fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

CPFF

A

cost plus fixed fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

CPI

A

cost performance index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

CPIF

A

cost plus incentive fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

CPM

A

critical path method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
CV
cost variance
26
EAC
estimate at completion
27
EF
early finish date
28
ES
early start date
29
ETC
estimate to complete
30
EV
earned value
31
EVM
earned value management
32
FF
finish-to-finish
33
FFP
firm fixed price
34
FPEPA
fixed price with economic price adjustment
35
FPIF
fixed price incentive fee
36
FS
finish to start
37
IFB
invitation for bid
38
LF
late finish date
39
LOE
level of effort
40
LS
late start date
41
OBS
organizational breakdown structure
42
PDM
precedence diagramming method
43
PMBOK
Project Management Body of Knowledge
44
PV
planned value
45
QFD
quality function deployment
46
RACI
responsible, accountable, consult, and inform
47
RAM
responsibility assignment matrix
48
RBS
risk breakdown structure
49
RFI
request for information
50
RFP
request for proposal
51
RFQ
request for quotation
52
SF
start-to-finish
53
SOW
statement of work
54
SPI
schedule performance index
55
SS
start-to-start
56
SV
schedule variance
57
SWOT
strengths, weaknesses, opportunities, and threats
58
T&M
time and material contract”
59
VAC
variance at completion
60
WBS
work breakdown structure