Flashcards in Trim Deck (21):
1

Why is it important to coordinate your daily schedule to meet trim package deliveries?

so that you can audit the load and check for damaged material

2

what form should be filled out if material is damaged on the lumber load?

SDR Site Delivery Report

3

how is miscellaneous material ordered in your area?

Thurmont customer service

4

what stage should your house be in prior to the trim package delivery?

Drywall and garage door should be in.

5

how do you handle damaged and missing materials

Audit load and fill out SDR

6

what is a coping saw and what is it used for?

Saw used to coy or shape the end of a piece of molding so that it will cover and fit the contour of the trim piece.

7

Chair Rail

dining rooms 1/3 of the wall height

8

Brick mold

trim used on exterior doors

9

Crown molding

Trim installed at the top of the wall, where it meets the ceiling

10

shoe mold

quarter round trim that is placed where tile/hardwood meet base board

11

Casing

Trim that is used around doorways and windows

12

what is a shim?

fills voids in framing

13

what does 2/6 mean?

2' 6" door 2'6" opening and 6'8" height

14

what is the rough opening of a 2/6 door?

2'8" opening and 6'11" height

15

describe where we use a privacy lock

bathrooms, bedrooms

16

describe where we use a passage lock

closets, pantries, laundry room

17

what is a rail bolt and describe where it is used

holds rail to knoll post

18

T/F: Casing miters should be nailed, not glued

false: glued, not nailed

19

List 5 things shown on the blueprints that pertain to the trim carpenter

cabinet location, door size, door swing, Ogee at stairs, eased openings, appliance location, attic access standard detail.

20

T/F: the trim carpenter is responsible for interior door adjustments for 1 year

True

21

what is the purpose of a casing wedge?

Holds Mitres together