21. Change Control Flashcards
1
Q
List 3 reasons why change control is important
A
- Manages all requests to change from baseline
- Understand impact
- Consequences of unmanaged change can impact BAU and project
2
Q
List 6 steps to change control process
A
- Change request - enter on log
- Initial evaluation - is it worth evaluating
- Detailed evaluation - impact to time, cost, quality, benefits
- Recommendation - approve, reject, defer
- update plans
- implement