Project Documents Flashcards

1
Q

Multiple attributes associated with each schedule activity that can be included within the activity list.

A

Activity Attributes

Activity attributes include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed

A

Activity List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A project document used to record all assumptions and constraints throughout the project life cycle.

A

Assumption Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

a document that identifies the logic, data, methodology and calculations used to estimate the resources required to perform a specific task or group of related tasks.

A

Basis of Estimate (BOE)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A comprehensive list of changes submitted during the project and their current status

A

Change Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

the approximation of the cost of a program, project, or operation.

A

cost estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

is a process you can use to adapt cost planning to constantly changing circumstances.

A

cost forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

the estimation of the amount of time required by a certain project activity given the available resources

A

Duration Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A project document where information about issues is recorded and monitored.

A

Issue Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A project document used to record knowledge gained during a project so that it can be used in the current project and entered into the lessons learned repository.

A

lessons learned register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

__________ list is a project management document that identifies all project milestone

A

milestone list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The documentation of the material, equipment, supplies, locations, and other physical resources that will be used during the project.

A

Physical resource assignments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A calendar that identifies working days and shifts that are available for scheduled activities. More than one may be required to allow for different work periods for some activities.
Created in:

Develop Schedule (P)
Updated in:
Develop Schedule (P)
Input to:
Control Schedule (M&C)
Part of:

Project documents

A

project calendar

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Documents such as performance reports, deliverable status, schedule progress, cost incurred, presentations, and other information required by stakeholders.

Created in:

Manage Communications (E)
Updated in:
Manage Communications (E)
Input to:

Direct and Manage Project Work (E)
Monitor Communications (M&C)
Monitor Stakeholder Engagement (M&C)
Close Project or Phase (C)

A

project communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

An output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources.

A

project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A graphical representation of the logical relationships among the project schedule activities

A

Project Schedule Network Diagram

17
Q

The description of the project scope, major deliverables, assumptions, and constraints

A

Project Scope Statement

18
Q

Documentation recording the team members and their roles and responsibilities for the project.

A

project team assignments

19
Q

The documented results of control quality activities.

A

Quality Control Measurements

20
Q

are used to directly translate customer needs into acceptable performance measures in both products and processes

A

Quality Metrics

21
Q

A project document that includes quality management issues, recommendations for corrective actions, and a summary of findings from quality control activities and may include recommendations for process, project, and product improvements.

A

Quality Report

22
Q

A description of how individual requirements meet the business need for the project

A

Requirements Documentation

23
Q

A grid that links product requirements from their origin to the deliverables that satisfy them.

A

Requirements Traceability Matrix

24
Q

A hierarchical representation of resources by category and type.

A

resource breakdown structure

25
A calendar that identifies the working days and shifts upon which each specific resource is available.
Resource Calendar
26
The types and quantities of resources required for each activity in a work package.
Resource Requirements
27
A repository in which outputs of risk management processes are recorded
Risk Register
28
A project document developed progressively throughout the Project Risk Management processes, which summarizes information on individual project risks and the level of overall project risk.
Risk Report
29
The collection of information for describing and controlling the schedule.
Schedule Data
30
Estimates or predictions of conditions and events in the project’s future based on information and knowledge available at the time the schedule is calculated.
Schedule Forecasts
31
A project document including the identification, assessment, and classification of project stakeholders.
Stakeholder Register
32
A document that records the team values, agreements, and operating guidelines, as well as establishing clear expectations regarding acceptable behavior by project team members.
Team Charter
33
Project documents that describe the activities used to determine if the product meets the quality objectives stated in the quality management plan.
Test and Evaluation Documents