15. Resource Management Flashcards

1
Q

List considerations in resource management

A
  • life cycle approach
  • tasks to be completed
  • skill set and capability
  • timeframe
  • BAU vs Project
  • Possible external resources
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Describe RAM or RACI

A

RAM - responsibility assignment matrix

RACI - Responsible, Accountable, Consulted, Informed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

List 2 resource categories

A

Consumable
Reusable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Describe difference in resource allocation between linear and iterative

A

Linear:
- duration fixed based on estimates
- extra work justified via change control
- priorities pre-agreed
- sponsor approves scope change

Iterative:
- extra work prioritised to fit into time bar
- duration diced and scope flexed to fit
- priorities are set while project in motion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Describe resource smoothing and levelling

A

Smoothing: utilising float in activity to increase/decrease the resource required (maintains end date)

Levelling: delays activities so resource usage is kept below specified limits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly