4. Reviews Flashcards
(8 cards)
Describe decision gate
A point between phases used to review and confirm viability of the work in line with the business case
Describe benefits review
review after a period of operations of the proejct deliverables. Establish extent of benefits realised (typically 6-12months after handover)
Describe audit
A means to provide assurance and give confidence to sponsor project is being managed as expected and agreed
Describe 4 reporting principles in a review
C - Clear
A - Accurate
R - Relevant
T- Timely
Describe 5 factors to include in review reports
- Time
- Risk
- Scope
- Cost
- Benefit
Other - Progress, audit findings, earned values, actual spend
Describe 4 stages of reporting cycle
Gather data –> collate & analyse –> create info –> make decisions
What is the importance of gather information and reporting
- Status reporting
- Estimating the project
- Risk identification
- Knowledge and information management
- Availability of information
Provide 5 reasons for replanning following a review
- planned scope is not required
- low team motivation
- poor contractor performance
- committed costs and cashflow higher than expected
- changes to risk