Methods of measuring works progression
Visiting site at regular intervals and checking works against the contractors programme. Reporting back to the client on progress
How is quality measured/assessed within contracts
- drawings and specification which set the quality standards
- Method statements
- Certificates for compliance
- Defects Liability Period
is a programme required under a JCT contract
Not a contractual requirement, but a plays a vital role in managing the works. Helps to assess progress, EOT
What is a flashing
It’s a thin, protective material, typically metal, installed at joints, edges, and penetrations to direct water away from vulnerable areas
Where was the flashing installed on the flat roof
Where the flat roof met with the adjoining building
Types of progress reports
Frequency: Weekly or monthly
Type: Formal report or email
Explain the defect at York
Internally wall wasn’t tied in and so the internal linings were being strupped this apperead undecure.
How are variations dealt with under a JCT minor works contract
Instruction must be issued by CA and approval will need to be obtained prior to proceeding
Assess in timescales implications on EOT
Was their any queries that highlighted within the inspection at Shrewsbury
- Strip oyt of tile cills
- Bi folding internal door (Keep in)
How did you ensure the strip out works at shrewsbru was completed
- Checked the works at completion with client and ensured all items had been completed as intended.