Q

Meaning of:
PBS
WBS
CBS

A

PBS - product breakdown structure
WBS - Work breakdown structure
CBS - Cost breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the critical path

A

A sequence of activities through a precedence network from start to finish, whose sum of durations are the total duration of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is critical chain

A

A resource-based approach to scheduling, protecting critical chain activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

List 3 benefits of re-estimating

A
  1. Greater involvement of project team
  2. Incorporate lessons learnt
  3. Realisation of accepted risk