Program Planning 2 Flashcards

(17 cards)

1
Q

To foster unity across teams, a _______ ________ is created to ensure a shared language for the program.

A

Program Glossary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A _______ _______ is established to resolve conflicts and align decisions across multiple teams.

A

Steering committee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The _______ matrix is maintained throughout the program lifecycle to clarify roles and responsibilities.

A

RACI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In the _______ framework, risks with low impact or likelihood are acknowledged but not acted upon.

A

ROAM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When a team member leaves, the _______ process involves deciding whether to replace them or redistribute their tasks.

A

Offboarding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The _______ _______ _______ consolidates all project timelines to analyse the impacts of schedule shifts.

A

Integrated program schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A _______ _______ _______ evaluates scope change requests to ensure alignment with program objectives.

A

Change review board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

To prevent mistrust and silos, programs should foster a culture of _______ by adopting a share-everything mindset.

A

Transparency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

For GlobeBank’s program, _______ was chosen as the methodology for software development, with training provided to non-technical teams.

A

Agile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The _______ _______ tracks system uptime, data accuracy, and IT productivity to measure program success.

A

real-time dashboards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

During program planning, _______ _______ ensures all impacted groups, including HQ and local branches, are involved early.

A

Stakeholder engagement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A _______ _______ prevents delays from cascading across teams by monitoring internal and external factors.

A

dependencies tracker

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The _______ _______ _______ approves budget adjustments to maintain financial control in the program.

A

Executive sign off

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

To avoid confusion, _______ assignments are predefined before interviewing or hiring replacements during onboarding.

A

RACI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What does ROAM stand for?

A

Resolve
Own
Accept
Mitigate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What does RAID stand for?

A

Risks
Assumptions
Issues
Dependencies

16
Q

What does RAID Mean

A

A method used to identify & manage potential problems that could impact a project’s success